Research package · Transmission · Partly verified
Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan
What federal records show about U.S. high-voltage line building, how it compares with China, and what ERCOT's 765-kV plan could mean for Texas. Eleven charts, every number sourced, and what is still open.
By Power Hopper Team · Research draft v4 prepared November 17, 2026; published November 17, 2026
The short version
U.S. builders added far less new high-voltage line after 2013 than before it. China added many times more over 2019 to 2023, though how many times depends on how the two countries' numbers are matched. In Texas, ERCOT has picked a 765-kilovolt (kV) backbone it estimates will cost about $2.2 billion more to build than a 345-kV alternative, and a national study recommends about 14,100 megawatts of new power transfer capability into ERCOT. A Power Hopper estimate puts the plan at roughly $7 to $19 a month in added transmission charges for an ERCOT home.
Reading guide. A kilovolt (kV) measures how much electrical pressure a line carries; higher is more power over longer distances. "345 kV and higher" lines are the long-distance backbone. Every number on this page links to its source in the list of all 64 numbers, each marked verified, partly verified, derived or estimate. Two items are still under review: the legal reading of the Senate bill in section 7 and a federal cost estimate for it; both are marked below.
1. U.S. high-voltage line building slowed after 2013
The Federal Energy Regulatory Commission (FERC) publishes an Energy Infrastructure Update that counts miles of new transmission line at 345 kV and above. Every December edition from 2010 through 2025 was read, and each year uses the latest figure FERC published.
- Peak: 4,194.5 miles in 2013.
- 2009 to 2016: about 1,565 miles a year on average. 2017 to 2025: about 548 miles a year (2017 is January to November only; 2025 is a first estimate).
- Lowest recent year: 2023 at 59.5 miles in FERC's latest table (first estimate 55.5). 2024 was 906.1 miles; 2025 is 402.6 miles (first estimate).
Chart 1 of 11 · verified against FERC documents
U.S. high-voltage line additions peaked in 2013 and have run far lower since
Miles of new transmission line at 345 kilovolts or higher completed each year, using the latest FERC figure for each year. 2017 covers January to November only; 2025 is a first estimate.

Download PNG of U.S. high-voltage line additions peaked in 2013 and have run far lower since WEBP of U.S. high-voltage line additions peaked in 2013 and have run far lower since SVG of U.S. high-voltage line additions peaked in 2013 and have run far lower since
Source: FERC Energy Infrastructure Updates. Status: verified against FERC documents. Data file: us-345kv-plus-latest-ferc-2009-2025.csv.
Cite this chart
Power Hopper Team. "U.S. high-voltage line additions peaked in 2013 and have run far lower since." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-01-us-345kv-transmission-line-miles-ferc-2009-2025. Accessed [date accessed].
Data table
| year | kv345plus_latest_mi | latest_edition | first_estimate_mi | first_edition | status | source_url |
|---|---|---|---|---|---|---|
| 2009 | 819.8 | Dec 2010 | latest FERC edition | https://web.archive.org/web/20120512023309id_/http://ferc.gov/legal/staff-reports/12-10-energy-infrastructure.pdf | ||
| 2010 | 1060.3 | Dec 2011 | 740.5 | Dec 2010 | latest FERC edition | https://web.archive.org/web/20120512023746id_/http://ferc.gov/legal/staff-reports/12-11-energy-infrastructure.pdf |
| 2011 | 778.5 | Dec 2012 | 490.2 | Dec 2011 | latest FERC edition | https://web.archive.org/web/20130216161213id_/http://www.ferc.gov/legal/staff-reports/dec-2012-energy-infrastructure.pdf |
| 2012 | 1299.8 | Dec 2013 | 962.9 | Dec 2012 | latest FERC edition | https://web.archive.org/web/20140210113437id_/http://ferc.gov/legal/staff-reports/2013/dec-energy-infrastructure.pdf |
| 2013 | 4194.5 | Dec 2014 | 2975.5 | Dec 2013 | latest FERC edition | https://web.archive.org/web/20150209022700id_/http://www.ferc.gov:80/legal/staff-reports/2014/dec-infrastructure.pdf |
| 2014 | 1729.8 | Dec 2015 | 1489.8 | Dec 2014 | latest FERC edition | https://web.archive.org/web/20160212114521id_/http://ferc.gov:80/legal/staff-reports/2015/dec-infrastructure.pdf |
| 2015 | 1585.5 | Dec 2016 | 1197.3 | Dec 2015 | latest FERC edition | https://web.archive.org/web/20170213220551id_/https://www.ferc.gov/legal/staff-reports/2016/dec-energy-infrastructure.pdf |
| 2016 | 1050.9 | Dec 2017 | 369.9 | Dec 2016 | latest FERC edition | https://web.archive.org/web/20180510111252id_/https://www.ferc.gov/legal/staff-reports/2017/dec-energy-infrastructure.pdf |
| 2017 | 363.1 | Nov 2018 | 154.5 | Dec 2017 | Jan-Nov only | https://web.archive.org/web/20190119164731id_/https://ferc.gov/legal/staff-reports/2018/nov-energy-infrastructure.pdf |
| 2018 | 916.6 | Dec 2019 | latest FERC edition | https://web.archive.org/web/2021id_/https://www.ferc.gov/sites/default/files/2020-04/dec-energy-infrastructure.pdf | ||
| 2019 | 612.2 | Dec 2020 (rev. 9-28-2022) | 469.2 | Dec 2019 | latest FERC edition | https://www.ferc.gov/sites/default/files/2022-09/DecemberMIR%202020%20%28Revised%209-28-2022%29.pdf |
| 2020 | 904.2 | Dec 2021 | 797.6 | Dec 2020 (rev. 9-28-2022) | latest FERC edition | https://www.ferc.gov/sites/default/files/2022-03/DecemberMIR%202021.pdf |
| 2021 | 566.6 | Dec 2022 | 92.1 | Dec 2021 | latest FERC edition | https://www.ferc.gov/sites/default/files/2023-02/DecemberMIR%202022.pdf |
| 2022 | 198.0 | Dec 2023 | 198.0 | Dec 2022 | latest FERC edition | https://www.ferc.gov/sites/default/files/2024-02/December%20MIR%202023.pdf |
| 2023 | 59.5 | Dec 2024 (rev. 4-22-2025) | 55.5 | Dec 2023 | latest FERC edition | https://www.ferc.gov/sites/default/files/2025-04/DecemberMIR2024Revised-4-22-2025.pdf |
| 2024 | 906.1 | Dec 2025 | 275.5 | Dec 2024 | latest FERC edition | https://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx |
| 2025 | 402.6 | Dec 2025 | 402.6 | Dec 2025 | first estimate only | https://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx |
FERC's first estimate for a year is often revised upward. Across 13 years the median latest-to-first ratio is 1.35, so recent years may rise.
Chart 2 of 11 · verified against FERC documents
FERC's first count of a year's new high-voltage lines is often revised up
FERC's first count of a year's new lines (open circle) compared with the latest edition (filled). The median revision is up by a factor of 1.35.

Download PNG of FERC's first count of a year's new high-voltage lines is often revised up WEBP of FERC's first count of a year's new high-voltage lines is often revised up SVG of FERC's first count of a year's new high-voltage lines is often revised up
Source: FERC Energy Infrastructure Updates. Status: verified against FERC documents. Data file: us-345kv-plus-latest-ferc-2009-2025.csv.
Cite this chart
Power Hopper Team. "FERC's first count of a year's new high-voltage lines is often revised up." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-02-ferc-first-vs-revised-transmission-miles. Accessed [date accessed].
Data table
| year | kv345plus_latest_mi | latest_edition | first_estimate_mi | first_edition | status | source_url |
|---|---|---|---|---|---|---|
| 2009 | 819.8 | Dec 2010 | latest FERC edition | https://web.archive.org/web/20120512023309id_/http://ferc.gov/legal/staff-reports/12-10-energy-infrastructure.pdf | ||
| 2010 | 1060.3 | Dec 2011 | 740.5 | Dec 2010 | latest FERC edition | https://web.archive.org/web/20120512023746id_/http://ferc.gov/legal/staff-reports/12-11-energy-infrastructure.pdf |
| 2011 | 778.5 | Dec 2012 | 490.2 | Dec 2011 | latest FERC edition | https://web.archive.org/web/20130216161213id_/http://www.ferc.gov/legal/staff-reports/dec-2012-energy-infrastructure.pdf |
| 2012 | 1299.8 | Dec 2013 | 962.9 | Dec 2012 | latest FERC edition | https://web.archive.org/web/20140210113437id_/http://ferc.gov/legal/staff-reports/2013/dec-energy-infrastructure.pdf |
| 2013 | 4194.5 | Dec 2014 | 2975.5 | Dec 2013 | latest FERC edition | https://web.archive.org/web/20150209022700id_/http://www.ferc.gov:80/legal/staff-reports/2014/dec-infrastructure.pdf |
| 2014 | 1729.8 | Dec 2015 | 1489.8 | Dec 2014 | latest FERC edition | https://web.archive.org/web/20160212114521id_/http://ferc.gov:80/legal/staff-reports/2015/dec-infrastructure.pdf |
| 2015 | 1585.5 | Dec 2016 | 1197.3 | Dec 2015 | latest FERC edition | https://web.archive.org/web/20170213220551id_/https://www.ferc.gov/legal/staff-reports/2016/dec-energy-infrastructure.pdf |
| 2016 | 1050.9 | Dec 2017 | 369.9 | Dec 2016 | latest FERC edition | https://web.archive.org/web/20180510111252id_/https://www.ferc.gov/legal/staff-reports/2017/dec-energy-infrastructure.pdf |
| 2017 | 363.1 | Nov 2018 | 154.5 | Dec 2017 | Jan-Nov only | https://web.archive.org/web/20190119164731id_/https://ferc.gov/legal/staff-reports/2018/nov-energy-infrastructure.pdf |
| 2018 | 916.6 | Dec 2019 | latest FERC edition | https://web.archive.org/web/2021id_/https://www.ferc.gov/sites/default/files/2020-04/dec-energy-infrastructure.pdf | ||
| 2019 | 612.2 | Dec 2020 (rev. 9-28-2022) | 469.2 | Dec 2019 | latest FERC edition | https://www.ferc.gov/sites/default/files/2022-09/DecemberMIR%202020%20%28Revised%209-28-2022%29.pdf |
| 2020 | 904.2 | Dec 2021 | 797.6 | Dec 2020 (rev. 9-28-2022) | latest FERC edition | https://www.ferc.gov/sites/default/files/2022-03/DecemberMIR%202021.pdf |
| 2021 | 566.6 | Dec 2022 | 92.1 | Dec 2021 | latest FERC edition | https://www.ferc.gov/sites/default/files/2023-02/DecemberMIR%202022.pdf |
| 2022 | 198.0 | Dec 2023 | 198.0 | Dec 2022 | latest FERC edition | https://www.ferc.gov/sites/default/files/2024-02/December%20MIR%202023.pdf |
| 2023 | 59.5 | Dec 2024 (rev. 4-22-2025) | 55.5 | Dec 2023 | latest FERC edition | https://www.ferc.gov/sites/default/files/2025-04/DecemberMIR2024Revised-4-22-2025.pdf |
| 2024 | 906.1 | Dec 2025 | 275.5 | Dec 2024 | latest FERC edition | https://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx |
| 2025 | 402.6 | Dec 2025 | 402.6 | Dec 2025 | first estimate only | https://www.ferc.gov/sites/default/files/2026-03/December%20MIR%202025.docx |
About 2023. A July 2025 addendum from Americans for a Clean Energy Grid puts 2023 at roughly 400 miles at 345 kV plus about 50 at 500 kV. That figure does not appear in any FERC table that was read, and a November 2026 Grid Strategies report notes that 2023 rose only about four miles across a year of FERC updates. A second federal source, FERC Form 1 filings (investor-owned utilities only, including rebuilds), lists 553 miles "added or altered" in 2023. All three are shown; none is chosen.
Chart 11 of 11 · partially verified
Two federal data sets disagree on how many U.S. high-voltage miles were added
Miles of new 345-kV-plus line per year: FERC infrastructure updates (all owners; 2025 is a first estimate) against FERC Form 1 filings (investor-owned utilities, lines added or altered).

Download PNG of Two federal data sets disagree on how many U.S. high-voltage miles were added WEBP of Two federal data sets disagree on how many U.S. high-voltage miles were added SVG of Two federal data sets disagree on how many U.S. high-voltage miles were added
Source: FERC EIU (verified); Form 1 via PUDL (carried from v3). Status: partially verified (Form 1 series not re-pulled). Data file: us-ferc-vs-form1-2009-2025.csv.
Cite this chart
Power Hopper Team. "Two federal data sets disagree on how many U.S. high-voltage miles were added." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-11-ferc-infrastructure-updates-vs-form1-transmission-miles. Accessed [date accessed].
Data table
| year | ferc_eiu_latest_mi | form1_p424_iou_added_or_altered_mi |
|---|---|---|
| 2009 | 819.8 | 420.8 |
| 2010 | 1060.3 | 785.1 |
| 2011 | 778.5 | 815.1 |
| 2012 | 1299.8 | 1185.5 |
| 2013 | 4194.5 | 2068.0 |
| 2014 | 1729.8 | 1793.7 |
| 2015 | 1585.5 | 2093.0 |
| 2016 | 1050.9 | 1095.3 |
| 2017 | 363.1 | 618.3 |
| 2018 | 916.6 | 1404.5 |
| 2019 | 612.2 | 681.4 |
| 2020 | 904.2 | 1494.8 |
| 2021 | 566.6 | 554.3 |
| 2022 | 198.0 | 371.6 |
| 2023 | 59.5 | 553.0 |
| 2024 | 906.1 | 797.8 |
| 2025 | 402.6 | 1047.5 |
2. China versus the U.S.: a range, not one number
China's 2024 Electric Power Industry Yearbook (China Electricity Council, Table 4-24) reports new lines by voltage. From 2019 through 2023, new alternating-current lines at 330 kV and above plus all direct-current lines averaged 15,619 km, about 9,705 miles, a year. FERC's U.S. 345 kV-plus figure averaged about 468 miles a year over the same years. Compared directly, that is about 20.7 to 1, but the comparison is not like-for-like:
- Voltage thresholds differ (330 kV against 345 kV). Counting only China's 500 kV-and-up lines gives 18.4.
- The length basis is unclear. China's additions closely match the year-to-year change in its circuit-length stock, which suggests circuit-kilometres, so a double-circuit line may count twice. If every Chinese kilometre were double-counted the ratio would fall to about 10.4, which is a bound, not an estimate.
- The U.S. figure is itself uncertain. Using the 2023 figure from the advocacy addendum gives 17.8; using FERC Form 1 gives 13.3.
Chart 3 of 11 · verified
China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023
Miles of new line per year. China: 330 kV and above, including direct-current lines. U.S.: 345 kV and above. The two countries' length measures are not the same.

Download PNG of China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023 WEBP of China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023 SVG of China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023
Source: CEC Yearbook 2024 Table 4-24; FERC EIUs. Status: verified (China table read from page image; U.S. from FERC); ratio is unharmonized. Data file: china-us-annual-2019-2023.csv.
Cite this chart
Power Hopper Team. "China's published high-voltage additions ran about 20 times U.S. additions, 2019-2023." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-03-china-vs-us-high-voltage-line-additions-2019-2023. Accessed [date accessed].
Data table
| year | china_330kv_plus_incl_dc_mi | us_ferc_345kv_plus_mi | ratio |
|---|---|---|---|
| 2019 | 9998 | 612.2 | 16.3 |
| 2020 | 10103 | 904.2 | 11.2 |
| 2021 | 9154 | 566.6 | 16.2 |
| 2022 | 9244 | 198.0 | 46.7 |
| 2023 | 10026 | 59.5 | 168.5 |
Chart 4 of 11 · derived
Change the definitions and the China-U.S. gap ranges from about 10 to 21 times
Ratio of China's average yearly additions to the U.S. figure, 2019 to 2023, under five definitions. No single like-for-like ratio can be built from public data.

Download PNG of Change the definitions and the China-U.S. gap ranges from about 10 to 21 times WEBP of Change the definitions and the China-U.S. gap ranges from about 10 to 21 times SVG of Change the definitions and the China-U.S. gap ranges from about 10 to 21 times
Source: Derived from verified inputs. Status: derived; no single like-for-like ratio is possible. Data file: china-us-ratio-sensitivity-2019-2023.csv.
Cite this chart
Power Hopper Team. "Change the definitions and the China-U.S. gap ranges from about 10 to 21 times." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-04-china-us-transmission-ratio-sensitivity. Accessed [date accessed].
Data table
| case | china_mi_yr | us_mi_yr | ratio | basis |
|---|---|---|---|---|
| A. Published figures: China 330 kV+ (incl. DC) vs U.S. FERC 345 kV+ (latest editions) | 9705 | 468.1 | 20.7 | closest published thresholds; length bases not harmonized |
| B. China 500 kV+ (incl. DC) vs U.S. FERC 345 kV+ | 8633 | 468.1 | 18.4 | drops China 330 kV class |
| C. As A, but U.S. 2023 = ~450 mi (ACEG addendum figure, not found in any FERC table) | 9705 | 546.2 | 17.8 | sensitivity only |
| D. As A, but U.S. = FERC Form 1 p.424 investor-owned utilities, lines added or altered | 9705 | 731.0 | 13.3 | Form 1 counts rebuilds; IOUs only (PUDL republication) |
| E. As A, with China halved (illustrative bound if every new km were a double circuit counted twice) | 4853 | 468.1 | 10.4 | hypothetical bound; actual double-circuit share not published |
Conclusion: across five definitions, China built roughly 10 to 21 times as much high-voltage line as the U.S. from 2019 to 2023. A single like-for-like ratio cannot be built from public data.
3. Timelines: compared at one shared milestone
Projects were compared from final approval to energization. For China, 13 ultra-high-voltage direct-current lines took a median of 2.0 years from national approval to full service. For the U.S., 12 energized projects in Power Hopper's ledger took a median of 3.3 years from their last major approval; the spread is wide, and Champlain Hudson took 11.6 years. These samples are small and not representative, and 8 of the 12 U.S. dates are low-confidence. They show only that both countries take years of the same order after approval; much of the U.S. delay in the ledger comes earlier, in planning, siting and permitting. No cause is claimed.
Chart 5 of 11 · partially verified
After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3
Years from final approval to energization. Each dot is one line; the diamond is the median. Hollow U.S. dots rest on low-confidence dates. Small samples, descriptive only.

Download PNG of After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3 WEBP of After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3 SVG of After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3
Source: Power Hopper ledgers (v3), re-cut on matched milestones. Status: partially verified; samples not representative; descriptive only. Data file: matched-approval-to-service-us-china.csv.
Cite this chart
Power Hopper Team. "After final approval, China's UHV DC lines took a median 2.0 years to energize; sampled U.S. lines took 3.3." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-05-approval-to-energization-us-vs-china-transmission. Accessed [date accessed].
Data table
| country | project | approval_date | approval_milestone | service_date | years | confidence | included |
|---|---|---|---|---|---|---|---|
| United States | SunZia | 2023-05-19 | BLM Record of Decision #2 | 2026-06-18 | 3.08 | medium | yes |
| United States | Gateway South | 2016-12-16 | BLM Record of Decision (NOA) | 2024-12-01 | 7.96 | high | yes |
| United States | Ten West Link | 2021-09-23 | CPUC grants CPCN (month) | 2024-05-01 | 2.6 | low | yes |
| United States | Cardinal-Hickory Creek | 2020-01-17 | RUS Record of Decision | 2024-09-26 | 4.69 | medium | yes |
| United States | Champlain Hudson Power Express | 2014-10-01 | DOE ROD / Presidential Permit | 2026-05-13 | 11.61 | medium | yes |
| United States | New England Clean Energy Connect | 2021-01-14 | DOE Presidential Permit | 2026-01-16 | 5.0 | low | yes |
| United States | Susquehanna-Roseland | 2012-10-17 | NPS Record of Decision (Delaware Water Gap crossing) | 2015-05-01 | 2.54 | low | yes |
| United States | TrAIL (Trans-Allegheny Interstate Line) | 2008-12-01 | PA PUC approval, last state (month) | 2011-05-01 | 2.41 | low | yes |
| United States | Sunrise Powerlink | 2009-01-20 | BLM ROD (NOA in FR 2009-02-20) | 2012-06-18 | 3.41 | low | yes |
| United States | Tehachapi Renewable Transmission | 2009-12-17 | CPUC CPCN | 2016-12-15 | 7.0 | low | yes |
| United States | CapX2020 Hampton-Rochester-La Crosse | 2012-05-30 | Wisconsin PSC CPCN (month) | 2015-09-01 | 3.26 | low | yes |
| United States | Badger-Coulee | 2016-04-14 | Wisconsin PSC approval (month) | 2018-12-01 | 2.63 | low | yes |
| United States | Texas CREZ (345 kV program) | no dated approval in ledger | 2014-01-01 | no | |||
| United States | Big Stone South-Ellendale | no dated approval in ledger | 2019-02-01 | no | |||
| United States | One Nevada (ON Line) | no dated approval in ledger | 2013-12-31 | no | |||
| China | Yunnan–Guangdong (Chuxiong–Suidong) | 2006-12 | NDRC approval (hezhun) | 2010-06-18 | 3.51 | document/media source | yes |
| China | Xiangjiaba–Shanghai (Fulong–Fengxian) | 2007-04-26 | NDRC approval (hezhun) | 2010-07-08 | 3.2 | document/media source | yes |
| China | Jinping–Southern Jiangsu | 2008-11 | NDRC approval (hezhun) | 2012-12-12 | 4.07 | document/media source | yes |
| China | Hami South–Zhengzhou | 2012-05 | NDRC approval (hezhun) | 2014-01-27 | 1.7 | document/media source | yes |
| China | Xiluodu–Zhejiang (Yibin–Jinhua) | 2012-07-06 | NDRC approval (hezhun) | 2014-07-03 | 1.99 | document/media source | yes |
| China | Nuozhadu–Guangdong | 2011-07 | NDRC approval (hezhun) | 2015-06 | document/media source | no (date not verified) | |
| China | Ningdong–Zhejiang (Lingzhou–Shaoxing) | 2014-08 | NDRC approval (hezhun) | 2016-08-24 | document/media source | no (date not verified) | |
| China | Jiuquan–Hunan (Qilian–Shaoshan) | 2015-05 | NDRC approval (hezhun) | 2017-06-22 | document/media source | no (date not verified) | |
| China | Northern Shanxi–Nanjing (Yanmen–Huai'an) | 2015-06 | NDRC approval (hezhun) | 2017-06-30 | 2.04 | search-excerpt source | yes |
| China | Xilingol–Taizhou | 2015-10 | NDRC approval (hezhun) | 2017-09-30 | 1.96 | document/media source | yes |
| China | Jarud–Qingzhou | 2016-08-16 | NDRC approval (hezhun) | 2017-12-31 | 1.37 | document/media source | yes |
| China | Shanghaimiao–Linyi | 2015-12-01 | NDRC approval (hezhun) | 2019-01-11 | document/media source | no (date not verified) | |
| China | Changji–Guquan (Zhundong–Southern Anhui) | 2015-12-28 | NDRC approval (hezhun) | 2019-09-26 | 3.75 | document/media source | yes |
| China | Qinghai–Henan | 2018-10 | NDRC approval (hezhun) | 2020-12-30 | document/media source | no (date not verified) | |
| China | Kunbei–Liuzhou–Longmen 3-terminal hybrid (LCC/VSC) | 2018-03-29 | NDRC approval (hezhun) | 2020-12-27 | document/media source | no (date not verified) | |
| China | Northwest Yunnan–Guangdong (Xinsong–Dongfang) | 2015-12-28 | NDRC approval (hezhun) | 2018-05-18 | search-excerpt source | no (date not verified) | |
| China | Yazhong–Jiangxi (Ya'an–Nanchang) | 2019-08-23 | NDRC approval (hezhun) | 2021-06-21 | 1.83 | search-excerpt source | yes |
| China | Northern Shaanxi–Wuhan | 2019-01 | NDRC approval (hezhun) | 2022-04-16 | 3.25 | document/media source | yes |
| China | Baihetan–Jiangsu | 2020-11-03 | NDRC approval (hezhun) | 2022-07-01 | document/media source | no (date not verified) | |
| China | Baihetan–Zhejiang | 2021-07 | NDRC approval (hezhun) | 2022-12-30 | 1.46 | document/media source | yes |
| China | Longdong–Shandong | 2023-02-27 | NDRC approval (hezhun) | 2025-05-08 | document/media source | no (date not verified) | |
| China | Hami–Chongqing | 2023-07 | NDRC approval (hezhun) | 2025-12-04 | document/media source | no (date not verified) | |
| China | Ningxia–Hunan | 2023-05-24 | NDRC approval (hezhun) | 2025-10-08 | 2.38 | search-excerpt source | yes |
| China | Upper Jinsha–Hubei | NDRC approval (hezhun) | 2025-12-18 | search-excerpt source | no (date not verified) |
4. ERCOT's 765-kV plan: what the $32.99 billion and $229 million mean
ERCOT's Permian Basin and Eastern 765-kV "STEP" Core Plan is estimated to cost $32.99 billion to build; the 345-kV alternative ERCOT studied is estimated at $30.75 billion. The difference is $2.24 billion, or about $1.35 billion after ERCOT's adjustments for outages and upgrades. The 765-kV plan needs about 3,441 miles of new right-of-way and 2,831 miles of upgrades, cuts annual system losses by about 5% (around 560 GWh) compared with the 345-kV plan, and raises the West Texas export stability limit from 12.7 GW to 16.2 GW. ERCOT says either plan implies roughly $5 billion a year of transmission investment.
Chart 6 of 11 · verified against ERCOT documents
ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan
ERCOT's estimated construction cost of two statewide transmission plans, in billions of dollars. These are generic cost estimates.

Download PNG of ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan WEBP of ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan SVG of ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan
Source: ERCOT Trending Topic Dec 2025; ERCOT 25RPG022 review. Status: verified against ERCOT documents.
Cite this chart
Power Hopper Team. "ERCOT estimates its 765-kV plan costs about $2.2 billion more to build than a 345-kV plan." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-06-ercot-765kv-vs-345kv-plan-construction-cost. Accessed [date accessed].
Data table
| Plan | Estimated construction cost, billions of dollars |
|---|---|
| 345-kV plan | 30.75 |
| 765-kV STEP Core Plan | 32.99 |
| Difference (before ERCOT's outage and upgrade adjustment) | 2.24 |
| Difference after adjustment | 1.35 |
The widely quoted $229 million is a model result for one study year, 2039: the extra reduction in system-wide consumer energy cost from the 765-kV plan compared with the 345-kV plan, not compared with building nothing. In 2034, ERCOT's model shows the 765-kV plan $136 million less favorable than the 345-kV plan. The first approved segment, Drill Hole-Sand Lake-Solstice, is a $742.2 million, 104.4-mile project with a summer 2030 in-service date.
Chart 7 of 11 · verified against ERCOT document
In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year
Change in modeled yearly system-wide consumer energy cost savings, 765-kV plan minus 345-kV plan, in millions of 2025 dollars.

Download PNG of In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year WEBP of In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year SVG of In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year
Source: ERCOT 25RPG022 independent review. Status: verified against ERCOT document.
Cite this chart
Power Hopper Team. "In ERCOT's model, the 765-kV plan's consumer-cost edge over 345 kV shows up only in the later study year." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-07-ercot-765kv-modeled-consumer-energy-cost-2034-2039. Accessed [date accessed].
Data table
| Study year | 765-kV plan minus 345-kV plan, millions of 2025 dollars a year |
|---|---|
| 2034 | -136 (345-kV plan saves more) |
| 2039 | +229 (765-kV plan saves more) |
5. Reliability and room to grow
The North American Electric Reliability Corporation's Interregional Transfer Capability Study found that in its 2033 case ERCOT had 135 hours of energy deficiency, with a maximum shortfall of 18,926 MW, and puts ERCOT's current modeled import limit at 820 MW. As "prudent additions" it recommends about 14,100 MW of new transfer capability into ERCOT: 5,700 MW from the Front Range, 4,300 MW from MISO-South and 4,100 MW from SPP-South, about 40% of the 35,000 MW it recommends nationwide. These are study recommendations; the study "does not prescribe how" to build them, and none has been approved.
Chart 8 of 11 · verified against NERC report
NERC's study recommends about 14,100 MW of new import capability for ERCOT
NERC's recommended "prudent additions" of transfer capability into ERCOT, in megawatts (2033 study case). These are study recommendations, not approved projects.

Download PNG of NERC's study recommends about 14,100 MW of new import capability for ERCOT WEBP of NERC's study recommends about 14,100 MW of new import capability for ERCOT SVG of NERC's study recommends about 14,100 MW of new import capability for ERCOT
Source: NERC ITCS Final Report (Nov 2024). Status: verified against NERC report.
Cite this chart
Power Hopper Team. "NERC's study recommends about 14,100 MW of new import capability for ERCOT." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-08-nerc-itcs-ercot-import-capability-recommendation. Accessed [date accessed].
Data table
| Source of added import capability | Megawatts |
|---|---|
| From Front Range (West) | 5,700 |
| From MISO South | 4,300 |
| From SPP South | 4,100 |
| Total recommended for ERCOT | 14,100 |
| Modeled import limit today | 820 |
For context, during Winter Storm Uri in February 2021 ERCOT's direct-current ties could import at most about 1,220 MW while firm load shed peaked near 20,000 MW. Those two figures were carried from the FERC-NERC report and not re-checked for this package.
6. What it could mean for a home's bill (Power Hopper estimate)
ERCOT does not publish a per-household figure, so Power Hopper built a transparent estimate. It assumes all $32.99 billion enters rates at a yearly carrying-charge rate of 8%, 11% or 14% (Power Hopper's assumption), and spreads the cost using 2025 transmission cost allocation data from PUCT Docket 59080 and each utility's residential rate factor.
| Utility area | At today's load (8% / 11% / 14%) | If ERCOT peak load grows to 111.3 GW | Extra over the 345-kV plan (central) |
|---|---|---|---|
| Oncor | $9.51 / $13.08 / $16.64 | $6.91 / $9.50 / $12.09 | about $0.89 |
| CenterPoint | $10.80 / $14.85 / $18.90 | $7.85 / $10.79 / $13.74 | about $1.01 |
Chart 9 of 11 · estimate
Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges
A Power Hopper estimate, not an ERCOT or utility forecast. The full $32.99 billion plan in rates: bars show an 8% to 14% yearly carrying charge, the dot 11%.

Download PNG of Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges WEBP of Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges SVG of Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges
Source: Power Hopper model; inputs from PUCT, ERCOT, EIA. Status: estimate; inputs verified except carrying-charge rate (assumption) and EIA customer counts (carried from v3). Data file: household-transmission-charge-estimate.csv.
Cite this chart
Power Hopper Team. "Our estimate: ERCOT's 765-kV plan could add about $7-19 a month to a home's transmission charges." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-09-household-transmission-charge-estimate-ercot-765kv-plan. Accessed [date accessed].
Data table
| scenario | tdu | fcr_low_8pct | fcr_central_11pct | fcr_high_14pct | incremental_vs_345kv_plan_central | note |
|---|---|---|---|---|---|---|
| Today's load (2025 4CP 80.9 GW) | Oncor | 9.51 | 13.08 | 16.64 | 0.89 | 4CP and TDU shares from PUCT Docket 59080 Matrix B |
| Today's load (2025 4CP 80.9 GW) | CenterPoint | 10.8 | 14.85 | 18.9 | 1.01 | 4CP and TDU shares from PUCT Docket 59080 Matrix B |
| Load grows to 111.3 GW (ERCOT 2032 forecast) | Oncor | 6.91 | 9.5 | 12.09 | 0.65 | same TDU share and residential customers assumed; illustrative |
| Load grows to 111.3 GW (ERCOT 2032 forecast) | CenterPoint | 7.85 | 10.79 | 13.74 | 0.73 | same TDU share and residential customers assumed; illustrative |
This is Power Hopper's estimate, not an ERCOT or PUCT figure. It ignores any energy-cost savings, timing, depreciation and the mix of retail plans. The carrying-charge rate is an assumption, and the customer counts come from an earlier draft. The calculation is in household-transmission-charge-estimate.csv.
7. What the Senate bill would do
Under review. The facts below are as of 6:45 a.m. CT on Nov. 17, 2026. Their legal effect has not been reviewed by counsel, and the cost estimate was seen only through congress.gov and a republication. A check of the Senate roll-call list later on Nov. 17 showed no vote after number 264. This is research, not legal advice.
- The text. The Bipartisan American Affordability and Jobs Act (BAAJA) is offered as Senate Amendment 6883, a full substitute for H.R. 2347, proposed Nov. 10. A bill with the same short title was introduced as S. 5653 on Sept. 30; the two texts were not compared.
- The votes. Vote 257, cloture on the motion to proceed, passed 73 to 25. Vote 258, the motion to proceed, passed 62 to 21. Vote 264, cloture on the amendment, Nov. 16 at 5:27 p.m. CT, passed 70 to 27. Both Texas senators voted yea.
- Where it stands. The latest official action is "Considered by Senate" on Nov. 16. There has been no vote on adopting the amendment or passing the bill.
- Cost. A preliminary CBO/JCT estimate (Nov. 13) reportedly finds the bill increases deficits by less than $1 billion over 2027 to 2036.
The amendment text, as printed in the Congressional Record, includes: Section 2101, which revises FERC's "backstop" siting authority to cover lines of at least 230 kV and adds a new subsection 216(k)(1) saying the section "shall not apply within the area referred to in section 212(k)(2)(A)," which is the ERCOT area. Section 2103 adds a recurring Department of Energy transmission study and planning provisions with a similar ERCOT exclusion in new section 225(b)(1). Section 2201 ("Accelerating Claims") sets a 150-day window for court challenges to federal authorizations. How the ERCOT exclusions would apply in practice, including to the ties NERC recommends, is a question for counsel.
Jobs claim. A senator said on the floor on Nov. 9 that the bill "is estimated to create over 100,000 jobs." No model was cited, and it is not stated whether the figure counts jobs or job-years. For scale, 100,000 is about 40% of the 251,549 people employed in U.S. power and communication line construction in 2025 (BLS, NAICS 237130); Texas accounted for 36,957.
8. Cost per mile
FERC Form 1 filings, as compiled by the PUDL project, give a median reported cost for long (20 miles or more) 345 kV-plus lines in 2025 dollars: about $1.5 million a mile in 2001 to 2008 (20 lines), about $2.0 million in 2009 to 2016 (84 lines) and about $2.0 million in 2017 to 2025 (70 lines). Filed costs may be partial, and these figures do not show whether costs rose. No claim is made about why U.S. and Chinese prices differ.
Chart 10 of 11 · partially verified
Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009
Median reported cost per mile of lines at 345 kV or higher and 20 miles or longer, in millions of 2025 dollars. Bar = median; whisker = middle half.

Download PNG of Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009 WEBP of Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009 SVG of Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009
Source: FERC Form 1 p.424 via PUDL. Status: partially verified (PUDL republication of FERC filings; not re-pulled in v4). Data file: form1-cost-per-mile-by-period.csv.
Cite this chart
Power Hopper Team. "Filed costs of long 345-kV-plus lines: a median of about $2 million a mile since 2009." Chart. Room to Grow: U.S. and China High-Voltage Transmission, and ERCOT's 765-kV Plan dataset. Power Hopper Media Data Room, published November 17, 2026. https://powerhopper.energy/media/data/us-china-high-voltage-transmission-and-ercot-765-kv-plan-research-package-2026#uhv-10-us-345kv-transmission-cost-per-mile-form1. Accessed [date accessed].
Data table
| period | n_lines | median_musd_per_mile_2025 | p25 | p75 | source | caveat |
|---|---|---|---|---|---|---|
| 2001-2008 | 20 | 1.54 | 0.52 | 2.32 | FERC Form 1 p.424 via PUDL (data.catalyst.coop); lines >=345 kV and >=20 mi; CPI-U to 2025 $ | filed cost may be partial; excludes <$0.1M/mi; IOUs only; not a test of whether costs rose |
| 2009-2016 | 84 | 2.04 | 1.0 | 2.77 | FERC Form 1 p.424 via PUDL (data.catalyst.coop); lines >=345 kV and >=20 mi; CPI-U to 2025 $ | filed cost may be partial; excludes <$0.1M/mi; IOUs only; not a test of whether costs rose |
| 2017-2025 | 70 | 2.01 | 1.25 | 2.82 | FERC Form 1 p.424 via PUDL (data.catalyst.coop); lines >=345 kV and >=20 mi; CPI-U to 2025 $ | filed cost may be partial; excludes <$0.1M/mi; IOUs only; not a test of whether costs rose |
All 64 numbers, with sources and status
"Verified" means the figure was read in the primary document on Nov. 17, 2026. "Partially verified", "carried from an earlier draft", "derived", "assumption" and "estimate" are marked as such.
Show the full table
| ID | Number | Value | Status | Source |
|---|---|---|---|---|
| US-01 | U.S. new 345 kV+ line, 2013 (peak year) | 4194.5 miles | verified (primary document read 2026-11-17) | source |
| US-02 | U.S. new 345 kV+ line, 2023 (latest FERC edition) | 59.5 miles | verified (primary document read 2026-11-17) | source |
| US-03 | U.S. new 345 kV+ line, 2024 (latest FERC edition) | 906.1 miles | verified (primary document read 2026-11-17); may still be revised | source |
| US-04 | U.S. new 345 kV+ line, 2024 (FERC first estimate) | 275.5 miles | verified (primary document read 2026-11-17) | source |
| US-05 | U.S. new 345 kV+ line, 2024 (FERC Apr 2025 interim revision) | 888.5 miles | verified (primary document read 2026-11-17) | source |
| US-06 | U.S. new 345 kV+ line, 2025 (FERC first estimate) | 402.6 miles | verified (primary document read 2026-11-17); first estimate | source |
| US-07 | U.S. average yearly 345 kV+ additions, 2019-2023 | 468.1 miles/yr | derived from verified inputs | data/us_345kv_plus_latest_ferc_2009_2025.csv |
| US-08 | U.S. average yearly 345 kV+ additions, 2009-2016 | 1564.9 miles/yr | derived from verified inputs | data/us_345kv_plus_latest_ferc_2009_2025.csv |
| US-09 | U.S. average yearly 345 kV+ additions, 2017-2025 (2017 Jan-Nov; 2025 first estimate) | 547.7 miles/yr | derived from verified inputs | data/us_345kv_plus_latest_ferc_2009_2025.csv |
| US-10 | Median ratio of latest to first FERC estimate, 13 years 2010-2024 | 1.35 ratio | derived (v3 said 1.4) | data/us_345kv_plus_latest_ferc_2009_2025.csv |
| US-11 | U.S. 2023 per ACEG July 2025 addendum (~400 at 345 kV + ~50 at 500 kV) | 450 miles | NOT FOUND in FERC tables: Apr 2025 EIU has no 2023 column; Dec 2024 edition and its Apr 2025 revision show 59.5 | source |
| US-12 | Grid Strategies (Nov 2026): 2023 data rose only about four miles across a year of FERC updates | 4 miles | secondary; consistent with FERC 55.5 -> 59.5 | source |
| US-13 | FERC Form 1 p.424 345 kV+ lines added or altered, 2023 (investor-owned utilities) | 553.0 miles | partially verified (carried from v3; not re-pulled) | source |
| CN-01 | China new lines 330 kV+ AC plus all DC, average 2019-2023 | 15619 km/yr | verified (table read from page image) | source |
| CN-02 | Same, in miles | 9705 miles/yr | derived from verified inputs | source |
| CN-03 | China new lines 500 kV+ AC plus all DC, average 2019-2023 | 8633 miles/yr | derived from verified inputs | source |
| CN-04 | China AC 330 kV+ circuit-length stock increase 2019-2023 (Table 3-15) vs additions 2020-2023 (Table 4-24) | 52282 vs 50374 km | derived; indicates additions are on a circuit-length basis (not proof) | source |
| R-01 | China/U.S. ratio, published figures 2019-2023 (330 kV+ vs 345 kV+) | 20.7 ratio | derived; not like-for-like | data/china_us_ratio_sensitivity_2019_2023.csv |
| R-02 | China/U.S. ratio range across five definitions | 10.4-20.7 ratio | derived; sensitivity | data/china_us_ratio_sensitivity_2019_2023.csv |
| T-01 | China UHV DC: median years, NDRC approval to full service (n=13) | 2.04 years | partially verified (3 of 13 rely on a search-excerpt source) | data/matched_approval_to_service_us_china.csv |
| T-02 | U.S. ledger: median years, final approval to energization (n=12) | 3.33 years | partially verified (8 of 12 rely on a low-confidence date) | data/matched_approval_to_service_us_china.csv |
| E-01 | ERCOT 765-kV STEP Core Plan construction cost estimate | 32.99 USD billion | verified (primary document read 2026-11-17) | source |
| E-02 | ERCOT 345-kV plan construction cost estimate | 30.75 USD billion | verified (primary document read 2026-11-17) | source |
| E-03 | Cost difference, 765 vs 345 (and after outage/upgrade adjustment) | 2.24 (1.35) USD billion | verified (primary document read 2026-11-17) | source |
| E-04 | 765 vs 345: added system-wide consumer energy cost reduction, study year 2039 | 229 USD million/yr (2025$) | verified (primary document read 2026-11-17); model result, not net savings vs no new lines | source |
| E-05 | 765 vs 345: consumer energy cost savings, study year 2034 | -136 USD million/yr (2025$) | verified (primary document read 2026-11-17) | source |
| E-06 | STEP Core Plan new right-of-way / existing line upgrades | 3441 / 2831 miles | verified (primary document read 2026-11-17) | source |
| E-07 | STEP Core Plan reduction in annual systemwide losses vs 345-kV plan | ~5% (~560 GWh) share / GWh | verified (primary document read 2026-11-17) | source |
| E-08 | West Texas Export stability limit, before/after STEP | 12.7 -> 16.2 GW | verified (primary document read 2026-11-17) | source |
| E-09 | ERCOT 2030 summer peak forecast used in planning | >150 GW | verified (primary document read 2026-11-17); forecast | source |
| E-10 | Drill Hole-Sand Lake-Solstice 765-kV project cost / new ROW / in-service | 742.2 / 104.4 / Summer 2030 USD million / miles / date | verified (primary document read 2026-11-17) | source |
| E-11 | Annual transmission investment needed under either plan (6-yr horizon) | 5 USD billion/yr | verified (primary document read 2026-11-17) | source |
| N-01 | NERC prudent additions into ERCOT: Front Range / MISO-S / SPP-S | 5700 / 4300 / 4100 MW | verified (primary document read 2026-11-17); study recommendation | source |
| N-02 | NERC prudent additions into ERCOT, total | 14100 MW | verified (primary document read 2026-11-17); study recommendation | source |
| N-03 | NERC prudent additions, U.S. total | 35000 MW | verified (primary document read 2026-11-17) | source |
| N-04 | ERCOT current modeled import limit (ITCS) | 820 MW | verified (primary document read 2026-11-17) | source |
| N-05 | ERCOT energy-deficiency hours / max deficiency, 2033 case | 135 / 18,926 hours / MW | verified (primary document read 2026-11-17) | source |
| N-06 | ERCOT maximum DC-tie import capability during Winter Storm Uri | 1220 MW | carried from v3; not re-opened in v4 | source |
| N-07 | ERCOT firm load shed at peak, Winter Storm Uri | 20000 MW | carried from v3; not re-opened in v4 | source |
| J-01 | U.S. power and communication line construction employment (NAICS 237130, private), 2025 | 251549 jobs | verified (primary document read 2026-11-17) | source |
| J-02 | Texas, same industry, 2025 | 36957 jobs | verified (primary document read 2026-11-17) | source |
| J-03 | "over 100,000 jobs" as share of J-01 | 39.8 percent | derived; the claim's unit (jobs vs job-years, direct vs total) is not stated | see source detail |
| J-04 | Floor statement: bill "is estimated to create over 100,000 jobs" | quote | verified (primary document read 2026-11-17) (quote); underlying estimate not cited | source |
| L-01 | S.Amdt. 6883 (BAAJA substitute) proposed to H.R. 2347 | 2026-11-10 date | verified (primary document read 2026-11-17) | source |
| L-02 | Senate vote 257: cloture on motion to proceed to H.R. 2347 | 73-25 votes | verified (primary document read 2026-11-17) | source |
| L-03 | Senate vote 258: motion to proceed | 62-21 votes | verified (primary document read 2026-11-17) | source |
| L-04 | Senate vote 264: cloture on S.Amdt. 6883 (Nov 16 2026, 5:27 PM CT) | 70-27 votes | verified (primary document read 2026-11-17) | source |
| L-05 | Latest official action as of 2026-11-17 06:40 CT | 2026-11-16 Considered by Senate status | verified (primary document read 2026-11-17); no adoption or passage vote recorded yet | source |
| L-06 | CBO/JCT preliminary estimate: deficit increase, 2027-2036 | <1 USD billion | partially verified: letter existence/date verified via congress.gov API; wording via Benton.org republication (cbo.gov blocked automated access) | source |
| L-07 | SA 6883 Sec. 2101(i): new FPA 216(k)(1) "This section shall not apply within the area referred to in section 212(k)(2)(A)" (ERCOT) | text | verified (primary document read 2026-11-17); legal effect needs counsel | source |
| L-08 | SA 6883 Sec. 2103: new FPA 225(b)(1) ERCOT exclusion and planning-region exclusion | text | verified (primary document read 2026-11-17); legal effect needs counsel | source |
| L-09 | SA 6883 Sec. 2101(b): FERC backstop eligibility includes facilities of not less than 230 kV; state 1-year clock runs from state filing date | text | verified (primary document read 2026-11-17); legal effect needs counsel | source |
| B-01 | ERCOT total TCOS (2026 matrix) | 6055.6 USD million/yr | verified (primary document read 2026-11-17) | source |
| B-02 | ERCOT average 4CP, 2025 | 80874 MW | verified (primary document read 2026-11-17) | source |
| B-03 | Oncor / CenterPoint average 4CP, 2025 | 28677 / 20180 MW | verified (primary document read 2026-11-17) | source |
| B-04 | Oncor Rider TCRF residential allocation factor | 42.407 percent | verified (primary document read 2026-11-17) | source |
| B-05 | CenterPoint Rider TCRF residential allocation factor | 48.9238 percent | verified (primary document read 2026-11-17) | source |
| B-06 | Oncor / CenterPoint residential customers, 2024 | 3477215 / 2485470 customers | carried from v3; not re-downloaded in v4 | source |
| B-07 | Annual carrying-charge rate (levelized revenue requirement / capital) | 8-14 (central 11) percent | ASSUMPTION; needs utility-specific check | see source detail |
| B-08 | Estimated added monthly transmission charge, Oncor home, full STEP in rates, today's load | 9.51-16.64 (central 13.08) USD/month | Power Hopper ESTIMATE, not ERCOT | data/household_transmission_charge_estimate.csv |
| B-09 | Same, CenterPoint home | 10.80-18.90 (central 14.85) USD/month | Power Hopper ESTIMATE | data/household_transmission_charge_estimate.csv |
| B-10 | Same, Oncor home, if ERCOT 4CP grows to 111.3 GW and new load absorbs the added share | 6.91-12.09 (central 9.50) USD/month | Power Hopper ESTIMATE; 111.3 GW forecast carried from v3 (ERCOT CEO update Apr 2026) | data/household_transmission_charge_estimate.csv |
| B-11 | Incremental cost of 765 plan vs 345 plan, Oncor home (central) | 0.89 USD/month | Power Hopper ESTIMATE | data/household_transmission_charge_estimate.csv |
| C-01 | Median filed cost per mile, 345 kV+ lines >=20 mi, 2001-08 / 2009-16 / 2017-25 (2025$) | 1.54 / 2.04 / 2.01 USD million/mile | partially verified (PUDL republication; not re-pulled in v4) | source |
What is still open
- The legal effect of the Senate bill's ERCOT exclusions (section 7) and the CBO figure have not been confirmed.
- FERC's 2025 figure is still a first estimate, and the 2023 figure in the advocacy addendum could not be matched to any FERC table.
- Whether China's lengths are circuit length is inferred, not published. Eight U.S. and three Chinese timeline dates are low-confidence.
- The carrying-charge rate (8% to 14%) is an assumption; customer counts, FERC Form 1 cost series and the Winter Storm Uri figures were carried from an earlier draft and not re-opened.
Downloads
Key numbers with sources (CSV) · Key numbers (JSON) · Chart manifest (CSV) · Earlier-draft chart review (CSV) · Source link check, Nov 17 (CSV) · China cec new lines by voltage 2019 2023 (CSV) · China circuit vs route check (CSV) · China us annual 2019 2023 (CSV) · China us ratio sensitivity 2019 2023 (CSV) · Ferc eiu 345kv plus all editions 2009 2025 (CSV) · Form1 cost per mile by period (CSV) · Household transmission charge estimate (CSV) · Matched approval to service us china (CSV) · Us 345kv plus latest ferc 2009 2025 (CSV) · Us ferc vs form1 2009 2025 (CSV) · SHA-256 checksums
Notes and limits
Scope. U.S. 345 kV-plus line additions 2009 to 2025 (FERC Energy Infrastructure Updates, every December edition 2010 to 2025), China's new lines 2019 to 2023 (China Electricity Council yearbook), approval-to-energization timelines, ERCOT's 765-kV plan (ERCOT and its independent review), NERC's interregional transfer study, a Power Hopper household-cost estimate, and the status of the Senate's BAAJA as of Nov. 17, 2026.
Verification. Each number is marked verified (read in the primary document on Nov. 17, 2026), partially verified, derived, assumption or estimate in key-numbers.csv. The 98 source links were checked on Nov. 17: 81 opened, 10 returned 403 because of bot protection (content confirmed through an API, the Congressional Record or the underlying file), six Chinese hosts refuse this network, and one returned 401. Those 17 need a manual browser check.
Comparisons. China-U.S. ratios are shown across five definitions because lengths are not measured the same way; no like-for-like ratio is claimed. Timeline medians are descriptive and rest on small samples. No cause is claimed for any difference between countries.
Estimates. The household figure is a Power Hopper estimate: capital cost times an assumed 8% to 14% carrying charge, allocated with PUCT Docket 59080 data. It is not an ERCOT, PUCT or utility forecast and ignores savings and timing.
Not included. Primary source documents (FERC, ERCOT, NERC, PUCT and BLS files) and rebuild scripts are not hosted here; each number links to its source. Legal effect of the Senate bill has not been reviewed by counsel. This is research, not legal advice.
Power Hopper is not affiliated with or endorsed by FERC, ERCOT, NERC, the PUCT, the U.S. Senate, the Congressional Budget Office, the China Electricity Council, or any other agency or organization named here.
Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility. This brief was prepared with AI assistance.