Research package · Transmission · Partly verified

Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan

What federal records show about U.S. high-voltage line building, how it compares with China, and what ERCOT's 765-kV plan could mean for Texas. Eleven charts, every number sourced, and what is still open.

By Power Hopper Team · Research draft v4 prepared November 17, 2026; published November 17, 2026

Download CSV Download JSON

The short version

U.S. builders added far less new high-voltage line after 2013 than before it. China added many times more over 2019 to 2023, though how many times depends on how the two countries' numbers are matched. In Texas, ERCOT has picked a 765-kilovolt (kV) backbone it estimates will cost about $2.2 billion more to build than a 345-kV alternative, and a national study recommends about 14,100 megawatts of new power transfer capability into ERCOT. A Power Hopper estimate puts the plan at roughly $7 to $19 a month in added transmission charges for an ERCOT home.

4,195 miU.S. new 345 kV+ line in 2013, the peak year
10 to 21xChina vs U.S. line additions, 2019-2023, by definition
$32.99BERCOT 765-kV plan estimate; 345-kV plan $30.75B
14,100 MWNERC-recommended new import capability into ERCOT

Reading guide. A kilovolt (kV) measures how much electrical pressure a line carries; higher is more power over longer distances. "345 kV and higher" lines are the long-distance backbone. Every number on this page links to its source in the list of all 64 numbers, each marked verified, partly verified, derived or estimate. Two items are still under review: the legal reading of the Senate bill in section 7 and a federal cost estimate for it; both are marked below.

1. U.S. high-voltage line building slowed after 2013

The Federal Energy Regulatory Commission (FERC) publishes an Energy Infrastructure Update that counts miles of new transmission line at 345 kV and above. Every December edition from 2010 through 2025 was read, and each year uses the latest figure FERC published.

Chart 1 of 11 · verified against FERC documents

U.S. high-voltage line additions peaked in 2013 and have run far lower since

Miles of new transmission line at 345 kilovolts or higher completed each year, using the latest FERC figure for each year. 2017 covers January to November only; 2025 is a first estimate.

Source: FERC Energy Infrastructure Updates. Status: verified against FERC documents. Data file: us-345kv-plus-latest-ferc-2009-2025.csv.

Chart: U.S. high-voltage line additions peaked in 2013 and have run far lower since · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "U.S. high-voltage line additions peaked in 2013 and have run far lower since." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-01-us-345kv-transmission-line-miles-ferc-2009-2025. Accessed [date accessed].

Data table
U.S. high-voltage line additions peaked in 2013 and have run far lower since
yearkv345plus_latest_milatest_editionfirst_estimate_mifirst_editionstatussource_url
2009819.8Dec 2010latest FERC editionhttps://web.archive.org/web/20120512023309id_/http://ferc.gov/legal/staff-reports/12-10-energy-infrastructure.pdf
20101060.3Dec 2011740.5Dec 2010latest FERC editionhttps://web.archive.org/web/20120512023746id_/http://ferc.gov/legal/staff-reports/12-11-energy-infrastructure.pdf
2011778.5Dec 2012490.2Dec 2011latest FERC editionhttps://web.archive.org/web/20130216161213id_/http://www.ferc.gov/legal/staff-reports/dec-2012-energy-infrastructure.pdf
20121299.8Dec 2013962.9Dec 2012latest FERC editionhttps://web.archive.org/web/20140210113437id_/http://ferc.gov/legal/staff-reports/2013/dec-energy-infrastructure.pdf
20134194.5Dec 20142975.5Dec 2013latest FERC editionhttps://web.archive.org/web/20150209022700id_/http://www.ferc.gov:80/legal/staff-reports/2014/dec-infrastructure.pdf
20141729.8Dec 20151489.8Dec 2014latest FERC editionhttps://web.archive.org/web/20160212114521id_/http://ferc.gov:80/legal/staff-reports/2015/dec-infrastructure.pdf
20151585.5Dec 20161197.3Dec 2015latest FERC editionhttps://web.archive.org/web/20170213220551id_/https://www.ferc.gov/legal/staff-reports/2016/dec-energy-infrastructure.pdf
20161050.9Dec 2017369.9Dec 2016latest FERC editionhttps://web.archive.org/web/20180510111252id_/https://www.ferc.gov/legal/staff-reports/2017/dec-energy-infrastructure.pdf
2017363.1Nov 2018154.5Dec 2017Jan-Nov onlyhttps://web.archive.org/web/20190119164731id_/https://ferc.gov/legal/staff-reports/2018/nov-energy-infrastructure.pdf
2018916.6Dec 2019latest FERC editionhttps://web.archive.org/web/2021id_/https://www.ferc.gov/sites/default/files/2020-04/dec-energy-infrastructure.pdf
2019612.2Dec 2020 (rev. 9-28-2022)469.2Dec 2019latest FERC editionhttps://www.ferc.gov/sites/default/files/2022-09/DecemberMIR%202020%20%28Revised%209-28-2022%29.pdf
2020904.2Dec 2021797.6Dec 2020 (rev. 9-28-2022)latest FERC editionhttps://www.ferc.gov/sites/default/files/2022-03/DecemberMIR%202021.pdf
2021566.6Dec 202292.1Dec 2021latest FERC editionhttps://www.ferc.gov/sites/default/files/2023-02/DecemberMIR%202022.pdf
2022198.0Dec 2023198.0Dec 2022latest FERC editionhttps://www.ferc.gov/sites/default/files/2024-02/December%20MIR%202023.pdf
202359.5Dec 2024 (rev. 4-22-2025)55.5Dec 2023latest FERC editionhttps://www.ferc.gov/sites/default/files/2025-04/DecemberMIR2024Revised-4-22-2025.pdf
2024906.1Dec 2025275.5Dec 2024latest FERC editionhttps://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx
2025402.6Dec 2025402.6Dec 2025first estimate onlyhttps://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx

FERC's first estimate for a year is often revised upward. Across 13 years the median latest-to-first ratio is 1.35, so recent years may rise.

Chart 2 of 11 · verified against FERC documents

FERC's first count of a year's new high-voltage lines is often revised up

FERC's first count of a year's new lines (open circle) compared with the latest edition (filled). The median revision is up by a factor of 1.35.

Source: FERC Energy Infrastructure Updates. Status: verified against FERC documents. Data file: us-345kv-plus-latest-ferc-2009-2025.csv.

Chart: FERC's first count of a year's new high-voltage lines is often revised up · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "FERC's first count of a year's new high-voltage lines is often revised up." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-02-ferc-first-vs-revised-transmission-miles. Accessed [date accessed].

Data table
FERC's first count of a year's new high-voltage lines is often revised up
yearkv345plus_latest_milatest_editionfirst_estimate_mifirst_editionstatussource_url
2009819.8Dec 2010latest FERC editionhttps://web.archive.org/web/20120512023309id_/http://ferc.gov/legal/staff-reports/12-10-energy-infrastructure.pdf
20101060.3Dec 2011740.5Dec 2010latest FERC editionhttps://web.archive.org/web/20120512023746id_/http://ferc.gov/legal/staff-reports/12-11-energy-infrastructure.pdf
2011778.5Dec 2012490.2Dec 2011latest FERC editionhttps://web.archive.org/web/20130216161213id_/http://www.ferc.gov/legal/staff-reports/dec-2012-energy-infrastructure.pdf
20121299.8Dec 2013962.9Dec 2012latest FERC editionhttps://web.archive.org/web/20140210113437id_/http://ferc.gov/legal/staff-reports/2013/dec-energy-infrastructure.pdf
20134194.5Dec 20142975.5Dec 2013latest FERC editionhttps://web.archive.org/web/20150209022700id_/http://www.ferc.gov:80/legal/staff-reports/2014/dec-infrastructure.pdf
20141729.8Dec 20151489.8Dec 2014latest FERC editionhttps://web.archive.org/web/20160212114521id_/http://ferc.gov:80/legal/staff-reports/2015/dec-infrastructure.pdf
20151585.5Dec 20161197.3Dec 2015latest FERC editionhttps://web.archive.org/web/20170213220551id_/https://www.ferc.gov/legal/staff-reports/2016/dec-energy-infrastructure.pdf
20161050.9Dec 2017369.9Dec 2016latest FERC editionhttps://web.archive.org/web/20180510111252id_/https://www.ferc.gov/legal/staff-reports/2017/dec-energy-infrastructure.pdf
2017363.1Nov 2018154.5Dec 2017Jan-Nov onlyhttps://web.archive.org/web/20190119164731id_/https://ferc.gov/legal/staff-reports/2018/nov-energy-infrastructure.pdf
2018916.6Dec 2019latest FERC editionhttps://web.archive.org/web/2021id_/https://www.ferc.gov/sites/default/files/2020-04/dec-energy-infrastructure.pdf
2019612.2Dec 2020 (rev. 9-28-2022)469.2Dec 2019latest FERC editionhttps://www.ferc.gov/sites/default/files/2022-09/DecemberMIR%202020%20%28Revised%209-28-2022%29.pdf
2020904.2Dec 2021797.6Dec 2020 (rev. 9-28-2022)latest FERC editionhttps://www.ferc.gov/sites/default/files/2022-03/DecemberMIR%202021.pdf
2021566.6Dec 202292.1Dec 2021latest FERC editionhttps://www.ferc.gov/sites/default/files/2023-02/DecemberMIR%202022.pdf
2022198.0Dec 2023198.0Dec 2022latest FERC editionhttps://www.ferc.gov/sites/default/files/2024-02/December%20MIR%202023.pdf
202359.5Dec 2024 (rev. 4-22-2025)55.5Dec 2023latest FERC editionhttps://www.ferc.gov/sites/default/files/2025-04/DecemberMIR2024Revised-4-22-2025.pdf
2024906.1Dec 2025275.5Dec 2024latest FERC editionhttps://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx
2025402.6Dec 2025402.6Dec 2025first estimate onlyhttps://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx

About 2023. A July 2025 addendum from Americans for a Clean Energy Grid puts 2023 at roughly 400 miles at 345 kV plus about 50 at 500 kV. That figure does not appear in any FERC table that was read, and a November 2026 Grid Strategies report notes that 2023 rose only about four miles across a year of FERC updates. A second federal source, FERC Form 1 filings (investor-owned utilities only, including rebuilds), lists 553 miles "added or altered" in 2023. All three are shown; none is chosen.

Chart 11 of 11 · partially verified

Two federal data sets disagree on how many U.S. high-voltage miles were added

Miles of new 345-kV-plus line per year: FERC infrastructure updates (all owners; 2025 is a first estimate) against FERC Form 1 filings (investor-owned utilities, lines added or altered).

Source: FERC EIU (verified); Form 1 via PUDL (carried from v3). Status: partially verified (Form 1 series not re-pulled). Data file: us-ferc-vs-form1-2009-2025.csv.

Chart: Two federal data sets disagree on how many U.S. high-voltage miles were added · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "Two federal data sets disagree on how many U.S. high-voltage miles were added." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-11-ferc-infrastructure-updates-vs-form1-transmission-miles. Accessed [date accessed].

Data table
Two federal data sets disagree on how many U.S. high-voltage miles were added
yearferc_eiu_latest_miform1_p424_iou_added_or_altered_mi
2009819.8420.8
20101060.3785.1
2011778.5815.1
20121299.81185.5
20134194.52068.0
20141729.81793.7
20151585.52093.0
20161050.91095.3
2017363.1618.3
2018916.61404.5
2019612.2681.4
2020904.21494.8
2021566.6554.3
2022198.0371.6
202359.5553.0
2024906.1797.8
2025402.61047.5

2. China versus the U.S.: a range, not one number

China's 2024 Electric Power Industry Yearbook (China Electricity Council, Table 4-24) reports new lines by voltage. From 2019 through 2023, new alternating-current lines at 330 kV and above plus all direct-current lines averaged 15,619 km, about 9,705 miles, a year. FERC's U.S. 345 kV-plus figure averaged about 468 miles a year over the same years. Compared directly, that is about 20.7 to 1, but the comparison is not like-for-like:

Chart 3 of 11 · verified

China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023

Miles of new line per year. China: 330 kV and above, including direct-current lines. U.S.: 345 kV and above. The two countries' length measures are not the same.

Source: CEC Yearbook 2024 Table 4-24; FERC EIUs. Status: verified (China table read from page image; U.S. from FERC); ratio is unharmonized. Data file: china-us-annual-2019-2023.csv.

Chart: China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023 · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-03-china-vs-us-high-voltage-line-additions-2019-2023. Accessed [date accessed].

Data table
China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023
yearchina_330kv_plus_incl_dc_mius_ferc_345kv_plus_miratio
20199998612.216.3
202010103904.211.2
20219154566.616.2
20229244198.046.7
20231002659.5168.5

Chart 4 of 11 · derived

Change the definitions and the China-U.S. gap ranges from about 10 to 21 times

Ratio of China's average yearly additions to the U.S. figure, 2019 to 2023, under five definitions. No single like-for-like ratio can be built from public data.

Source: Derived from verified inputs. Status: derived; no single like-for-like ratio is possible. Data file: china-us-ratio-sensitivity-2019-2023.csv.

Chart: Change the definitions and the China-U.S. gap ranges from about 10 to 21 times · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "Change the definitions and the China-U.S. gap ranges from about 10 to 21 times." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-04-china-us-transmission-ratio-sensitivity. Accessed [date accessed].

Data table
Change the definitions and the China-U.S. gap ranges from about 10 to 21 times
casechina_mi_yrus_mi_yrratiobasis
A. Published figures: China 330 kV+ (incl. DC) vs U.S. FERC 345 kV+ (latest editions)9705468.120.7closest published thresholds; length bases not harmonized
B. China 500 kV+ (incl. DC) vs U.S. FERC 345 kV+8633468.118.4drops China 330 kV class
C. As A, but U.S. 2023 = ~450 mi (ACEG addendum figure, not found in any FERC table)9705546.217.8sensitivity only
D. As A, but U.S. = FERC Form 1 p.424 investor-owned utilities, lines added or altered9705731.013.3Form 1 counts rebuilds; IOUs only (PUDL republication)
E. As A, with China halved (illustrative bound if every new km were a double circuit counted twice)4853468.110.4hypothetical bound; actual double-circuit share not published

Conclusion: across five definitions, China built roughly 10 to 21 times as much high-voltage line as the U.S. from 2019 to 2023. A single like-for-like ratio cannot be built from public data.

3. Timelines: compared at one shared milestone

Projects were compared from final approval to energization. For China, 13 ultra-high-voltage direct-current lines took a median of 2.0 years from national approval to full service. For the U.S., 12 energized projects in Power Hopper's ledger took a median of 3.3 years from their last major approval; the spread is wide, and Champlain Hudson took 11.6 years. These samples are small and not representative, and 8 of the 12 U.S. dates are low-confidence. They show only that both countries take years of the same order after approval; much of the U.S. delay in the ledger comes earlier, in planning, siting and permitting. No cause is claimed.

Chart 5 of 11 · partially verified

After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3

Years from final approval to energization. Each dot is one line; the diamond is the median. Hollow U.S. dots rest on low-confidence dates. Small samples, descriptive only.

Source: Power Hopper ledgers (v3), re-cut on matched milestones. Status: partially verified; samples not representative; descriptive only. Data file: matched-approval-to-service-us-china.csv.

Chart: After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3 · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-05-approval-to-energization-us-vs-china-transmission. Accessed [date accessed].

Data table
After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3
countryprojectapproval_dateapproval_milestoneservice_dateyearsconfidenceincluded
United StatesSunZia2023-05-19BLM Record of Decision #22026-06-183.08mediumyes
United StatesGateway South2016-12-16BLM Record of Decision (NOA)2024-12-017.96highyes
United StatesTen West Link2021-09-23CPUC grants CPCN (month)2024-05-012.6lowyes
United StatesCardinal-Hickory Creek2020-01-17RUS Record of Decision2024-09-264.69mediumyes
United StatesChamplain Hudson Power Express2014-10-01DOE ROD / Presidential Permit2026-05-1311.61mediumyes
United StatesNew England Clean Energy Connect2021-01-14DOE Presidential Permit2026-01-165.0lowyes
United StatesSusquehanna-Roseland2012-10-17NPS Record of Decision (Delaware Water Gap crossing)2015-05-012.54lowyes
United StatesTrAIL (Trans-Allegheny Interstate Line)2008-12-01PA PUC approval, last state (month)2011-05-012.41lowyes
United StatesSunrise Powerlink2009-01-20BLM ROD (NOA in FR 2009-02-20)2012-06-183.41lowyes
United StatesTehachapi Renewable Transmission2009-12-17CPUC CPCN2016-12-157.0lowyes
United StatesCapX2020 Hampton-Rochester-La Crosse2012-05-30Wisconsin PSC CPCN (month)2015-09-013.26lowyes
United StatesBadger-Coulee2016-04-14Wisconsin PSC approval (month)2018-12-012.63lowyes
United StatesTexas CREZ (345 kV program)no dated approval in ledger2014-01-01no
United StatesBig Stone South-Ellendaleno dated approval in ledger2019-02-01no
United StatesOne Nevada (ON Line)no dated approval in ledger2013-12-31no
ChinaYunnan–Guangdong (Chuxiong–Suidong)2006-12NDRC approval (hezhun)2010-06-183.51document/media sourceyes
ChinaXiangjiaba–Shanghai (Fulong–Fengxian)2007-04-26NDRC approval (hezhun)2010-07-083.2document/media sourceyes
ChinaJinping–Southern Jiangsu2008-11NDRC approval (hezhun)2012-12-124.07document/media sourceyes
ChinaHami South–Zhengzhou2012-05NDRC approval (hezhun)2014-01-271.7document/media sourceyes
ChinaXiluodu–Zhejiang (Yibin–Jinhua)2012-07-06NDRC approval (hezhun)2014-07-031.99document/media sourceyes
ChinaNuozhadu–Guangdong2011-07NDRC approval (hezhun)2015-06document/media sourceno (date not verified)
ChinaNingdong–Zhejiang (Lingzhou–Shaoxing)2014-08NDRC approval (hezhun)2016-08-24document/media sourceno (date not verified)
ChinaJiuquan–Hunan (Qilian–Shaoshan)2015-05NDRC approval (hezhun)2017-06-22document/media sourceno (date not verified)
ChinaNorthern Shanxi–Nanjing (Yanmen–Huai'an)2015-06NDRC approval (hezhun)2017-06-302.04search-excerpt sourceyes
ChinaXilingol–Taizhou2015-10NDRC approval (hezhun)2017-09-301.96document/media sourceyes
ChinaJarud–Qingzhou2016-08-16NDRC approval (hezhun)2017-12-311.37document/media sourceyes
ChinaShanghaimiao–Linyi2015-12-01NDRC approval (hezhun)2019-01-11document/media sourceno (date not verified)
ChinaChangji–Guquan (Zhundong–Southern Anhui)2015-12-28NDRC approval (hezhun)2019-09-263.75document/media sourceyes
ChinaQinghai–Henan2018-10NDRC approval (hezhun)2020-12-30document/media sourceno (date not verified)
ChinaKunbei–Liuzhou–Longmen 3-terminal hybrid (LCC/VSC)2018-03-29NDRC approval (hezhun)2020-12-27document/media sourceno (date not verified)
ChinaNorthwest Yunnan–Guangdong (Xinsong–Dongfang)2015-12-28NDRC approval (hezhun)2018-05-18search-excerpt sourceno (date not verified)
ChinaYazhong–Jiangxi (Ya'an–Nanchang)2019-08-23NDRC approval (hezhun)2021-06-211.83search-excerpt sourceyes
ChinaNorthern Shaanxi–Wuhan2019-01NDRC approval (hezhun)2022-04-163.25document/media sourceyes
ChinaBaihetan–Jiangsu2020-11-03NDRC approval (hezhun)2022-07-01document/media sourceno (date not verified)
ChinaBaihetan–Zhejiang2021-07NDRC approval (hezhun)2022-12-301.46document/media sourceyes
ChinaLongdong–Shandong2023-02-27NDRC approval (hezhun)2025-05-08document/media sourceno (date not verified)
ChinaHami–Chongqing2023-07NDRC approval (hezhun)2025-12-04document/media sourceno (date not verified)
ChinaNingxia–Hunan2023-05-24NDRC approval (hezhun)2025-10-082.38search-excerpt sourceyes
ChinaUpper Jinsha–HubeiNDRC approval (hezhun)2025-12-18search-excerpt sourceno (date not verified)

4. ERCOT's 765-kV plan: what the $32.99 billion and $229 million mean

ERCOT's Permian Basin and Eastern 765-kV "STEP" Core Plan is estimated to cost $32.99 billion to build; the 345-kV alternative ERCOT studied is estimated at $30.75 billion. The difference is $2.24 billion, or about $1.35 billion after ERCOT's adjustments for outages and upgrades. The 765-kV plan needs about 3,441 miles of new right-of-way and 2,831 miles of upgrades, cuts annual system losses by about 5% (around 560 GWh) compared with the 345-kV plan, and raises the West Texas export stability limit from 12.7 GW to 16.2 GW. ERCOT says either plan implies roughly $5 billion a year of transmission investment.

Chart 6 of 11 · verified against ERCOT documents

ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan

ERCOT's estimated construction cost of two statewide transmission plans, in billions of dollars. These are generic cost estimates.

Source: ERCOT Trending Topic Dec 2025; ERCOT 25RPG022 review. Status: verified against ERCOT documents.

Chart: ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-06-ercot-765kv-vs-345kv-plan-construction-cost. Accessed [date accessed].

Data table
ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan
PlanEstimated construction cost, billions of dollars
345-kV plan30.75
765-kV STEP Core Plan32.99
Difference (before ERCOT's outage and upgrade adjustment)2.24
Difference after adjustment1.35

The widely quoted $229 million is a model result for one study year, 2039: the extra reduction in system-wide consumer energy cost from the 765-kV plan compared with the 345-kV plan, not compared with building nothing. In 2034, ERCOT's model shows the 765-kV plan $136 million less favorable than the 345-kV plan. The first approved segment, Drill Hole-Sand Lake-Solstice, is a $742.2 million, 104.4-mile project with a summer 2030 in-service date.

Chart 7 of 11 · verified against ERCOT document

In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year

Change in modeled yearly system-wide consumer energy cost savings, 765-kV plan minus 345-kV plan, in millions of 2025 dollars.

Source: ERCOT 25RPG022 independent review. Status: verified against ERCOT document.

Chart: In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-07-ercot-765kv-modeled-consumer-energy-cost-2034-2039. Accessed [date accessed].

Data table
In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year
Study year765-kV plan minus 345-kV plan, millions of 2025 dollars a year
2034-136 (345-kV plan saves more)
2039+229 (765-kV plan saves more)

5. Reliability and room to grow

The North American Electric Reliability Corporation's Interregional Transfer Capability Study found that in its 2033 case ERCOT had 135 hours of energy deficiency, with a maximum shortfall of 18,926 MW, and puts ERCOT's current modeled import limit at 820 MW. As "prudent additions" it recommends about 14,100 MW of new transfer capability into ERCOT: 5,700 MW from the Front Range, 4,300 MW from MISO-South and 4,100 MW from SPP-South, about 40% of the 35,000 MW it recommends nationwide. These are study recommendations; the study "does not prescribe how" to build them, and none has been approved.

Chart 8 of 11 · verified against NERC report

NERC's study recommends about 14,100 MW of new import capability for ERCOT

NERC's recommended "prudent additions" of transfer capability into ERCOT, in megawatts (2033 study case). These are study recommendations, not approved projects.

Source: NERC ITCS Final Report (Nov 2024). Status: verified against NERC report.

Chart: NERC's study recommends about 14,100 MW of new import capability for ERCOT · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "NERC's study recommends about 14,100 MW of new import capability for ERCOT." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-08-nerc-itcs-ercot-import-capability-recommendation. Accessed [date accessed].

Data table
NERC's study recommends about 14,100 MW of new import capability for ERCOT
Source of added import capabilityMegawatts
From Front Range (West)5,700
From MISO South4,300
From SPP South4,100
Total recommended for ERCOT14,100
Modeled import limit today820

For context, during Winter Storm Uri in February 2021 ERCOT's direct-current ties could import at most about 1,220 MW while firm load shed peaked near 20,000 MW. Those two figures were carried from the FERC-NERC report and not re-checked for this package.

6. What it could mean for a home's bill (Power Hopper estimate)

ERCOT does not publish a per-household figure, so Power Hopper built a transparent estimate. It assumes all $32.99 billion enters rates at a yearly carrying-charge rate of 8%, 11% or 14% (Power Hopper's assumption), and spreads the cost using 2025 transmission cost allocation data from PUCT Docket 59080 and each utility's residential rate factor.

Estimated added monthly transmission charge for a home (Power Hopper estimate)
Utility areaAt today's load (8% / 11% / 14%)If ERCOT peak load grows to 111.3 GWExtra over the 345-kV plan (central)
Oncor$9.51 / $13.08 / $16.64$6.91 / $9.50 / $12.09about $0.89
CenterPoint$10.80 / $14.85 / $18.90$7.85 / $10.79 / $13.74about $1.01

Chart 9 of 11 · estimate

Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges

A Power Hopper estimate, not an ERCOT or utility forecast. The full $32.99 billion plan in rates: bars show an 8% to 14% yearly carrying charge, the dot 11%.

Source: Power Hopper model; inputs from PUCT, ERCOT, EIA. Status: estimate; inputs verified except carrying-charge rate (assumption) and EIA customer counts (carried from v3). Data file: household-transmission-charge-estimate.csv.

Chart: Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-09-household-transmission-charge-estimate-ercot-765kv-plan. Accessed [date accessed].

Data table
Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges
scenariotdufcr_low_8pctfcr_central_11pctfcr_high_14pctincremental_vs_345kv_plan_centralnote
Today's load (2025 4CP 80.9 GW)Oncor9.5113.0816.640.894CP and TDU shares from PUCT Docket 59080 Matrix B
Today's load (2025 4CP 80.9 GW)CenterPoint10.814.8518.91.014CP and TDU shares from PUCT Docket 59080 Matrix B
Load grows to 111.3 GW (ERCOT 2032 forecast)Oncor6.919.512.090.65same TDU share and residential customers assumed; illustrative
Load grows to 111.3 GW (ERCOT 2032 forecast)CenterPoint7.8510.7913.740.73same TDU share and residential customers assumed; illustrative

This is Power Hopper's estimate, not an ERCOT or PUCT figure. It ignores any energy-cost savings, timing, depreciation and the mix of retail plans. The carrying-charge rate is an assumption, and the customer counts come from an earlier draft. The calculation is in household-transmission-charge-estimate.csv.

7. What the Senate bill would do

Under review. The facts below are as of 6:45 a.m. CT on Nov. 17, 2026. Their legal effect has not been reviewed by counsel, and the cost estimate was seen only through congress.gov and a republication. A check of the Senate roll-call list later on Nov. 17 showed no vote after number 264. This is research, not legal advice.

The amendment text, as printed in the Congressional Record, includes: Section 2101, which revises FERC's "backstop" siting authority to cover lines of at least 230 kV and adds a new subsection 216(k)(1) saying the section "shall not apply within the area referred to in section 212(k)(2)(A)," which is the ERCOT area. Section 2103 adds a recurring Department of Energy transmission study and planning provisions with a similar ERCOT exclusion in new section 225(b)(1). Section 2201 ("Accelerating Claims") sets a 150-day window for court challenges to federal authorizations. How the ERCOT exclusions would apply in practice, including to the ties NERC recommends, is a question for counsel.

Jobs claim. A senator said on the floor on Nov. 9 that the bill "is estimated to create over 100,000 jobs." No model was cited, and it is not stated whether the figure counts jobs or job-years. For scale, 100,000 is about 40% of the 251,549 people employed in U.S. power and communication line construction in 2025 (BLS, NAICS 237130); Texas accounted for 36,957.

8. Cost per mile

FERC Form 1 filings, as compiled by the PUDL project, give a median reported cost for long (20 miles or more) 345 kV-plus lines in 2025 dollars: about $1.5 million a mile in 2001 to 2008 (20 lines), about $2.0 million in 2009 to 2016 (84 lines) and about $2.0 million in 2017 to 2025 (70 lines). Filed costs may be partial, and these figures do not show whether costs rose. No claim is made about why U.S. and Chinese prices differ.

Chart 10 of 11 · partially verified

Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009

Median reported cost per mile of lines at 345 kV or higher and 20 miles or longer, in millions of 2025 dollars. Bar = median; whisker = middle half.

Source: FERC Form 1 p.424 via PUDL. Status: partially verified (PUDL republication of FERC filings; not re-pulled in v4). Data file: form1-cost-per-mile-by-period.csv.

Chart: Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009 · Methodology for Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · Dataset: Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan · CC BY 4.0

Cite this chart

Power Hopper Team. "Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-10-us-345kv-transmission-cost-per-mile-form1. Accessed [date accessed].

Data table
Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009
periodn_linesmedian_musd_per_mile_2025p25p75sourcecaveat
2001-2008201.540.522.32FERC Form 1 p.424 via PUDL (data.catalyst.coop); lines >=345 kV and >=20 mi; CPI-U to 2025 $filed cost may be partial; excludes <$0.1M/mi; IOUs only; not a test of whether costs rose
2009-2016842.041.02.77FERC Form 1 p.424 via PUDL (data.catalyst.coop); lines >=345 kV and >=20 mi; CPI-U to 2025 $filed cost may be partial; excludes <$0.1M/mi; IOUs only; not a test of whether costs rose
2017-2025702.011.252.82FERC Form 1 p.424 via PUDL (data.catalyst.coop); lines >=345 kV and >=20 mi; CPI-U to 2025 $filed cost may be partial; excludes <$0.1M/mi; IOUs only; not a test of whether costs rose

All 64 numbers, with sources and status

"Verified" means the figure was read in the primary document on Nov. 17, 2026. "Partially verified", "carried from an earlier draft", "derived", "assumption" and "estimate" are marked as such.

Show the full table
All 64 numbers used in this package
IDNumberValueStatusSource
US-01U.S. new 345 kV+ line, 2013 (peak year)4194.5 milesverified (primary document read 2026-11-17)source
US-02U.S. new 345 kV+ line, 2023 (latest FERC edition)59.5 milesverified (primary document read 2026-11-17)source
US-03U.S. new 345 kV+ line, 2024 (latest FERC edition)906.1 milesverified (primary document read 2026-11-17); may still be revisedsource
US-04U.S. new 345 kV+ line, 2024 (FERC first estimate)275.5 milesverified (primary document read 2026-11-17)source
US-05U.S. new 345 kV+ line, 2024 (FERC Apr 2025 interim revision)888.5 milesverified (primary document read 2026-11-17)source
US-06U.S. new 345 kV+ line, 2025 (FERC first estimate)402.6 milesverified (primary document read 2026-11-17); first estimatesource
US-07U.S. average yearly 345 kV+ additions, 2019-2023468.1 miles/yrderived from verified inputsdata/us_345kv_plus_latest_ferc_2009_2025.csv
US-08U.S. average yearly 345 kV+ additions, 2009-20161564.9 miles/yrderived from verified inputsdata/us_345kv_plus_latest_ferc_2009_2025.csv
US-09U.S. average yearly 345 kV+ additions, 2017-2025 (2017 Jan-Nov; 2025 first estimate)547.7 miles/yrderived from verified inputsdata/us_345kv_plus_latest_ferc_2009_2025.csv
US-10Median ratio of latest to first FERC estimate, 13 years 2010-20241.35 ratioderived (v3 said 1.4)data/us_345kv_plus_latest_ferc_2009_2025.csv
US-11U.S. 2023 per ACEG July 2025 addendum (~400 at 345 kV + ~50 at 500 kV)450 milesNOT FOUND in FERC tables: Apr 2025 EIU has no 2023 column; Dec 2024 edition and its Apr 2025 revision show 59.5source
US-12Grid Strategies (Nov 2026): 2023 data rose only about four miles across a year of FERC updates4 milessecondary; consistent with FERC 55.5 -> 59.5source
US-13FERC Form 1 p.424 345 kV+ lines added or altered, 2023 (investor-owned utilities)553.0 milespartially verified (carried from v3; not re-pulled)source
CN-01China new lines 330 kV+ AC plus all DC, average 2019-202315619 km/yrverified (table read from page image)source
CN-02Same, in miles9705 miles/yrderived from verified inputssource
CN-03China new lines 500 kV+ AC plus all DC, average 2019-20238633 miles/yrderived from verified inputssource
CN-04China AC 330 kV+ circuit-length stock increase 2019-2023 (Table 3-15) vs additions 2020-2023 (Table 4-24)52282 vs 50374 kmderived; indicates additions are on a circuit-length basis (not proof)source
R-01China/U.S. ratio, published figures 2019-2023 (330 kV+ vs 345 kV+)20.7 ratioderived; not like-for-likedata/china_us_ratio_sensitivity_2019_2023.csv
R-02China/U.S. ratio range across five definitions10.4-20.7 ratioderived; sensitivitydata/china_us_ratio_sensitivity_2019_2023.csv
T-01China UHV DC: median years, NDRC approval to full service (n=13)2.04 yearspartially verified (3 of 13 rely on a search-excerpt source)data/matched_approval_to_service_us_china.csv
T-02U.S. ledger: median years, final approval to energization (n=12)3.33 yearspartially verified (8 of 12 rely on a low-confidence date)data/matched_approval_to_service_us_china.csv
E-01ERCOT 765-kV STEP Core Plan construction cost estimate32.99 USD billionverified (primary document read 2026-11-17)source
E-02ERCOT 345-kV plan construction cost estimate30.75 USD billionverified (primary document read 2026-11-17)source
E-03Cost difference, 765 vs 345 (and after outage/upgrade adjustment)2.24 (1.35) USD billionverified (primary document read 2026-11-17)source
E-04765 vs 345: added system-wide consumer energy cost reduction, study year 2039229 USD million/yr (2025$)verified (primary document read 2026-11-17); model result, not net savings vs no new linessource
E-05765 vs 345: consumer energy cost savings, study year 2034-136 USD million/yr (2025$)verified (primary document read 2026-11-17)source
E-06STEP Core Plan new right-of-way / existing line upgrades 3441 / 2831 milesverified (primary document read 2026-11-17)source
E-07STEP Core Plan reduction in annual systemwide losses vs 345-kV plan~5% (~560 GWh) share / GWhverified (primary document read 2026-11-17)source
E-08West Texas Export stability limit, before/after STEP12.7 -> 16.2 GWverified (primary document read 2026-11-17)source
E-09ERCOT 2030 summer peak forecast used in planning>150 GWverified (primary document read 2026-11-17); forecastsource
E-10Drill Hole-Sand Lake-Solstice 765-kV project cost / new ROW / in-service742.2 / 104.4 / Summer 2030 USD million / miles / dateverified (primary document read 2026-11-17)source
E-11Annual transmission investment needed under either plan (6-yr horizon)5 USD billion/yrverified (primary document read 2026-11-17)source
N-01NERC prudent additions into ERCOT: Front Range / MISO-S / SPP-S5700 / 4300 / 4100 MWverified (primary document read 2026-11-17); study recommendationsource
N-02NERC prudent additions into ERCOT, total14100 MWverified (primary document read 2026-11-17); study recommendationsource
N-03NERC prudent additions, U.S. total35000 MWverified (primary document read 2026-11-17)source
N-04ERCOT current modeled import limit (ITCS)820 MWverified (primary document read 2026-11-17)source
N-05ERCOT energy-deficiency hours / max deficiency, 2033 case135 / 18,926 hours / MWverified (primary document read 2026-11-17)source
N-06ERCOT maximum DC-tie import capability during Winter Storm Uri1220 MWcarried from v3; not re-opened in v4source
N-07ERCOT firm load shed at peak, Winter Storm Uri20000 MWcarried from v3; not re-opened in v4source
J-01U.S. power and communication line construction employment (NAICS 237130, private), 2025251549 jobsverified (primary document read 2026-11-17)source
J-02Texas, same industry, 202536957 jobsverified (primary document read 2026-11-17)source
J-03"over 100,000 jobs" as share of J-0139.8 percentderived; the claim's unit (jobs vs job-years, direct vs total) is not statedsee source detail
J-04Floor statement: bill "is estimated to create over 100,000 jobs"quote verified (primary document read 2026-11-17) (quote); underlying estimate not citedsource
L-01S.Amdt. 6883 (BAAJA substitute) proposed to H.R. 23472026-11-10 dateverified (primary document read 2026-11-17)source
L-02Senate vote 257: cloture on motion to proceed to H.R. 234773-25 votesverified (primary document read 2026-11-17)source
L-03Senate vote 258: motion to proceed62-21 votesverified (primary document read 2026-11-17)source
L-04Senate vote 264: cloture on S.Amdt. 6883 (Nov 16 2026, 5:27 PM CT)70-27 votesverified (primary document read 2026-11-17)source
L-05Latest official action as of 2026-11-17 06:40 CT2026-11-16 Considered by Senate statusverified (primary document read 2026-11-17); no adoption or passage vote recorded yetsource
L-06CBO/JCT preliminary estimate: deficit increase, 2027-2036<1 USD billionpartially verified: letter existence/date verified via congress.gov API; wording via Benton.org republication (cbo.gov blocked automated access)source
L-07SA 6883 Sec. 2101(i): new FPA 216(k)(1) "This section shall not apply within the area referred to in section 212(k)(2)(A)" (ERCOT)text verified (primary document read 2026-11-17); legal effect needs counselsource
L-08SA 6883 Sec. 2103: new FPA 225(b)(1) ERCOT exclusion and planning-region exclusiontext verified (primary document read 2026-11-17); legal effect needs counselsource
L-09SA 6883 Sec. 2101(b): FERC backstop eligibility includes facilities of not less than 230 kV; state 1-year clock runs from state filing datetext verified (primary document read 2026-11-17); legal effect needs counselsource
B-01ERCOT total TCOS (2026 matrix)6055.6 USD million/yrverified (primary document read 2026-11-17)source
B-02ERCOT average 4CP, 202580874 MWverified (primary document read 2026-11-17)source
B-03Oncor / CenterPoint average 4CP, 202528677 / 20180 MWverified (primary document read 2026-11-17)source
B-04Oncor Rider TCRF residential allocation factor42.407 percentverified (primary document read 2026-11-17)source
B-05CenterPoint Rider TCRF residential allocation factor48.9238 percentverified (primary document read 2026-11-17)source
B-06Oncor / CenterPoint residential customers, 20243477215 / 2485470 customerscarried from v3; not re-downloaded in v4source
B-07Annual carrying-charge rate (levelized revenue requirement / capital)8-14 (central 11) percentASSUMPTION; needs utility-specific checksee source detail
B-08Estimated added monthly transmission charge, Oncor home, full STEP in rates, today's load9.51-16.64 (central 13.08) USD/monthPower Hopper ESTIMATE, not ERCOTdata/household_transmission_charge_estimate.csv
B-09Same, CenterPoint home10.80-18.90 (central 14.85) USD/monthPower Hopper ESTIMATEdata/household_transmission_charge_estimate.csv
B-10Same, Oncor home, if ERCOT 4CP grows to 111.3 GW and new load absorbs the added share6.91-12.09 (central 9.50) USD/monthPower Hopper ESTIMATE; 111.3 GW forecast carried from v3 (ERCOT CEO update Apr 2026)data/household_transmission_charge_estimate.csv
B-11Incremental cost of 765 plan vs 345 plan, Oncor home (central)0.89 USD/monthPower Hopper ESTIMATEdata/household_transmission_charge_estimate.csv
C-01Median filed cost per mile, 345 kV+ lines >=20 mi, 2001-08 / 2009-16 / 2017-25 (2025$)1.54 / 2.04 / 2.01 USD million/milepartially verified (PUDL republication; not re-pulled in v4)source

What is still open

Downloads

Key numbers with sources (CSV) · Key numbers (JSON) · Chart manifest (CSV) · Earlier-draft chart review (CSV) · Source link check, Nov 17 (CSV) · China cec new lines by voltage 2019 2023 (CSV) · China circuit vs route check (CSV) · China us annual 2019 2023 (CSV) · China us ratio sensitivity 2019 2023 (CSV) · Ferc eiu 345kv plus all editions 2009 2025 (CSV) · Form1 cost per mile by period (CSV) · Household transmission charge estimate (CSV) · Matched approval to service us china (CSV) · Us 345kv plus latest ferc 2009 2025 (CSV) · Us ferc vs form1 2009 2025 (CSV) · SHA-256 checksums

Notes and limits

Scope. U.S. 345 kV-plus line additions 2009 to 2025 (FERC Energy Infrastructure Updates, every December edition 2010 to 2025), China's new lines 2019 to 2023 (China Electricity Council yearbook), approval-to-energization timelines, ERCOT's 765-kV plan (ERCOT and its independent review), NERC's interregional transfer study, a Power Hopper household-cost estimate, and the status of the Senate's BAAJA as of Nov. 17, 2026.

Verification. Each number is marked verified (read in the primary document on Nov. 17, 2026), partially verified, derived, assumption or estimate in key-numbers.csv. The 98 source links were checked on Nov. 17: 81 opened, 10 returned 403 because of bot protection (content confirmed through an API, the Congressional Record or the underlying file), six Chinese hosts refuse this network, and one returned 401. Those 17 need a manual browser check.

Comparisons. China-U.S. ratios are shown across five definitions because lengths are not measured the same way; no like-for-like ratio is claimed. Timeline medians are descriptive and rest on small samples. No cause is claimed for any difference between countries.

Estimates. The household figure is a Power Hopper estimate: capital cost times an assumed 8% to 14% carrying charge, allocated with PUCT Docket 59080 data. It is not an ERCOT, PUCT or utility forecast and ignores savings and timing.

Not included. Primary source documents (FERC, ERCOT, NERC, PUCT and BLS files) and rebuild scripts are not hosted here; each number links to its source. Legal effect of the Senate bill has not been reviewed by counsel. This is research, not legal advice.

Power Hopper is not affiliated with or endorsed by FERC, ERCOT, NERC, the PUCT, the U.S. Senate, the Congressional Budget Office, the China Electricity Council, or any other agency or organization named here.

Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility. This brief was prepared with AI assistance.