Texas power grid map: what the Grid Atlas shows

The Grid Atlas maps the Texas power grid's physical backbone: about 55,888 miles of mapped power lines, 6,257 substations and 986 power plants, as drawn by volunteers in OpenStreetMap and colored by voltage. High-voltage lines (230 kV and above, mostly 345 kV in ERCOT) move bulk power between regions; 138 kV and 69 kV lines feed local substations.

Line lengths are the length of each mapped OpenStreetMap way: route geometry, not circuit-miles. Operators and voltages appear only where a mapper recorded them; anything missing reads "unavailable". OSM does not say whether a line is energized and an OSM edit date is not a construction date, so ages, owners, conductors and official line names come only from public records: FERC Form 1, ERCOT's transmission project tracker, PUCT monthly construction reports and PUCT dockets. Anything without a record reads "Not publicly documented" and is never estimated.

Click a substation to see its transformers and capacity from FERC Form 1, the distribution feeders its utility reported to the PUCT (where the utility's substation name could be matched to the map, about 4 in 10 reported feeders), when it was connected as a new substation (PUCT construction reports), the ERCOT generating units connected there and every mapped line that ends there. Click a power plant for its ERCOT installed capacity, its EIA nameplate capacity, in-service years, planned generators and planned retirements, and a line for its name, ends, age, last rebuild, conductor, owner, PUCT docket and congestion history.

Key figures

Most congested Texas transmission elements

Ranked by hours binding in ERCOT's day-ahead market, 2026-10-22 to 2026-11-21 (ERCOT NP4-191-CD). Binding means the element was at its limit in the market solution; it is not an outage.

ElementkVDay-ahead hours bindingERCOT limit (median)
MATHIS – ARGENTAline · ERCOT LN:ARGENTA:MATHIS:696970469 MW
PSA – BCVline · ERCOT LN:BCV:PSA:138138661478 MW
Blessing Substation – Blessing Substationtransformer · ERCOT XF:BLESSING:345/138345637428 MW
Putnam Switching Station – LENSWline · ERCOT LN:LENSW:PUTN:13813856087 MW
Scurry Chevron Substation – Knapp Substationline · ERCOT LN:KNAPP:SCRCV:138138544222 MW
Solstice Substation – Fort Stockton Plant Substationline · ERCOT LN:FTST:SOLSTICE:138138540231 MW
Grant Substation – Plaza Substationline · ERCOT LN:GN:PZ:138138501387 MW
Blessing Substation – PAVLOVline · ERCOT LN:BLESSING:PAVLOV:138138490157 MW
Asherton Substation – CATARINAline · ERCOT LN:ASHERTON:CATARINA:138138457152 MW
transformer · ERCOT XF::0/004291,000 MW

Largest power plants on the map by ERCOT capacity

Installed capacity from ERCOT's Monthly Outlook for Resource Adequacy unit list, matched to mapped plants (the map lists the ERCOT units behind each figure).

PlantFuel (as mapped)Installed MWIn service
W. A. Parish Electric Generating Station9 ERCOT unitscoal;gas4,0091958–1982
Martin Lake Power Plant3 ERCOT unitscoal2,6791977–1979
Comanche Peak Nuclear Power Plant2 ERCOT unitsnuclear2,5381990–1993
Forney Energy Center8 ERCOT unitsgas2,0242003
Limestone Electric Generating Station2 ERCOT unitscoal1,8501985–1986
Oak Grove Power Plant2 ERCOT unitscoal1,8342010–2011
Midlothian Energy Facility6 ERCOT unitsgas1,5812001–2002
J K Spruce Power Plant2 ERCOT unitscoal1,4821992–2010
T. H. Wharton Power Plant17 ERCOT unitsgas1,2961967–1975
Handley Power Plant3 ERCOT unitsgas1,2651963–1977
Lamar Power Project6 ERCOT unitsgas1,1762000
Guadalupe Power Partners Generating Station6 ERCOT unitsgas1,1322000
Freestone Energy Center6 ERCOT unitsgas1,0992002
Sandy Creek Energy Station1 ERCOT unitcoal1,0082013
Hays Energy Project4 ERCOT unitsgas9882002

Texas generating capacity by fuel

Nameplate capacity of every generator of 1 MW or more on EIA's operating list for Texas, from the U.S. Energy Information Administration's monthly generator inventory (Form EIA-860M) as of September 2026. The list includes 3,674 MW on standby or out of service. Nameplate is a generator's rated size, not what it produces; wind and solar produce well below nameplate most hours. 183,431 MW of the total is in ERCOT; the rest is in the Southwest Power Pool (13,708 MW), MISO (7,663 MW), El Paso Electric (1,928 MW) and balancing authority code DOPD as published by EIA (500 MW).

FuelNameplate MWShare
Natural gas and oil85,16341.1%
Wind44,52621.5%
Solar34,97916.9%
Battery storage19,4009.4%
Coal and lignite16,5828.0%
Nuclear5,1392.5%
Hydro7350.4%
Other (biomass, waste heat, landfill gas and others)7080.3%
Total207,230100%

Planned power plant retirements in Texas

Generators whose owners had told EIA they plan to retire them, as of EIA's September 2026 inventory (8,412 MW in all). A planned retirement can be delayed or cancelled, and a date that has already passed may since have happened or moved; it is the owner's plan as reported, not a forecast.

PlantTechnologyMWPlanned retirement
SabineOrange County · 3 generators · Entergy Texas Inc.Natural Gas Steam Turbine1,304Oct 2026
O W SommersBexar County · 1 generator · City of San Antonio - (TX)Natural Gas Steam Turbine446Mar 2027
Plant XLamb County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine190Dec 2027
NicholsPotter County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine114Dec 2027
NewmanEl Paso County · 1 generator · El Paso Electric CoNatural Gas Steam Turbine82Dec 2027
Hal C Weaver Power PlantTravis County · 2 generators · University of Texas at AustinNatural Gas Fired Combined Cycle14Jan 2028
TolkLamb County · 2 generators · Southwestern Public Service CoConventional Steam Coal1,136Dec 2028
J K SpruceBexar County · 1 generator · City of San Antonio - (TX)Conventional Steam Coal566Dec 2028
NicholsPotter County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine114Dec 2028
NewmanEl Paso County · 1 generator · El Paso Electric CoNatural Gas Steam Turbine82Dec 2028
O W SommersBexar County · 1 generator · City of San Antonio - (TX)Natural Gas Steam Turbine446Mar 2029
Works 4Wichita County · 1 generator · Vitro Architectural GlassPetroleum Liquids2Nov 2029
NicholsPotter County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine248Dec 2030
CopperEl Paso County · 1 generator · El Paso Electric CoNatural Gas Fired Combustion Turbine87Dec 2030
JonesLubbock County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine248Dec 2031
NewmanEl Paso County · 4 generators · El Paso Electric CoNatural Gas Steam Turbine; Natural Gas Fired Combined Cycle412Dec 2031
Flower Valley IReeves County · 1 generator · Flower ValleyBatteries10Aug 2032
Lewis CreekMontgomery County · 2 generators · Entergy Texas Inc.Natural Gas Steam Turbine543Jun 2034
JonesLubbock County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine248Dec 2034
HarringtonPotter County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine360Dec 2036
HarringtonPotter County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine360Dec 2038
HarringtonPotter County · 1 generator · Southwestern Public Service CoNatural Gas Steam Turbine360Dec 2040
Madero GridHidalgo County · 1 generator · Madero Grid, LLCBatteries100Jun 2042
Ignacio Grid Energy Storage SystemHidalgo County · 1 generator · Ignacio Grid, LLCBatteries100Jun 2042
Hale Community Wind FarmHale County · 1 generator · Southwestern Public Service CoOnshore Wind Turbine478Dec 2044
JonesLubbock County · 1 generator · Southwestern Public Service CoNatural Gas Fired Combustion Turbine183Dec 2056
JonesLubbock County · 1 generator · Southwestern Public Service CoNatural Gas Fired Combustion Turbine183Dec 2058

Data centers and other large loads, by region

Large loads are data centers, crypto mining and other sites that would use 75 MW or more. In September 2026 ERCOT conditionally classified the loads in its first large-load study round ("Batch Zero") for 2032: 66.4 GW as base load (204 projects: already energized, or qualifying through ERCOT's other base-load categories: committed, advancing, the Permian reliability plan, earlier studies, or net metering) and 125.4 GW as studied load (158 projects ERCOT will study separately; some were moved there from the base-load path). It excluded another 302.2 GW (373 projects). About 22 GW of the base load is already energized; the rest are plans that may change, and ERCOT's final verification is due in December 2026. ERCOT does not publish individual projects or locations.

ERCOT weather zoneBase load 2032 (MW)Studied load 2032 (MW)Total (MW)
North Central14,55925,80740,366
North14,22224,30938,531
South4,26620,44724,713
West5,98616,39522,381
South Central6,74714,77221,519
Far West8,49310,53919,032
Coast10,9766,49717,473
East1,1106,6257,735

Counties ERCOT named: the most base load is in Dallas (5,713 MW), Harris (5,672 MW), Haskell (2,689 MW), Brazoria (2,357 MW), Ellis (2,330 MW); the most base plus studied load is in Cameron (12,235 MW), Dallas (7,637 MW), Jones (7,000 MW), Harris (6,899 MW), Childress (6,750 MW). In ERCOT's November 2026 data-center survey (preliminary), 433 of 465 loads responded; the 429 responses ERCOT reviewed request 177.4 GW in all; by load zone: West 73 GW, South 49 GW, North 45 GW, Houston 10 GW.

The largest Texas power outages since 2014

Statewide customers without power at the worst 15-minute moment of each event, from Oak Ridge National Laboratory's EAGLE-I records, which read utility outage maps every 15 minutes. An event is a run of consecutive days when at least 100,000 Texas customers were out at some moment. EAGLE-I's coverage grew over the years, so its counts are lower bounds; it does not record causes.

Dates (UTC)Peak customers outCustomer-hours out
2021-02-15 to 2021-02-204,257,873222,415,752
2024-07-08 to 2024-07-162,762,057208,323,881
2024-05-16 to 2024-05-231,047,79356,049,494
2024-05-28 to 2024-06-011,045,16031,201,237
2021-09-14 to 2021-09-15523,9608,815,014
2023-06-22447,3575,643,511
2023-02-01 to 2023-02-05444,49324,471,529
2025-03-04 to 2025-03-05416,1457,383,842
2019-06-09 to 2019-06-11384,42811,215,244
2023-03-03345,6383,150,291

The map's outage-history layer shows each county's customer-hours without power per 1,000 residents per year, 2018 to 2025. EAGLE-I sometimes assigns a utility's outages to the wrong county, so county figures are approximate and are not ranked here; 43 county-years with more customers out than a county plausibly has are left out.

Emergency incidents reported to the U.S. Department of Energy

Utilities and ERCOT must report major outages, load shedding, public appeals to save power, suspicious activity and physical or cyber attacks on grid equipment to the U.S. Department of Energy within hours (Form OE-417). Rows naming Texas or the Texas RE region are counted; some cover several states. Texas reports by year: 2014: 20, 2015: 21, 2016: 14, 2017: 14, 2018: 15, 2019: 39, 2020: 48, 2021: 91, 2022: 52, 2023: 59, 2024: 76, 2025: 32. By kind: severe weather 186, vandalism, physical or cyber attack 92, system operations (control-centre events) 49, suspicious activity (no attack reported) 49, other 44, load shed or loss of service 33, fuel or generation shortfall 13, public appeal to save power 11, transmission or equipment 4. One incident can be reported more than once, and many reports give customers as unknown.

BeganArea (as reported)TypeCustomers affected (as reported)
2021-02-10Texas:Severe Weather2,000,000
2021-02-15Texas: Harris County;Severe Weather1,390,000
2017-08-27Texas: Harris County;Severe Weather1,076,868
2017-08-26Texas:Severe Weather1,076,868
2021-02-16Texas:Severe Weather840,000
2024-05-16Harris County, TexasWeather or natural disaster807,584
2021-09-14Texas: Harris County;Severe Weather705,415
2024-05-28McLennan County, Texas; Dallas County, Texas; Hill County, Texas; Bell County, Texas; Kaufman County, Texas; Brown CountWeather or natural disaster650,000
2020-08-27Texas: Louisiana:Severe Weather615,992
2019-06-09Texas: Collin County, Dallas County, Denton County, Palo Pinto County, Tarrant County, Ellis County, Williamson County;Severe Weather558,000

How reliable are Texas utilities?

Average minutes without power per customer in 2025, as each utility reported to the U.S. Energy Information Administration (Form EIA-861) for its Texas customers. "All events" counts every day; "without major event days" removes the rare worst days (usually big storms), picked by the statistical threshold the IEEE 1366 standard defines. Utilities marked "own standard" measure differently, so their figures are not directly comparable. These official figures differ from the outage-map estimates above.

UtilityTexas customersMinutes out, all eventsMinutes out, without major event daysInterruptions per customer
Oncor Electric Delivery Company LLCutility's own standard4,084,817232671.55
CenterPoint Energy2,898,2921931511.954
City of San Antonio - (TX)940,662111751.54
AEP Texas Central Company921,5642051551.761
Austin Energy575,518182771.29
Entergy Texas Inc.539,0434033052.579
Pedernales Electric Coop, Inc441,00790781.156
El Paso Electric Co363,34155550.858
Denton County Elec Coop, Inc333,69049370.399
Texas-New Mexico Power Coutility's own standard274,2821651191.501
Southwestern Public Service Co270,1494411511.71
AEP Texas North Company200,4761331061.407
Southwestern Electric Power Co192,8874673122.979
Magic Valley Electric Coop Inc149,858288231not reported
Tri-County Electric Coop, Inc (TX)144,3222031321.67

Rooftop solar and other small generators, by utility

Each year Texas utilities report to the PUCT every small generator connected to their distribution lines. These totals come from the 2025 reports.

UtilitySystems at the end of 2025Solar MW (incl. with batteries)Battery-only MWGas and diesel MWSystems added in 2025
Oncor122,7671,323211779not reported separately
CenterPoint Energy Houston Electric63,0575862094519,602
AEP Texas28,2803024721071,593
El Paso Electric27,6461530151,200
TNMP7,142230026835

Distributed generation = small generators connected to the local distribution system: mostly rooftop solar, plus batteries and some gas and diesel units. Capacity is the nameplate each utility reported, summed by fuel. End of 2025 = systems in service before 2025 plus those added in 2025 (Oncor reports one list through December 31, 2025). Rows marked superseded, cancelled or withdrawn are left out; TNMP's 2025 count includes some capacity additions to existing systems. TNMP's 'Other' capacity columns are left out because they appear to mix kW and kWh. Categories follow each utility's own sheets (in service, added in 2025, pending, removed); utilities organise their reports differently, so compare utilities with care. Not included (reports filed as PDF only): Entergy Texas (PDF only), SWEPCO (PDF only), SPS (PDF only).

Substations in FEMA flood zones

We checked the FEMA flood zone at the centre of each of the 6,257 mapped substations. 304 sit in a 1% annual chance flood area (the "100-year floodplain"), including 27 in a floodway and 3 in a coastal high-hazard zone, and 180 more in a 0.2% annual chance area. Another 69 are behind levees that FEMA credits with reducing the risk. 1,692 are in places with no digital FEMA flood map, so their risk is unknown, not low. Click a substation to see its zone.

FEMA maps show flood risk for insurance and planning; they do not show past flooding, and many floods happen outside mapped zones.

Transmission projects from utilities' own (archived) web pages

Utilities post pages for transmission projects while they are planned and built, then often take them down. We read 78 such pages from the Internet Archive (CPS Energy 44, CenterPoint Energy 3, Oncor 30, TNMP 1). Rows with a stated date or PUCT docket are listed; dates are what the utility said at the time.

ProjectUtilitykVStated datePUCT docketArchived page
blossom substationCPS Energy138June 20172021-10-19
buckeye la heights transmission line rebuildCPS Energy138May 20212020-11-30
coliseum to kirby transmission lineCPS Energy138June 20172021-10-19
five points to westside transmission projectCPS Energy138June 20172021-10-19
howard solstice transmissionCPS Energy765593362026-03-05
howard to san miguel transmissionCPS Energy571152026-07-11
hunt lane to pinn road transmission line rebuild projectCPS Energy138June 20172021-10-19
hunt lane to pinn road transmission rebuildCPS Energy13820222021-12-02
merida to westside trans line rebuild projectCPS Energy138May 20192021-10-19
omicronCPS Energy138582762026-07-11
padua transmission line projectCPS Energy138543082024-10-04
pawnee to tangoCPS Energy345582532026-07-11
potranco substationCPS Energy138summer 20182019-07-22
rafter phase two transmission lineCPS Energy138April 20202020-03-30
rafter substationCPS Energy138June 20182019-08-24
ranchtown to talley roadCPS Energy138572062026-07-11
sat15 substation transmission lineCPS Energy557282026-07-11
scenic loop projectCPS Energy138510232024-10-09
spruce to pawnee transmission lineCPS Energy345578492026-07-11
tezel substationCPS Energyend of 20242024-10-09
oyster creek transmission projectCenterPoint Energy138417492017-02-05
bell county east big hill 765Oncor345, 765summer 20302026-04-21
border switch to clearfork switchOncor34520292026-02-14
double creek to primeOncor138Summer 20282026-04-17
plowboy to oak spring 138kvOncor13820282026-04-17
porterville to shifting sands 138kvOncor138end of 20282026-04-17
quarry field to kyle ranch 138 kvOncor138493022022-07-13

Dates and voltages are as the utility stated them on the date the page was captured; a planned date is a plan, not a fact. Archived copies can be incomplete. Each row links to the archived page so the wording can be checked.

What Texas fossil plants actually produced, hour by hour

The U.S. Environmental Protection Agency measures the output of every large fossil-fuel unit in Texas each hour, for its air-pollution programs. Click a gas or coal plant on the map to see its yearly output, its busiest hour, how often it started up, and its output through Winter Storm Uri. These are gross figures measured at the generator; the plant's own use is included, so they run a little above EIA's net generation.

Winter Storm Uri: fossil output, February 10-20, 2021

Fossil plants in EPA's data reached 64,641 MW at Feb 14, 18:00 (local standard time). During February 15-18, when ERCOT ordered rotating outages, their output fell as low as 40,396 MW (Feb 16, 13:00). Wind, solar, nuclear and small units are not in EPA's data, so this is not total Texas generation.

032,32164,641Feb 10Feb 11Feb 12Feb 13Feb 14Feb 15Feb 16Feb 17Feb 18Feb 19Feb 20
Total gross output of Texas fossil units in EPA's data, MW each hour. Source: EPA CAMPD.
Daily table
DayHighest hour, MWLowest hour, MW
Feb 1053,34238,416
Feb 1159,25345,388
Feb 1263,22847,491
Feb 1363,08053,505
Feb 1464,64150,557
Feb 1561,96642,645
Feb 1646,34240,396
Feb 1748,65841,245
Feb 1850,89840,895
Feb 1954,58329,879
Feb 2044,37721,134

Largest fossil plants by measured output, 2025

PlantGross GWhBusiest hour, MWStartsCO₂, million tons
W A Parish16,7513,60818015.6
Oak Grove12,0551,8384012.5
Forney Power Plant10,2592,0059844.4
Martin Lake9,3571,749449.6
Sam Seymour9,0771,7041210.2
Limestone8,2721,781209.1
Odessa Ector Generating Station8,2451,2202483.4
Channelview Cogeneration Facility8,2091,268253.4
Deer Park Energy Center8,0461,3401294.6
Temple Power Station7,9071,556483.7
Montgomery County Power Station7,1531,076192.9
Midlothian Energy7,0921,7619283.2

Starts count unit start-ups across all of a plant's units. CO₂ as EPA reports it, in short tons.

New gas plants backed by the Texas Energy Fund

Texas voters created the Texas Energy Fund in 2023 to finance new dispatchable power plants. As of 2026-11-20, the PUCT lists 9 executed loans for 5,446 MW and 5 completion bonus grants for 1,438 MW. Click a plant on the EIA layer to see its loan or grant.

Loans
ProjectPlaceMWOperationsAmount
Rock Island Generation ProjectKerrville Public Utility BoardColorado County, about 10 miles south of Columbus122Summer 2027$105 million
T H Wharton expansion (northwest Houston)NRG Energy, Inc.Harris County456May 26, 2026$216 million
New unit at the Cedar Bayou Generating StationNRG Energy, Inc.Chambers County (near Baytown)721Summer 2028$562 million
Pin Oak Creek Energy CenterConstellation Energy Generation, LLC (Calpine)Freestone County460April 29, 2026$278 million
CPV Basin RanchCompetitive Power VenturesWard County1,3502029$1.12 billion
Expansion at the Greens Bayou Generating StationNRG Energy, Inc.Harris County4552028$370 million
Rayburn Energy Station IIRayburn Country Electric Cooperative, Inc.Sherman (Grayson County)5702028$411 million
Two new units at the Permian Basin Power PlantVistra Corp.Ward County8602028$583.3 million
Pecos Power PlantMercuria Investments U.S., Inc. and Continental Resources, Inc. (Pecos Power Plant LLC)Reeves County4522027$459 million
Completion bonus grants
ProjectPlaceMWOperationsAmount
Timmerman Power Plant (first unit)Lower Colorado River AuthorityCaldwell County188August 14, 2025$22,560,000 over 10 years
Timmerman Unit 2Lower Colorado River AuthorityCaldwell County188April 16, 2026$22,560,000 over 10 years
Pin Oak Creek Energy CenterCalpine (Constellation)Freestone County460April 29, 2026$55,200,000 over 10 years
T H Wharton expansionNRG Energy, Inc.Harris County456May 26, 2026$54,720,000 over 10 years
Friendswood Energy Center expansionTejas Power Generation, LLC (Shell Energy North America)Harris County146May 21, 2026$17,520,000 over 10 years

Loans and grants the PUCT has executed. Sizes and operating dates are as the PUCT lists them; a planned date can slip. Each EIA plant link is to a plant the release names. Rayburn Energy Station II and the Pecos Power Plant are not yet in EIA's inventory. Some projects received both a loan and a completion bonus grant (T H Wharton, Pin Oak Creek); do not add the two tables together.

Energy projects with Texas school-tax agreements (Chapter 313)

Until it closed to new applications at the end of 2022, Chapter 313 of the Texas Tax Code let school districts cap the taxable value of large new projects. 367 solar, wind, storage and power projects reached signed agreements (421 agreements: a project crossing several school districts signs one with each). The Comptroller posts each company's application, which states the project's county, size and planned start. We read those applications and checked each project against the U.S. EIA plant list.

TechnologyProjectsAgreementsMW stated in applications (each project once)EIA lists as operatingEIA lists as planned
Solar21222444,122188 of 212 state a size4819
Wind15119222,66299 of 151 state a size353
Other or unclear456942 of 4 state a size20

County, MW and planned start come from the company's application and may have changed later. An agreement does not prove the project was built. A project with no EIA match may have been renamed, combined with another phase, cancelled or not yet reported. Open a county on the outage layer to see its projects.

Reliability needs in ERCOT's transmission plans

Each year ERCOT's Regional Transmission Plan lists the transmission projects its studies find are needed to keep the grid reliable over the next six years. Many are placeholders that utilities later turn into tracked projects; a listing is not an approval or a schedule. The 2024 list is ERCOT's 345-kV plan appendix. Listings by plan year: 2015: 62, 2016: 40, 2017: 62, 2018: 40, 2019: 58, 2020: 51, 2021: 67, 2022: 89, 2023: 173, 2024: 237, 2025: 192. Counties named most often in the 2021 to 2025 plans (a project listed in several years counts each time): Dallas (90), Travis (34), Ellis (31), Pecos (31), Bell (30), Howard (30), Reeves (28), Midland (26), Mitchell (23), Tarrant (21).

Texas substations with the most transformer capacity

In-service transformer capacity reported by investor-owned utilities on FERC Form 1 page 426, for substations matched one-to-one to the map. Co-op and city substations do not file FERC Form 1 and are not ranked.

SubstationUtility (filing year)MVA in serviceTransformersVoltages (kV)
Sheffield SubstationAEP Texas Inc. (2025)10,0121269 / 7.56
Bellaire SubstationCenterPoint Energy Houston Electric, LLC (2025)3,3409345 / 138 / 35 / 23 / 12
Lon Hill SubstationAEP Texas Inc. (2025)2,83011345 / 138 / 70.5 / 69 / 13.8 / 12.47 / 12 / 7.62
Jones Creek SubstationCenterPoint Energy Houston Electric, LLC (2025)2,5005345 / 138 / 23 / 12
Mulberry Creek SubstationAEP Texas Inc. (2025)2,16016345 / 138 / 34.5 / 13.8
Cypress SubstationEntergy Texas, Inc. (2025)2,1004500 / 230 / 13.8
North Belt SubstationCenterPoint Energy Houston Electric, LLC (2025)2,0005345 / 138 / 35 / 23
White Oak SubstationCenterPoint Energy Houston Electric, LLC (2025)1,7978345 / 138 / 69 / 23 / 12
Jeanetta SubstationCenterPoint Energy Houston Electric, LLC (2025)1,7475345 / 138 / 23 / 12
Addicks SubstationCenterPoint Energy Houston Electric, LLC (2025)1,7005345 / 138 / 35 / 23
Rothwood SubstationCenterPoint Energy Houston Electric, LLC (2025)1,6002345 / 138 / 23
Hartburg SubstationEntergy Texas, Inc. (2025)1,5852500 / 230 / 13.8
Grimes SubstationEntergy Texas, Inc. (2025)1,5764345 / 230 / 34.5 / 13.8
Odessa EHV SubstationOncor Electric Delivery Company LLC (2025)1,4963345 / 138 / 14 / 12
Stewart Road SubstationAEP Texas Inc. (2025)1,3833345 / 138 / 69 / 34.5 / 13.8 / 12

Frequently asked questions

What does the Texas Grid Atlas show?

A map of the Texas power grid: high-voltage transmission lines colored by voltage, substations and power plants as mapped in OpenStreetMap, with line names, owners and ages from public records, substation transformer capacity from FERC Form 1, ERCOT generating-unit capacity, every Texas power plant from the EIA generator inventory, ERCOT wholesale prices and binding transmission constraints, and source-linked PUCT transmission project costs.

How old are Texas transmission lines?

Only lines with a public record get an age on the map: an in-service year from FERC Form 1, ERCOT's transmission project tracker or a PUCT construction report. Many Texas lines were built decades before electronic records begin in 1994, so most mapped miles are still marked not documented rather than estimated.

Does the map show power outages?

No. ERCOT's detailed transmission outage schedules are restricted to market participants, and a congested line or a dark area in the nighttime imagery is not evidence of an outage. For outages at your home, check your local utility's outage map.

What does transmission congestion mean in ERCOT?

A transmission constraint binds when ERCOT's dispatch has to keep flow on a line or transformer at its limit, so cheaper power cannot reach where it is needed and prices separate across the grid. The map flags elements that bound in ERCOT's day-ahead market over the last 31 days and in real-time dispatch over the last 7 days, together with ERCOT's enforced limit in MW.

Where does the data come from?

OpenStreetMap for the mapped lines, substations and plants; FERC Form 1 for line and substation records of investor-owned utilities; the Public Utility Commission of Texas for monthly construction reports, CCN dockets and project costs; and ERCOT for prices, constraints, the transmission project tracker, the interconnection queue and the generating-unit list; and the U.S. Energy Information Administration (Form EIA-860M) for every Texas generator's capacity, in-service year and planned retirement. Every value in the map names its source.

Can I download the data?

Yes. Every layer and record set is available as GeoJSON, JSON or CSV from the Download menu, with a manifest of file hashes. Map data derived from OpenStreetMap is under the Open Database License.

Wholesale prices on the map

The price layer reads ERCOT's public market reports directly: real-time locational marginal prices from each security-constrained economic dispatch (SCED) run, real-time 15-minute settlement point prices, and hourly day-ahead settlement point prices. Each is labeled with its price type, interval, age and source. These are the latest public postings, delayed by ERCOT's publication schedule, not a live feed.

ERCOT does not publish coordinates for its price nodes. Power Hopper places a price only where ERCOT's public bus mapping names a substation that matches exactly one OpenStreetMap substation with an agreeing voltage (about 580 substations); every other node is counted but not drawn, and nothing is interpolated between points. Compare with ERCOT's official LMP contour map.

Congestion

The congestion layer lists ERCOT's latest binding transmission constraints (report NP6-86-CD). A binding constraint means a line or transformer limit was binding in a dispatch run. It is not evidence of an outage or equipment failure. ERCOT's detailed transmission outage schedules are restricted to market participants and are not used here, so asset panels say "No asset-specific outage verified from accessible public records" rather than "no outages".

Transmission projects

The projects layer draws ERCOT's Transmission Project and Information Tracking list (2,208 projects, 2026-11-17), colored by status. A project is drawn on a mapped line only when both of its terminal substations match OpenStreetMap by name, voltage and county, and either one mapped line joins them or exactly one mapped corridor of reasonable length does; otherwise only its terminals, or nothing, is shown. ERCOT's public edition of this list has no per-project cost; costs come from the PUCT and ERCOT documents below.

Transmission project costs

Utilities that build Texas transmission file a monthly construction progress report with the Public Utility Commission of Texas under 16 TAC §25.83. For each project that needed a certificate of convenience and necessity (CCN), the report gives the cost estimate in the CCN application, the final estimate when construction started and, about six months after completion, the final actual cost, split into line and substation facilities. Power Hopper reads those filed workbooks (382 filings from 2020-01-15 to 2025-06-16), keeps every figure tied to its filing, sheet and cell, checks that the components add up, has an independent reviewer re-read a sample of the source files, and publishes only figures that pass. Estimates and final actual costs are never mixed, and a cost per mile is shown only when the cost and the miles describe the same facilities.

Texas transmission projects with verified cost records (101 projects; largest 60 shown, all in the CSV)
ProjectHeadline costPer mileStatusEvidence
Texas 765-kV STEP Eastern Backbone ProjectAEP Texas; CPS Energy; Oncor Electric Delivery; CenterPoint Energy Houston Electric · 765 kV · PUCT n/a $9.384 billionERCOT planning estimate; line plus substation $8,463,203per circuit-mile ERCOT staff recommended Board endorsement (Board meeting Dec 8-9, 2025). The Board vote itself and the PUCT CCN filings were not verified in this pilot. Source, page 17Verified estimate
Oncor Southern DFW Load Interconnection and General Grid Strengthening Project (Option 3)Oncor Electric Delivery · 345 kV · PUCT n/a $2.886 billionERCOT planning estimate; whole project as reported unavailable ERCOT staff recommended Board endorsement (Board meeting April 20-21, 2026). The Board vote itself was not verified in this pilot. Source, page 1Verified estimate
Howard to Solstice 765-kV transmission lineAEP Texas Inc.; City of San Antonio, acting by and through the City Public Service Board (CPS Energy) · 765 kV · PUCT 59336 $2.153 billionPUCT-approved route estimate; line facilities only $5,843,387per circuit-mile PUCT order approving route 4 mod 1 filed 2026-09-18. The docket's filing list shows an 'Order extending time to act on motions for rehearing' filed 2026-11-05 (item 2800), so rehearing was still pending at that date. The rehearing order itself was not reviewed in this pilot. Source, page 22Verified estimate
Euclid 765-kV Substation and Transmission Line AdditionLCRA Transmission Services Corporation; CenterPoint Energy Houston Electric · 765 kV · PUCT n/a $1.831 billionERCOT planning estimate; line plus substation $13,934,551per circuit-mile ERCOT staff recommended Board endorsement (Board meeting June 2026). The Board vote itself and any PUCT CCN filing were not verified in this pilot. Source, page 14Verified estimate
Drill Hole to Sand Lake to Solstice 765-kV Line ProjectOncor Electric Delivery; American Electric Power Service Corporation (AEPSC) · 765 kV · PUCT n/a $742.2 millionERCOT planning estimate; line plus substation $7,109,195per circuit-mile ERCOT staff recommended Board endorsement (Board meeting Dec 8-9, 2025). The Board vote itself and any PUCT CCN filing were not verified in this pilot. Source, page 12Verified estimate
Ramhorn Hill - Dunham 345 kV Transmission LineOncor Electric Delivery · 345 kV · PUCT 55067 $264.7 millionFinal estimate (construction start); line facilities only $6,347,709per circuit-mile Construction underway (7% complete, 2025-06-13)Not publicly verified PUCT filing, cell I1385Verified estimate
Odessa EHV - Riverton and Moss - Riverton 345 kV LineOncor Electric Delivery · 345 kV · PUCT 48095 $248.6 millionFinal estimate (construction start); line facilities only $1,147,074per circuit-mile Completed 2020-12-202020-12-20 PUCT filing, cell I1188Verified estimate
North McCamey - Sand Lake 345 kV LineOncor Electric Delivery · 345 kV · PUCT 55121 $167.3 millionFinal estimate (construction start); line facilities only $950,388per circuit-mile Construction underway (5% complete, 2025-06-13)Not publicly verified PUCT filing, cell I1383Verified estimate
Cruce - Reforzar 345-kV Double-Circuit T-LineAEP Texas · 345 kV · PUCT 55397 $150.3 millionCCN application estimate; whole project as reported unavailable Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H144Verified estimate
Del Sol - Frontera 345-kV T-LineAEP Texas · 345 kV · PUCT 55001 $127.2 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (20% complete, 2025-06-13)Not publicly verified PUCT filing, cell I103Verified estimate
Cruce - Del Sol 345-kV Double-Circuit T-LineElectric Transmission Texas · 345 kV · PUCT 55151 $112.5 millionCCN application estimate; whole project as reported unavailable Construction underway (5% complete, 2025-06-13)Not publicly verified PUCT filing, cell H13Verified estimate
Leander - Round Rock TL Addition (CCN)LCRA Transmission Services Corporation · 138 kV · PUCT 45866 $111.9 millionFinal actual cost; whole project as reported unavailable Completed 2020-06-042020-06-04 PUCT filing, cell J3Verified final actual
Cruce - Del Sol 345-kV Double-Circuit T-LineAEP Texas · 345 kV · PUCT 55151 $107.2 millionCCN application estimate; whole project as reported unavailable Construction underway (5% complete, 2025-06-13)Not publicly verified PUCT filing, cell H136Verified estimate
Cenizo - Cruce 345-kV Double-Circuit T-LineAEP Texas · 345 kV · PUCT 55296 $100.7 millionCCN application estimate; whole project as reported unavailable Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H209Verified estimate
Drill Hole Switch - El Capitan Switch 345 kV Transmission LineOncor Electric Delivery · 345 kV · PUCT 57828 $97.5 millionCCN application estimate; line facilities only $2,298,774per circuit-mile Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1400Verified estimate
Drill Hole Switch - Riverton Switch 345 kV Transmission LineOncor Electric Delivery · 345 kV · PUCT 58007 $88.0 millionCCN application estimate; line facilities only $1,929,781per circuit-mile Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1403Verified estimate
Ogallala - Abernathy 345 kV LineOncor Electric Delivery · 345 kV · PUCT 48625 $76.7 millionFinal actual cost; line facilities only $1,324,567per circuit-mile Completed 2021-06-212021-06-21 PUCT filing, cell J1245Verified final actual
Mountain Home TL Addition (CCN)LCRA Transmission Services Corporation · 138 kV · PUCT 49523 $76.5 millionFinal actual cost; whole project as reported unavailable Completed 2022-12-27Not publicly verified PUCT filing, cell J2Verified final actual
Del Sol - Frontera 345-kV T-LineElectric Transmission Texas · 345 kV · PUCT 55001 $75.1 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (20% complete, 2025-06-13)Not publicly verified PUCT filing, cell I10Verified estimate
Angstrom - Naismith 345-kV T-LineAEP Texas · 345 kV · PUCT 52656 $72.5 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (99% complete, 2025-06-13)2025-12-14 (estimated) PUCT filing, cell I61Verified estimate
Riverton Switch - Sand Lake Switch 138 kV Transmission LineOncor Electric Delivery · 138 kV · PUCT 57633 $70.9 millionCCN application estimate; line facilities only $1,771,375per circuit-mile Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1397Verified estimate
Sand Lake - Solstice 345 kV LineOncor Electric Delivery · 345 kV · PUCT 48785 $68.9 millionFinal estimate (construction start); line facilities only unavailable Completed 2020-12-282020-12-28 PUCT filing, cell I1189Verified estimate
Brackettville - Escondido 138-kV T-LineAEP Texas · 138 kV · PUCT 50545 $68.6 millionFinal actual cost; whole project as reported unavailable Completed 2024-02-232023-12-21 PUCT filing, cell J23Verified final actual
Far West Texas Project: Solstice to Bakersfield 345-kV T-LineAEP Texas · 345 kV · PUCT 48787 $66.2 millionFinal actual cost; whole project as reported unavailable Completed 2020-11-202020-12-20 PUCT filing, cell J32Verified final actual
Riverton - Sand Lake 345 kV Line (Operating at 138 kV)Oncor Electric Delivery · 138 kV · PUCT 47368 $64.7 millionFinal estimate (construction start); line facilities only $1,630,187per circuit-mile Completed 2019-12-302019-12-30 PUCT filing, cell I685Verified estimate
Watermill Switch - Wilmer Switch 345 kV Transmission LineOncor Electric Delivery · 345 kV · PUCT 57918 $63.3 millionCCN application estimate; line facilities only $7,193,182per circuit-mile Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1402Verified estimate
Frontera 345-kV StationAEP Texas · 345 kV · PUCT 55001 $63.0 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (15% complete, 2025-06-13)Not publicly verified PUCT filing, cell I104Verified estimate
Angstrom-Grissom 345-kV T-LineAEP Texas · 345 kV · PUCT 51912 $62.8 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (85% complete, 2025-06-13)Not publicly verified PUCT filing, cell I13Verified estimate
Ajo - Reforzar 345-kV Double-Circuit T-LineAEP Texas · 345 kV · PUCT 55573 $61.8 millionCCN application estimate; whole project as reported unavailable Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H225Verified estimate
Poesta - Tuleta 138-kV T-LineAEP Texas · 138 kV · PUCT 49347 $60.4 millionFinal estimate (construction start); whole project as reported unavailable Energized 2024-08-292024-08-29 PUCT filing, cell I12Verified estimate
Bearkat Switching Station to Oncor Switching Station Transmission Line ProjectWind Energy Transmission Texas · 345 kV · PUCT 50410 $51.8 millionFinal estimate (construction start); line facilities only unavailable Approved; construction not started as of 2022-07-14Not publicly verified PUCT filing, cell I6Verified estimate
Zorn - Marion TL Addition (CCN)LCRA Transmission Services Corporation · 345 kV · PUCT 45601 $48.6 millionFinal actual cost; whole project as reported unavailable Completed 2019-05-302019-05-30 PUCT filing, cell J3Verified final actual
Solstice Expansion for 345-kV StationAEP Texas · 345 kV · PUCT 48787 $48.4 millionFinal actual cost; whole project as reported unavailable Completed 2020-12-312020-12-20 PUCT filing, cell J31Verified final actual
Cooks Point TL Addition (CCN)LCRA Transmission Services Corporation · 138 kV · PUCT 48358 $47.0 millionFinal actual cost; whole project as reported unavailable Completed 2021-06-302021-06-30 PUCT filing, cell J2Verified final actual
Far West Texas Project: Solstice to Sand Lake 345-kV T-LineAEP Texas · 345 kV · PUCT 48785 $45.8 millionFinal actual cost; whole project as reported unavailable Completed 2020-11-202020-12-16 PUCT filing, cell J33Verified final actual
Tuleta to Coleto Creek 138-kV Dbl Ckt LineAEP Texas · 138 kV · PUCT 44837 $45.7 millionFinal actual cost; whole project as reported unavailable Energized 2019-09-272019-09-27 PUCT filing, cell J9Verified final actual
Poesta - Three Rivers 138-kV T-LineAEP Texas · 138/69 kV · PUCT 49347 $45.0 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (50% complete, 2023-11-20)Not publicly verified PUCT filing, cell I126Verified estimate
Horseshoe Springs - Owl Hills 138 kV LineOncor Electric Delivery · 138 kV · PUCT 48544 $40.3 millionFinal estimate (construction start); line facilities only $1,348,250per circuit-mile Completed 2020-02-112020-02-11 PUCT filing, cell I687Verified estimate
Border Switch - Quarry Field Switch 345 kV Transmission LineOncor Electric Delivery · 345 kV · PUCT 57837 $36.1 millionCCN application estimate; line facilities only $1,770,049per circuit-mile Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1401Verified estimate
Stewart Rd. 345-kV Station: ExpansionAEP Texas · 345 kV · PUCT 47603 $35.7 millionFinal actual cost; whole project as reported unavailable Completed 2021-10-312021-10-18 PUCT filing, cell J3Verified final actual
Bearkat - Longshore 345 kV LineOncor Electric Delivery · 345 kV · PUCT 50410 $34.8 millionFinal estimate (construction start); line facilities only unavailable Completed 2023-12-012023-12-01 PUCT filing, cell I1190Verified estimate
Lufkin Switch - Redland Switch 345 kV LineOncor Electric Delivery · 345 kV · PUCT 55172 $34.5 millionFinal estimate (construction start); line facilities only $4,356,272per circuit-mile Construction underway (2% complete, 2025-06-13)Not publicly verified PUCT filing, cell I1384Verified estimate
Exchange Switch - Roanoke Switch 138/345 kV Transmission Line RebuildOncor Electric Delivery · 345/138 kV · PUCT 55575 $34.4 millionCCN application estimate; line facilities only unavailable Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1387Verified estimate
Bernoulli Switching station and 345kV Transmission line to Lacy Creek Collector stationWind Energy Transmission Texas · 345 kV · PUCT 52977 $33.8 millionCCN application estimate; line facilities only $2,467,445per circuit-mile Construction underway (55% complete, 2022-07-14)Not publicly verified PUCT filing, cell H7Verified estimate
Ranger Camp Switch - Cattleman Switch 345 kV Transmission LineOncor Electric Delivery · 345 kV · PUCT 57519 $33.5 millionFinal estimate (construction start); line facilities only $3,982,794per circuit-mile Approved; construction not started as of 2025-06-13Not publicly verified PUCT filing, cell I1393Verified estimate
Glaze Lake Switch 138 kV Loop Transmission LineOncor Electric Delivery · 138 kV · PUCT 57723 $32.2 millionCCN application estimate; line facilities only $1,608,400per circuit-mile Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1398Verified estimate
Del Sol 345-kV StationElectric Transmission Texas · 345 kV · PUCT 55001 $30.3 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (30% complete, 2025-06-13)Not publicly verified PUCT filing, cell I11Verified estimate
Flat Iron Substation – Barr Ranch Switch – Quickriver Tap 138 kV LineOncor Electric Delivery · 138 kV · PUCT 53491 $29.8 millionFinal actual cost; line facilities only $1,568,317per circuit-mile Completed 2023-05-302023-05-30 PUCT filing, cell J1229Verified final actual
Owl Hills - Tunstill POD 138 kV LineOncor Electric Delivery · 138 kV · PUCT 48582 $27.2 millionFinal estimate (construction start); line facilities only $1,456,922per circuit-mile Completed 2020-12-102020-12-10 PUCT filing, cell I964Verified estimate
Blumenthal TL Addition (CCN)LCRA Transmission Services Corporation · 138 kV · PUCT 43599 $26.8 millionFinal actual cost; whole project as reported unavailable Completed 2018-05-182018-05-18 PUCT filing, cell J2Verified final actual
New Bethel 345 kV Loop LineOncor Electric Delivery · 345 kV · PUCT 44672 $26.5 millionCCN application estimate; line facilities only $981,444per circuit-mile Proposed (CCN docket open as of 2024-05-07)Not publicly verified PUCT filing, cell H1091Verified estimate
Stewart Rd. 345-kV HairpinElectric Transmission Texas · 345 kV · PUCT 47973 $25.5 millionFinal actual cost; whole project as reported unavailable Completed 2021-05-192021-05-19 PUCT filing, cell J2Verified final actual
Hartring Substation - Upland Substation 138 kV Transmission LineOncor Electric Delivery · 138 kV · PUCT 57263 $22.7 millionFinal estimate (construction start); line facilities only $1,291,558per circuit-mile Approved; construction not started as of 2025-06-13Not publicly verified PUCT filing, cell I1395Verified estimate
Nacogdoches Southeast Switch - Redland Switch 345 kV LineOncor Electric Delivery · 345 kV · PUCT 54524 $22.2 millionFinal estimate (construction start); line facilities only $1,655,115per circuit-mile Completed 2024-12-262024-12-26 PUCT filing, cell I1381Verified estimate
Resnik - Naismith 138-kV Double Circuit Transmission LineAEP Texas · 138 kV · PUCT 53987 $19.4 millionFinal estimate (construction start); whole project as reported unavailable Construction underway (98% complete, 2025-06-13)Not publicly verified PUCT filing, cell I108Verified estimate
Heartland-Yellowjacket ETTElectric Transmission Texas · 138 kV · PUCT 46234 $19.2 millionFinal actual cost; whole project as reported unavailable Completed 2019-10-212020-06-03 PUCT filing, cell J3Verified final actual
Kyle Ranch - Quarry Field 138 kV LineOncor Electric Delivery · 138 kV · PUCT 49302 $19.0 millionFinal estimate (construction start); substation facilities only unavailable Completed 2020-12-102020-12-10 PUCT filing, cell I725Verified estimate
Riverton - Kyle Ranch 138 kV LineOncor Electric Delivery · 138 kV · PUCT 49304 $18.9 millionFinal actual cost; line facilities only $1,244,768per circuit-mile Completed 2020-12-102020-12-10 PUCT filing, cell J1225Verified final actual
Cogdell - Clairemont 138 kV LineOncor Electric Delivery · 138 kV · PUCT 47808 $18.6 millionFinal estimate (construction start); line facilities only unavailable Completed 2020-12-302020-12-30 PUCT filing, cell I720Verified estimate
Reiter Switch - Tesoro Switch 345 kV Transmission LineOncor Electric Delivery · 345 kV · PUCT 56799 $18.1 millionCCN application estimate; line facilities only $2,058,523per circuit-mile Proposed (CCN docket open as of 2025-06-13)Not publicly verified PUCT filing, cell H1392Verified estimate

Imagery and terrain

Nighttime Lights uses NASA Black Marble imagery served by NASA GIBS: a 2016 annual composite and the most recent single-night NOAA-20 pass. Neither is real time, and a dark area is not evidence of an outage. Terrain uses the public Terrain Tiles dataset on AWS Open Data. Satellite view uses USGS The National Map imagery (public domain). Each loads only when you turn it on.

Not on the map yet

Sources and licensing

Beta. Grid snapshot 2026-11-16T21:22:36Z; layers built 2026-11-17T22:52:53Z; project records generated 2026-11-18T03:48:50.886Z.