Grid and Transmission · Source-checked
Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues
ERCOT reported about 474 GW of large-load requests as of June 2026, about 90% from data centers; it conditionally included 191.8 GW in Batch Zero as of Sept. 3, after a preliminary July 28 screen found about 205 GW eligible. Requests, eligibility, survey responses and company megawatts are different populations and are labeled, not added or subtracted. Verification results and cost-allocation rules were still pending as of Nov. 10, 2026, and no reviewed record shows a household bill effect.
About 474 GW
Large-load requests tracked by ERCOT as of June 2026, about 90% from data centers (ERCOT, Senate Business and Commerce update, July 29, 2026)
Takeaway
- ERCOT reported about 474 GW of large-load requests as of June 2026, about 90% from data centers; it conditionally included 191.8 GW in Batch Zero as of Sept. 3, after a preliminary July 28 screen found about 205 GW eligible. Requests, eligibility, survey responses and company megawatts are different populations and are labeled, not added or subtracted. Verification results and cost-allocation rules were still pending as of Nov. 10, 2026, and no reviewed record shows a household bill effect.
Article: Data centers make up about 90% of ERCOT's 474 GW of large-load requests
Data
172 figures in 22 groups. Each group is one population, date and source; rows from different groups are not added or subtracted.
Large-load request totals (9 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Large-load interconnection requests tracked by ERCOTAll large-load requests | 438 GW (more than) | All large-load requests ERCOT was tracking; nearly 89% from data centers | ERCOT news release on PUCT approval of the Batch Zero processParagraph 3 · REQ-1 | ERCOT: "more than 438,000 MW". Superseded by REQ-6 (about 474 GW as of June 2026, ERCOT Senate B&C July 29); shown as history | |
| Data-center share of large-load requestsData centers | 89 % (nearly) | Same population as REQ-1 | ERCOT news release on PUCT approval of the Batch Zero processParagraph 3 · REQ-2 | ERCOT: "nearly 89 percent"; Power Hopper does not multiply the two rounded figures. Superseded by REQ-7/REQ-8 (about 90%; 420,812 MW, 90.2%); shown as history | |
| Large load preliminarily eligible for Batch ZeroEligible (base, allocated or TBD) | 205 GW (approximately) | Batch Zero eligibility screen; preliminary | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3, Key Takeaways · REQ-3 | Slide bar labels sum to 204 GW because of rounding. Superseded by ERCOT's Sept. 3 conditional classification (BZ-SEP rows: 191.8 GW conditionally included); shown as history | |
| Requested peak interconnection capacity, reviewed RFI dataset429 reviewed loads | 177.4 GW | Community Impact RFI reviewed dataset (243 large, 186 medium loads) | Data Center State and Community Impact RFI: Preliminary SummarySlide 7, Total · REQ-4 | Preliminary, subject to change | |
| Data-center requests in Oncor transmission LC&I interconnection queueOncor service area | 293 GW (approximately) | Oncor active transmission LC&I queue, 795 requests | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · REQ-5 | Company-reported; a utility-level queue, not an ERCOT total | |
| Large-load interconnection requests tracked by ERCOTAll large-load requests | 474 GW (approximately) | All large Loads seeking interconnection, as of June 2026 | ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, Key Takeaway · REQ-6 | ERCOT: "approximately 474 GW"; slide 6 chart totals 474.1 GW (2031) and 474.7 GW (2032-2033) | |
| Data-center share of large-load requestsData centers | 90 % (approximately) | Same population as REQ-6 | ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, Key Takeaway · REQ-7 | ERCOT: "~90% are data centers" | |
| Data-center large-load requests (ERCOT pie value)Data centers | 420812 MW | Large Loads by Project Type, as of June 2026 | ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, pie chart label "90.2% (420812 MW)" · REQ-8 | ERCOT pie value; implied base ≈466.5 GW differs from 474.7 GW total; not reconciled by ERCOT | |
| Large load observed energizedObserved energized | 5.9 GW | Actual and projected large-load growth table, 2026 column | ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, table row "Observed Energized" · REQ-9 | Cumulative observed energized large load shown by ERCOT |
Batch Zero conditional classification, Sept. 3 (8 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Large-load requested capacity by Batch Zero conditional classificationConditionally included (base + studied) | 191.8 GW | Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026 | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026; ERCOT Updates presentation, PUCT open meeting (PUCT Project No. 59142, Item 55)Slides 1, 5, 6; PUCT Project No. 59142, Item 55, Batch Zero eligibility overview slide (Key Takeaways) · BZ-SEP-INC-GW | ERCOT, PUCT Project No. 59142, Item 55 (Sept. 11, 2026): "191.8 GW in Batch Zero, combined base and studied load" (equals slide 6 values 66.4 GW + 125.4 GW); ERCOT slide 5: "362 Large Loads in either base or studied load categories"; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes | |
| Large loads / projects by Batch Zero conditional classificationConditionally included (base + studied) | 362 large loads (projects) | Same as BZ-SEP GW rows | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-INC-N | ||
| Large-load requested capacity by Batch Zero conditional classificationConditionally included as base load | 66.4 GW | Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026 | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-BASE-GW | Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes | |
| Large loads / projects by Batch Zero conditional classificationConditionally included as base load | 204 large loads (projects) | Same as BZ-SEP GW rows | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-BASE-N | ||
| Large-load requested capacity by Batch Zero conditional classificationConditionally included as studied load | 125.4 GW | Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026 | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-STU-GW | 125.4 GW on slide 6 chart; 127.9 GW in slide 1 key-takeaway text; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes | |
| Large loads / projects by Batch Zero conditional classificationConditionally included as studied load | 158 large loads (projects) | Same as BZ-SEP GW rows | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-STU-N | ||
| Large-load requested capacity by Batch Zero conditional classificationExcluded from Batch Zero | 302.2 GW | Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026 | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-EXC-GW | Slide 6: "This chart omits excluded load (302.2 GW, 373 projects)"; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes | |
| Large loads / projects by Batch Zero conditional classificationExcluded from Batch Zero | 373 large loads (projects) | Same as BZ-SEP GW rows | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-EXC-N |
Batch Zero verification review (4 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Size threshold for ERCOT pause on approvals to energize new data centers and crypto mining facilitiesPause threshold | 75 MW or greater | New Large Load data centers and virtual currency mining facilities not yet connected | Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 3-4 · PAUSE-75 | Paused until completion of the verification and audit and the community impact review (ERCOT, Sept. 14-15 board) | |
| Developers whose first-round verification responses ERCOT reviewedDevelopers | 257 developers | Batch Zero verification | Batch Zero Eligibility Verification Process UpdateSlide 2 · V-1 | ||
| Share of developers ERCOT expects to send second-round RFIsDevelopers | 80 % | Batch Zero verification | Batch Zero Eligibility Verification Process UpdateSlide 2 · V-2 | ||
| First-round questions reviewedQuestions | 5140 questions (approximately) | Batch Zero verification | Batch Zero Eligibility Verification Process UpdateSlide 2 · V-3 |
Batch Zero preliminary screen, July 28 (superseded) (10 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Large-load requests by preliminary Batch Zero eligibilityEligible as base load | 65 GW (rounded slide label) | Eligible | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-150 | ||
| Projects by preliminary Batch Zero eligibilityEligible as base load | 150 projects | Eligible | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-150 | ||
| Large-load requests by preliminary Batch Zero eligibilityEligible, base or allocated to be determined | 25 GW (rounded slide label) | Eligible | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-49 | ||
| Projects by preliminary Batch Zero eligibilityEligible, base or allocated to be determined | 49 projects | Eligible | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-49 | ||
| Large-load requests by preliminary Batch Zero eligibilityEligible as allocated load | 114 GW (rounded slide label) | Eligible | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-127 | ||
| Projects by preliminary Batch Zero eligibilityEligible as allocated load | 127 projects | Eligible | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-127 | ||
| Large-load requests by preliminary Batch Zero eligibilityNot included: no dynamic model by July 10 | 20 GW (rounded slide label) | Not included | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-47 | ||
| Projects by preliminary Batch Zero eligibilityNot included: no dynamic model by July 10 | 47 projects | Not included | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-47 | ||
| Large-load requests by preliminary Batch Zero eligibilityNot included: no qualifying study | 274 GW (rounded slide label) | Not included | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-315 | ||
| Projects by preliminary Batch Zero eligibilityNot included: no qualifying study | 315 projects | Not included | ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-315 |
Data center survey: by load zone (12 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Requested peak interconnection capacity by ERCOT load zoneWest | 73 GW (rounded) | 429 reviewed loads; zone from facility GPS | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-West-GW | 37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded | |
| Large loads (75 MW or more) by load zoneWest | 88 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-West-LL | ||
| Medium loads (under 75 MW) by load zoneWest | 39 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-West-ML | ||
| Requested peak interconnection capacity by ERCOT load zoneSouth | 49 GW (rounded) | 429 reviewed loads; zone from facility GPS | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-South-GW | 37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded | |
| Large loads (75 MW or more) by load zoneSouth | 72 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-South-LL | ||
| Medium loads (under 75 MW) by load zoneSouth | 38 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-South-ML | ||
| Requested peak interconnection capacity by ERCOT load zoneNorth | 45 GW (rounded) | 429 reviewed loads; zone from facility GPS | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-North-GW | 37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded | |
| Large loads (75 MW or more) by load zoneNorth | 69 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-North-LL | ||
| Medium loads (under 75 MW) by load zoneNorth | 85 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-North-ML | ||
| Requested peak interconnection capacity by ERCOT load zoneHouston | 10 GW (rounded) | 429 reviewed loads; zone from facility GPS | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-Houston-GW | 37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded | |
| Large loads (75 MW or more) by load zoneHouston | 14 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-Houston-LL | ||
| Medium loads (under 75 MW) by load zoneHouston | 24 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-Houston-ML |
Data center survey: by request size (14 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Requested peak interconnection capacity by request sizeUnder 50 MW | 1.5 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-43-GW | ||
| Loads by request sizeUnder 50 MW | 43 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-43-N | ||
| Requested peak interconnection capacity by request size50 to under 75 MW | 9.8 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-143-GW | ||
| Loads by request size50 to under 75 MW | 143 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-143-N | ||
| Requested peak interconnection capacity by request size75 to under 200 MW | 7.2 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-47-GW | ||
| Loads by request size75 to under 200 MW | 47 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-47-N | ||
| Requested peak interconnection capacity by request size200 to under 500 MW | 31.7 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-89-GW | ||
| Loads by request size200 to under 500 MW | 89 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-89-N | ||
| Requested peak interconnection capacity by request size500 to under 1,000 MW | 62.7 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-74-GW | ||
| Loads by request size500 to under 1,000 MW | 74 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-74-N | ||
| Requested peak interconnection capacity by request size1,000 to 2,000 MW | 38.3 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-25-GW | ||
| Loads by request size1,000 to 2,000 MW | 25 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-25-N | ||
| Requested peak interconnection capacity by request sizeOver 2,000 MW | 26.2 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-8-GW | ||
| Loads by request sizeOver 2,000 MW | 8 loads | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-8-N |
Data center survey: responses (3 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Community Impact RFI response statusSubmitted on time | 417 loads | 465 loads issued the RFI | Data Center State and Community Impact RFI: Preliminary SummarySlides 2-3 · R-417 | ||
| Community Impact RFI response statusSubmitted late | 16 loads | 465 loads issued the RFI | Data Center State and Community Impact RFI: Preliminary SummarySlides 2-3 · R-16 | ||
| Community Impact RFI response statusNot submitted | 32 loads | 465 loads issued the RFI | Data Center State and Community Impact RFI: Preliminary SummarySlides 2-3 · R-32 |
Data center survey: requested energization (4 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Facilities by requested energization dateRequested energization before 2028 | 169 facilities | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-169 | ||
| Average "N/A or unable to answer" responses per RFIRequested energization before 2028 | 23 responses per RFI | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-169-NA | ||
| Facilities by requested energization dateRequested energization January 2028 or later | 260 facilities | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-260 | ||
| Average "N/A or unable to answer" responses per RFIRequested energization January 2028 or later | 30 responses per RFI | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-260-NA |
Data center survey: by function (6 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Requested capacity by facility functionNo virtual currency mining | 175.9 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-407-175.9 | ||
| Facilities by functionNo virtual currency mining | 407 facilities | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-407-N-175.9 | ||
| Requested capacity by facility functionPartial virtual currency mining | 0.8 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-0.8 | ||
| Facilities by functionPartial virtual currency mining | 11 facilities | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-N-0.8 | ||
| Requested capacity by facility functionAll virtual currency mining | 0.7 GW | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-0.7 | ||
| Facilities by functionAll virtual currency mining | 11 facilities | 429 reviewed loads | Data Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-N-0.7 |
Oncor-reported figures (7 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Customer collateral held for active generation and LC&I transmission POI requestsAll | 6.0 US$ billion (approximately) | Oncor | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · ON-1 | ||
| Large-load customer collateral related to Batch Zero projects (part of ON-1)Batch Zero | 2.0 US$ billion (approximately) | Oncor | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-2 | Release dated Nov. 5, 2026; holder date not separately stated | |
| Large load conditionally classified as base load, already energizedBase load, energized | 10 GW (approximately) | Oncor as transmission service provider | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-3 | ||
| Large load conditionally classified as base load, not yet energizedBase load, other | 14 GW (approximately) | Oncor as TSP | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-4 | Power Hopper subtraction: 24 GW base load minus 10 GW energized | |
| Large load conditionally classified as studied loadStudied load | 21 GW (approximately) | Oncor as TSP | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-5 | ||
| Other industrial load requests in Oncor LC&I queue (excluding crypto-mining)Other industrial | 15 GW (approximately) | Oncor LC&I queue | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · ON-6 | Power Hopper subtraction: ~19 GW other industrial including ~4 GW crypto-mining | |
| Crypto-mining load requests in Oncor LC&I queueCrypto-mining | 4 GW (approximately) | Oncor LC&I queue | Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · ON-7 |
Transmission project estimates (11 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Muscovy and Voss Lake (25RPG009) estimate as submitted by Oncor and LCRA TSCSubmitted | 381.83 US$ million (approximately) | RPG submittal | 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)EIR executive summary · TX-MUS-ORIG | ||
| Muscovy and Voss Lake Option 7A estimate recommended by ERCOTERCOT-recommended | 1457 US$ million (approximately) | ERCOT independent review; TAC endorsed May 19, 2026; ERCOT Board endorsed June 1, 2026 (June 1-2 meeting) | 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Board item slides 1 and 3 · TX-MUS-REC | Includes ~$603.33M of upgrades also identified in 25RPG041 | |
| Muscovy and Voss Lake Option 7A cost componentsUpdated initial cost estimate | 388.94 US$ million (approximately) | ERCOT board item | 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Slide 3 · TX-MUS-C388 | Components sum to $1,457.47M | |
| Muscovy and Voss Lake Option 7A cost componentsUpgrades also in Oncor Set 1 project (25RPG041) | 603.33 US$ million (approximately) | ERCOT board item | 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Slide 3 · TX-MUS-C603 | Components sum to $1,457.47M | |
| Muscovy and Voss Lake Option 7A cost componentsAdditional upgrades for peak-load violations | 465.2 US$ million (approximately) | ERCOT board item | 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Slide 3 · TX-MUS-C465 | Components sum to $1,457.47M | |
| ERCOT Board endorsement of Muscovy and Voss Lake Option 7A (unanimous voice vote)Board endorsed | 1457 US$ million (approximately) | Option 7A, Williamson and Milam counties (Central Texas) | Draft General Session Minutes, ERCOT Board of Directors meeting June 1-2, 2026 (posted Sept. 8, 2026)Agenda Item 5.3 · TX-MUS-BOARD | Endorsed at the June 1-2, 2026 board meeting (minutes record the vote in the June 1 session, before the recess to June 2) per draft minutes posted Sept. 8, 2026; endorsement is not a cost approved for rates | |
| Additional load modeled, Oncor area, 2029Oncor | 600 MW (approximately) | EIR Table 2.6 | 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)EIR Table 2.6 · TX-MUS-L1 | Load type not stated | |
| Additional load modeled, LCRA TSC area, 2029LCRA TSC | 3573 MW (approximately) | EIR Table 2.6 | 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)EIR Table 2.6 · TX-MUS-L2 | Load type not stated | |
| Southeast Brownsville estimate as submitted by STECSubmitted | 96.35 US$ million (approximately) | RPG submittal (Nov. 2025) | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 2 · TX-BRO-ORIG | ||
| Southeast Brownsville Option 1 estimate recommended by ERCOTERCOT-recommended | 96.6 US$ million (approximately) | ERCOT independent review | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slides 14 and 18 · TX-BRO-REC | Marked "updated cost estimate from the original estimate" | |
| Medina Load Project estimate as submitted by STECSubmitted | 492 US$ million | RPG submittal (Dec. 2025); review combined with 25RPG020 | STEC Medina Load Project - ERCOT Independent Review Scope (RPG, Feb. 2, 2026)Slide 2 · TX-MED-ORIG | ~1 GW load; June 2031 target; no ERCOT-recommended estimate found by cutoff |
Southeast Brownsville options (8 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Estimated costOption 1 (STEC proposed; ERCOT-recommended) | 96.6 US$ million (approximately) | Feasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 1-C | ||
| Incremental long-term load-serving capability (study result)Option 1 (STEC proposed; ERCOT-recommended) | 564 MW (approximately) | Feasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 13 · BRO-Option 1-MW | ||
| New right-of-way requiring a CCNOption 1 (STEC proposed; ERCOT-recommended) | 19.1 miles (approximately) | Feasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 1-MI | ||
| Estimated costOption 2 (STEC alternative) | 191.2 US$ million (approximately) | Feasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 2-C | ||
| Incremental long-term load-serving capability (study result)Option 2 (STEC alternative) | 274 MW (approximately) | Feasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 13 · BRO-Option 2-MW | ||
| New right-of-way requiring a CCNOption 2 (STEC alternative) | 31.1 miles (approximately) | Feasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 2-MI | ||
| Estimated costOption 3 (ERCOT alternative) | 151.2 US$ million (approximately) | Infeasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 3-C | Option 3 is $151.5M on slide 15 | |
| Incremental long-term load-serving capability (study result)Option 3 (ERCOT alternative) | 881 MW (approximately) | Infeasible | STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 13 · BRO-Option 3-MW |
January 2027 resource adequacy (MORA) (12 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Installed capacity ratingNatural gas | 69601 MW | Operational resources | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Natural gas-I | ||
| Expected available capacity, highest-risk hourNatural gas | 56954 MW | Deterministic scenario, normal conditions | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Natural gas-A | 81.8% of installed | |
| Installed capacity ratingCoal | 13705 MW | Operational resources | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Coal-I | ||
| Expected available capacity, highest-risk hourCoal | 12725 MW | Deterministic scenario, normal conditions | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Coal-A | 92.8% of installed | |
| Installed capacity ratingNuclear | 5268 MW | Operational resources | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Nuclear-I | ||
| Expected available capacity, highest-risk hourNuclear | 5153 MW | Deterministic scenario, normal conditions | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Nuclear-A | 97.8% of installed | |
| Installed capacity ratingWind | 40819 MW | Operational resources | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Wind-I | ||
| Expected available capacity, highest-risk hourWind | 16151 MW | Deterministic scenario, normal conditions | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Wind-A | 39.6% of installed | |
| Installed capacity ratingSolar | 41018 MW | Operational resources | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Solar-I | ||
| Expected available capacity, highest-risk hourSolar | 27 MW | Deterministic scenario, normal conditions | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Solar-A | 0.1% of installed | |
| Installed capacity ratingBatteries | 21528 MW | Operational resources | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Batteries-I | ||
| Expected available capacity, highest-risk hourBatteries | 12525 MW | Deterministic scenario, normal conditions | Monthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Batteries-A | 58.2% of installed |
New generating capacity (4 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| New generation capacity added, Oct. 15, 2025 to May 15, 2026Storage | 4942 MW | ERCOT | Item 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-Stor | Storage also 10,536 MWh | |
| New generation capacity added, Oct. 15, 2025 to May 15, 2026Solar | 4243 MW | ERCOT | Item 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-Sola | ||
| New generation capacity added, Oct. 15, 2025 to May 15, 2026Natural gas / diesel | 1515 MW | ERCOT | Item 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-Natu | ||
| New generation capacity added, Oct. 15, 2025 to May 15, 2026Wind | 148 MW | ERCOT | Item 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-Wind |
Generation queue, September (5 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Generation interconnection queue capacity by fuelBattery | 166 GW | Excludes inactive projects | Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Battery | Battery also ~398 GWh (ERCOT estimate) | |
| Generation interconnection queue capacity by fuelSolar | 158 GW | Excludes inactive projects | Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Solar | ||
| Generation interconnection queue capacity by fuelGas | 80 GW | Excludes inactive projects | Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Gas | Up from 65 GW in June update | |
| Generation interconnection queue capacity by fuelWind | 49 GW | Excludes inactive projects | Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Wind | ||
| Generation interconnection queue capacity by fuelOther | 4 GW | Excludes inactive projects | Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Other |
Generation interconnection status, October (12 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Generation interconnection requests under studyGas | 95032.2 MW | Large and small generators; excludes inactive | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Gas | ||
| Large-generator requests with a signed interconnection agreementGas | 17255.1 MW | Large generators, IA executed | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-Gas | Large generators only | |
| Generation interconnection requests under studyWind | 49781.2 MW | Large and small generators; excludes inactive | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Wind | ||
| Large-generator requests with a signed interconnection agreementWind | 20510.1 MW | Large generators, IA executed | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-Wind | Large generators only | |
| Generation interconnection requests under studySolar | 151797.8 MW | Large and small generators; excludes inactive | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Solar | ||
| Large-generator requests with a signed interconnection agreementSolar | 63132.6 MW | Large generators, IA executed | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-Solar | Large generators only | |
| Generation interconnection requests under studyBattery | 160102.3 MW | Large and small generators; excludes inactive | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Battery | ||
| Large-generator requests with a signed interconnection agreementBattery | 36511.9 MW | Large generators, IA executed | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-Battery | Large generators only | |
| Generation interconnection requests under studyOther | 4700.1 MW | Large and small generators; excludes inactive | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Other | ||
| Large-generator requests with a signed interconnection agreementOther | 0 MW | Large generators, IA executed | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-Other | Large generators only | |
| Generation interconnection requests under studyTotal | 461413.6 MW | Large and small generators; excludes inactive | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Total | ||
| Large-generator requests with a signed interconnection agreementTotal | 137409.7 MW | Large generators, IA executed | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-Total | Large generators only; the Summary tab's separate "Interconnection Agreements Executed" line shows 138,904.65 MW |
Signed interconnection agreements by projected year (25 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Gas | 81.1 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Gas | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Wind | 4102.4 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Wind | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Solar | 10648.2 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Solar | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Battery | 4173.7 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Battery | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Other | 0.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Other | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Gas | 1928.2 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Gas | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Wind | 5372.2 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Wind | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Solar | 17421.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Solar | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Battery | 8917.3 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Battery | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Other | 0.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Other | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Gas | 9149.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Gas | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Wind | 5909.7 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Wind | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Solar | 24032.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Solar | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Battery | 15816.4 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Battery | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Other | 0.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Other | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Gas | 1478.7 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Gas | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Wind | 2646.6 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Wind | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Solar | 8709.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Solar | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Battery | 6223.3 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Battery | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Other | 0.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Other | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Gas | 4618.1 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Gas | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Wind | 2479.2 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Wind | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Solar | 2322.4 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Solar | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Battery | 1381.1 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Battery | 2026 bucket includes 5 projects with projected dates in 2025 | |
| Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Other | 0.0 MW | Large generators with IA; year = Projected COD | Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Other | 2026 bucket includes 5 projects with projected dates in 2025 |
Company-reported campus megawatts (6 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Total planned power capacity (gross MW)IREN Sweetwater 1 | 1400 MW (gross planned power) | Company-reported | IREN Form 10-K, fiscal year ended June 30, 2026Item 1, data center projects table · NP-IREN-S1 | ||
| Total planned power capacity (gross MW)IREN Sweetwater 2 | 600 MW (gross planned power) | Company-reported | IREN Form 10-K, fiscal year ended June 30, 2026Item 1, data center projects table · NP-IREN-S2 | ||
| Total planned power capacity (gross MW)IREN Childress | 750 MW (gross planned power) | Company-reported | IREN Form 10-K, fiscal year ended June 30, 2026Item 1, data center projects table · NP-IREN-C | ||
| Sweetwater Hub conditional inclusion in Batch Zero as base load (company-reported)IREN Sweetwater Hub | 2000 MW (company-reported) | Company-reported | IREN Reports Q1 FY27 Results (Form 6-K exhibit)Development and platform updates · NP-IREN-BZ | ||
| Developed capacity for Bitcoin miningRiot Corsicana | 400 MW (developed capacity) | Company-reported | Riot Platforms Form 10-Q, quarter ended Sept. 30, 2026Item 2 / business overview · NP-RIOT-DEV | ||
| Expected developed capacity on completionRiot Corsicana | 1000 MW (approximately) | Company-reported | Riot Platforms Form 10-Q, quarter ended Sept. 30, 2026Item 2 · NP-RIOT-FULL |
Riot Platforms Corsicana delivery schedule (3 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Corsicana lease delivery schedule, critical IT capacitySeptember 2027 | 400 MW (critical IT) | Company-reported | Riot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)Delivery Schedule bullet · NP-RIOT-Sep | Critical IT capacity is not metered grid demand | |
| Corsicana lease delivery schedule, critical IT capacityJanuary 2028 | 200 MW (critical IT) | Company-reported | Riot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)Delivery Schedule bullet · NP-RIOT-Jan | Critical IT capacity is not metered grid demand | |
| Corsicana lease delivery schedule, critical IT capacityJuly 2028 | 310 MW (critical IT) | Company-reported | Riot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)Delivery Schedule bullet · NP-RIOT-Jul | Critical IT capacity is not metered grid demand |
NRG Texas gas plants (data page only) (3 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| NRG Texas gas plant capacityT.H. Wharton peaker (operating since May 26, 2026) | 415 MW (company-described) | Operating | NRG Energy Form 10-Q, quarter ended Sept. 30, 2026Glossary; Texas Energy Fund discussion · NRG-415 | No verified link to any data-center load | |
| NRG Texas gas plant capacityCedar Bayou 5 (under construction) | 689 MW (company-described) | Under construction | NRG Energy Form 10-Q, quarter ended Sept. 30, 2026Glossary; Texas Energy Fund discussion · NRG-689 | No verified link to any data-center load | |
| NRG Texas gas plant capacityGreens Bayou 6 (under construction) | 443 MW (company-described) | Under construction | NRG Energy Form 10-Q, quarter ended Sept. 30, 2026Glossary; Texas Energy Fund discussion · NRG-443 | No verified link to any data-center load |
Financial security illustration (§25.194) (4 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| Intermediate financial security at $50,000 per MW (arithmetic illustration)75 MW requested | 3.75 US$ million | Adopted 16 TAC §25.194; 2026 value | 16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-75 | Illustration only; applicability, credits and later obligations are project-specific | |
| Intermediate financial security at $50,000 per MW (arithmetic illustration)100 MW requested | 5.0 US$ million | Adopted 16 TAC §25.194; 2026 value | 16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-100 | Illustration only; applicability, credits and later obligations are project-specific | |
| Intermediate financial security at $50,000 per MW (arithmetic illustration)500 MW requested | 25.0 US$ million | Adopted 16 TAC §25.194; 2026 value | 16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-500 | Illustration only; applicability, credits and later obligations are project-specific | |
| Intermediate financial security at $50,000 per MW (arithmetic illustration)1,000 MW requested | 50.0 US$ million | Adopted 16 TAC §25.194; 2026 value | 16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-1000 | Illustration only; applicability, credits and later obligations are project-specific |
Forecasts (2 rows)
| Metric | Value | Population or basis | As of | Source | Note |
|---|---|---|---|---|---|
| 2026 preliminary long-term load forecast, peak2029 | 278003 MW | TSP-provided forecast before ERCOT adjustment | Market Notice M-B051826-01, Proposal to Adjust 2026 Long-Term Load ForecastLong description · LTLF-2029 | ||
| 2026 preliminary long-term load forecast, peak2032 | 367790 MW | TSP-provided forecast before ERCOT adjustment | Market Notice M-B051826-01, Proposal to Adjust 2026 Long-Term Load ForecastLong description · LTLF-2032 |
Charts
Grid and Transmission · 2026
Four 2026 counts of large-load requests describe four different groups of projects
Gigawatts (GW) requested. Each bar has a different scope and date, so the bars cannot be subtracted to measure cancellations or growth.

Download PNG of Large-load interconnection request totals reported in 2026, by population and date WebP of Large-load interconnection request totals reported in 2026, by population and date SVG of Large-load interconnection request totals reported in 2026, by population and date
Sources: ERCOT update to the Texas Senate Committee on Business and Commerce, July 29, 2026, slide 6; ERCOT presentation to the PUCT open meeting, Sept. 11, 2026 (PUCT Project No. 59142, Item 55), Batch Zero eligibility overview slide; Oncor Q3 2026 results release, Nov. 5, 2026; ERCOT Community Impact RFI summary, Nov. 5, 2026, slide 7.
Cite this chart
Power Hopper Team. "Large-load interconnection request totals reported in 2026, by population and date." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-large-load-requests-four-snapshots-2026. Accessed [date accessed].
Grid and Transmission · 2026
About 205 GW of large-load requests passed ERCOT's preliminary Batch Zero screen; about 294 GW did not
Requested GW by preliminary category, data as of July 28, 2026. Eligibility was preliminary; final inclusion depends on ERCOT's later review and verification. Preliminary July 28 screen, superseded by ERCOT's Sept. 3 conditional classification (191.8 GW included).

Download PNG of ERCOT preliminary Batch Zero eligibility screen, by requested gigawatts, July 28, 2026 WebP of ERCOT preliminary Batch Zero eligibility screen, by requested gigawatts, July 28, 2026 SVG of ERCOT preliminary Batch Zero eligibility screen, by requested gigawatts, July 28, 2026
Source: ERCOT, update to the Texas House Committee on State Affairs, Aug. 19, 2026, slide 3 (preliminary; data as of July 28, 2026); superseded by ERCOT Board item 14, Sept. 14-15, 2026.
Cite this chart
Power Hopper Team. "ERCOT preliminary Batch Zero eligibility screen, by requested gigawatts, July 28, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-batch-zero-eligibility-by-gigawatts-july-2026. Accessed [date accessed].
Grid and Transmission · 2026
362 of 688 large-load projects were not included in ERCOT's preliminary Batch Zero screen
Number of projects by preliminary category, data as of July 28, 2026. Not being included reflects study readiness on that date, not cancellation. Preliminary July 28 screen, superseded by ERCOT's Sept. 3 conditional classification (191.8 GW included).

Download PNG of ERCOT preliminary Batch Zero eligibility screen, by number of projects, July 28, 2026 WebP of ERCOT preliminary Batch Zero eligibility screen, by number of projects, July 28, 2026 SVG of ERCOT preliminary Batch Zero eligibility screen, by number of projects, July 28, 2026
Source: ERCOT, update to the Texas House Committee on State Affairs, Aug. 19, 2026, slide 3 (preliminary; data as of July 28, 2026).
Cite this chart
Power Hopper Team. "ERCOT preliminary Batch Zero eligibility screen, by number of projects, July 28, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-batch-zero-eligibility-by-project-count-july-2026. Accessed [date accessed].
Grid and Transmission · 2026
West Texas accounts for 73 GW, or 41%, of the capacity requested in ERCOT's data center survey
Requested peak interconnection capacity of 429 reviewed loads (177.4 GW), by ERCOT load zone. Preliminary as of Nov. 5, 2026.

Download PNG of Requested data-center interconnection capacity by ERCOT load zone, Nov. 2026 survey WebP of Requested data-center interconnection capacity by ERCOT load zone, Nov. 2026 survey SVG of Requested data-center interconnection capacity by ERCOT load zone, Nov. 2026 survey
Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 9.
Cite this chart
Power Hopper Team. "Requested data-center interconnection capacity by ERCOT load zone, Nov. 2026 survey." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-capacity-by-load-zone-2026. Accessed [date accessed].
Grid and Transmission · 2026
North has the most surveyed data-center facilities; West has the most requested capacity
Number of reviewed loads by load zone: large loads (75 MW or more) and medium loads (under 75 MW). 429 loads, preliminary as of Nov. 5, 2026.

Download PNG of Surveyed data-center facilities by ERCOT load zone and load size, Nov. 2026 WebP of Surveyed data-center facilities by ERCOT load zone and load size, Nov. 2026 SVG of Surveyed data-center facilities by ERCOT load zone and load size, Nov. 2026
Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 9.
Cite this chart
Power Hopper Team. "Surveyed data-center facilities by ERCOT load zone and load size, Nov. 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-facilities-by-load-zone-and-size-2026. Accessed [date accessed].
Grid and Transmission · 2026
33 requests of 1 GW or more account for 64.5 GW, or 36%, of capacity in ERCOT's data center survey
Requested peak interconnection capacity of 429 reviewed loads, by size of each request. Number of loads in parentheses.

Download PNG of Requested data-center interconnection capacity by request size, Nov. 2026 survey WebP of Requested data-center interconnection capacity by request size, Nov. 2026 survey SVG of Requested data-center interconnection capacity by request size, Nov. 2026 survey
Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 7.
Cite this chart
Power Hopper Team. "Requested data-center interconnection capacity by request size, Nov. 2026 survey." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-capacity-by-request-size-2026. Accessed [date accessed].
Grid and Transmission · 2026
433 of 465 loads answered ERCOT's data center community impact survey; 32 had not
Response status as of Nov. 5, 2026 (preliminary). All large loads (75 MW or more) responded; the 32 not submitted are medium loads.

Download PNG of Response status of ERCOT's data center community impact survey, Nov. 2026 WebP of Response status of ERCOT's data center community impact survey, Nov. 2026 SVG of Response status of ERCOT's data center community impact survey, Nov. 2026
Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slides 2-3.
Cite this chart
Power Hopper Team. "Response status of ERCOT's data center community impact survey, Nov. 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-survey-response-status-2026. Accessed [date accessed].
Grid and Transmission · 2026
Six in 10 surveyed data-center facilities request power in 2028 or later
Reviewed facilities by requested energization date. Later projects answered "N/A or unable to answer" more often (30 vs. 23 per survey on average).

Download PNG of Surveyed data-center facilities by requested energization date WebP of Surveyed data-center facilities by requested energization date SVG of Surveyed data-center facilities by requested energization date
Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 5.
Cite this chart
Power Hopper Team. "Surveyed data-center facilities by requested energization date." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-energization-before-and-after-2028. Accessed [date accessed].
Grid and Transmission · 2026
Facilities with no crypto mining account for 175.9 GW of the 177.4 GW surveyed
Requested peak interconnection capacity by reported computation function, 429 reviewed loads. Facilities in parentheses.

Download PNG of Requested capacity in ERCOT's data center survey by crypto-mining function WebP of Requested capacity in ERCOT's data center survey by crypto-mining function SVG of Requested capacity in ERCOT's data center survey by crypto-mining function
Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 8.
Cite this chart
Power Hopper Team. "Requested capacity in ERCOT's data center survey by crypto-mining function." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-capacity-by-crypto-mining-function-2026. Accessed [date accessed].
Grid and Transmission · 2026
ERCOT expects to send follow-up questions to 80% of developers in its data center verification review
Batch Zero eligibility verification ordered after the Governor's Aug. 3, 2026 letter. ERCOT says it must finish the review to report to the PUCT on Dec. 10, 2026.

Download PNG of Status of ERCOT's Batch Zero eligibility verification, Nov. 5, 2026 WebP of Status of ERCOT's Batch Zero eligibility verification, Nov. 5, 2026 SVG of Status of ERCOT's Batch Zero eligibility verification, Nov. 5, 2026
Sources: ERCOT, Batch Zero Eligibility Verification Process Update, Nov. 5, 2026, slide 2; ERCOT Market Notices M-A080326-01 and M-A090926-01; ERCOT Board item 14, Sept. 14-15, 2026, slides 3-4.
Cite this chart
Power Hopper Team. "Status of ERCOT's Batch Zero eligibility verification, Nov. 5, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-batch-zero-verification-review-status-nov-2026. Accessed [date accessed].
Grid and Transmission · 2026
Oncor reports about $2 billion of its $6 billion in customer collateral relates to Batch Zero large loads
Customer collateral Oncor holds for active generation and large commercial and industrial transmission interconnection requests, billions of dollars.

Download PNG of Oncor customer collateral for interconnection requests, and the part tied to Batch Zero large loads WebP of Oncor customer collateral for interconnection requests, and the part tied to Batch Zero large loads SVG of Oncor customer collateral for interconnection requests, and the part tied to Batch Zero large loads
Source: Oncor Electric Delivery, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 5, 2026.
Cite this chart
Power Hopper Team. "Oncor customer collateral for interconnection requests, and the part tied to Batch Zero large loads." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-oncor-customer-collateral-batch-zero-large-loads-2026. Accessed [date accessed].
Grid and Transmission · 2026
Oncor reports 45 GW of large load conditionally classified in Batch Zero in its area, 10 GW already energized
Gigawatts conditionally classified by ERCOT, as reported by Oncor on Nov. 5, 2026. Classification is conditional pending ERCOT's audit.

Download PNG of Large load conditionally classified in ERCOT's Batch Zero where Oncor is the transmission provider WebP of Large load conditionally classified in ERCOT's Batch Zero where Oncor is the transmission provider SVG of Large load conditionally classified in ERCOT's Batch Zero where Oncor is the transmission provider
Source: Oncor Electric Delivery, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 5, 2026.
Cite this chart
Power Hopper Team. "Large load conditionally classified in ERCOT's Batch Zero where Oncor is the transmission provider." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-oncor-batch-zero-conditional-classification-gigawatts-2026. Accessed [date accessed].
Grid and Transmission · 2026
Data centers make up about 293 GW of the load in Oncor's large-customer interconnection queue
Requested load in Oncor's active transmission LC&I interconnection queue (795 requests), gigawatts, as of Sept. 30, 2026.

Download PNG of Oncor transmission large commercial and industrial interconnection queue by load type, Sept. 30, 2026 WebP of Oncor transmission large commercial and industrial interconnection queue by load type, Sept. 30, 2026 SVG of Oncor transmission large commercial and industrial interconnection queue by load type, Sept. 30, 2026
Source: Oncor Electric Delivery, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 5, 2026.
Cite this chart
Power Hopper Team. "Oncor transmission large commercial and industrial interconnection queue by load type, Sept. 30, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-oncor-large-load-queue-data-centers-vs-other-industries-2026. Accessed [date accessed].
Grid and Transmission · 2026
ERCOT's generation queue held 461 GW in October; 137 GW of large-generator projects had signed interconnection agreements
Gigawatts of generation interconnection requests under study (excluding inactive projects) and large-generator capacity with a signed interconnection agreement.

Download PNG of ERCOT generation interconnection queue and capacity with signed interconnection agreements, by fuel, October 2026 WebP of ERCOT generation interconnection queue and capacity with signed interconnection agreements, by fuel, October 2026 SVG of ERCOT generation interconnection queue and capacity with signed interconnection agreements, by fuel, October 2026
Source: ERCOT Generator Interconnection Status report, October 2026 (data as of Oct. 31, 2026); Power Hopper totals.
Cite this chart
Power Hopper Team. "ERCOT generation interconnection queue and capacity with signed interconnection agreements, by fuel, October 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-generation-interconnection-queue-signed-agreements-by-fuel-oct-2026. Accessed [date accessed].
Grid and Transmission · 2026
Generators with signed ERCOT agreements project 54.9 GW for 2028, the largest year
Gigawatts of large-generator capacity with a signed interconnection agreement, by projected commercial operation date in ERCOT's October 2026 report.

Download PNG of Generation capacity with signed ERCOT interconnection agreements, by developer-projected commercial operation year and fuel WebP of Generation capacity with signed ERCOT interconnection agreements, by developer-projected commercial operation year and fuel SVG of Generation capacity with signed ERCOT interconnection agreements, by developer-projected commercial operation year and fuel
Source: ERCOT Generator Interconnection Status report, October 2026 (data as of Oct. 31, 2026); Power Hopper totals.
Cite this chart
Power Hopper Team. "Generation capacity with signed ERCOT interconnection agreements, by developer-projected commercial operation year and fuel." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-signed-generation-agreements-by-projected-year-and-fuel-2026. Accessed [date accessed].
Grid and Transmission · 2026
ERCOT's January 2027 outlook expects 82% of gas capacity but under 1% of solar to be available at 8 a.m.
Installed capacity rating and expected available capacity, hour ending 8 a.m. CST, deterministic scenario under normal conditions. Gigawatts.

Download PNG of ERCOT January 2027 outlook: installed and expected available capacity by fuel in the highest-risk hour WebP of ERCOT January 2027 outlook: installed and expected available capacity by fuel in the highest-risk hour SVG of ERCOT January 2027 outlook: installed and expected available capacity by fuel in the highest-risk hour
Source: ERCOT, Monthly Outlook for Resource Adequacy, January 2027 (published Nov. 6, 2026), p. 5.
Cite this chart
Power Hopper Team. "ERCOT January 2027 outlook: installed and expected available capacity by fuel in the highest-risk hour." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-january-2027-installed-vs-expected-available-capacity-by-fuel. Accessed [date accessed].
Grid and Transmission · 2026
ERCOT added more than 10,800 MW of new generating capacity from October 2025 to May 2026, led by batteries
Megawatts of new capacity by fuel, Oct. 15, 2025 to May 15, 2026, as reported to ERCOT's board.

Download PNG of New generation capacity added to the ERCOT grid by fuel, Oct. 15, 2025 to May 15, 2026 WebP of New generation capacity added to the ERCOT grid by fuel, Oct. 15, 2025 to May 15, 2026 SVG of New generation capacity added to the ERCOT grid by fuel, Oct. 15, 2025 to May 15, 2026
Source: ERCOT, CEO Update, Board of Directors meeting June 1-2, 2026, slide 6.
Cite this chart
Power Hopper Team. "New generation capacity added to the ERCOT grid by fuel, Oct. 15, 2025 to May 15, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-new-generation-capacity-by-fuel-oct-2025-may-2026. Accessed [date accessed].
Grid and Transmission · 2026
ERCOT's recommended Muscovy-Voss Lake option, with added scope, is estimated at $1.457 billion vs. $381.83 million submitted
Estimated cost, millions of dollars. Submitted = utility's RPG submittal; recommended = ERCOT independent review. Not approved costs or rates.

Download PNG of Cost estimates for three large-load transmission reviews: as submitted and as recommended by ERCOT WebP of Cost estimates for three large-load transmission reviews: as submitted and as recommended by ERCOT SVG of Cost estimates for three large-load transmission reviews: as submitted and as recommended by ERCOT
Sources: ERCOT Board item 5.3 and EIR for 25RPG009 (May 22, 2026); ERCOT EIR scope for Medina (Feb. 2, 2026); ERCOT EIR recommendation for Southeast Brownsville (May 11, 2026); ERCOT Board draft minutes, June 1-2, 2026 (posted Sept. 8, 2026).
Cite this chart
Power Hopper Team. "Cost estimates for three large-load transmission reviews: as submitted and as recommended by ERCOT." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-large-load-transmission-project-estimates-submitted-vs-recommended-2026. Accessed [date accessed].
Grid and Transmission · 2026
About $603 million of the $1.457 billion Muscovy-Voss Lake estimate is work also listed in another Oncor project
Cost components of Option 7A as listed in ERCOT's board materials, millions of dollars (approximate).

Download PNG of Components of ERCOT's $1.457 billion estimate for the Muscovy and Voss Lake project (Option 7A) WebP of Components of ERCOT's $1.457 billion estimate for the Muscovy and Voss Lake project (Option 7A) SVG of Components of ERCOT's $1.457 billion estimate for the Muscovy and Voss Lake project (Option 7A)
Source: ERCOT, Board item 5.3: 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, slide 3 (Board meeting June 1-2, 2026).
Cite this chart
Power Hopper Team. "Components of ERCOT's $1.457 billion estimate for the Muscovy and Voss Lake project (Option 7A)." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-muscovy-voss-lake-transmission-project-cost-components-2026. Accessed [date accessed].
Grid and Transmission · 2026
ERCOT recommended the least-cost Southeast Brownsville option, estimated at about $96.6 million
Estimated cost by option, millions of dollars. Labels show ERCOT's modeled incremental load-serving capability and feasibility.

Download PNG of Southeast Brownsville large-load transmission options: cost estimate and modeled load-serving capability WebP of Southeast Brownsville large-load transmission options: cost estimate and modeled load-serving capability SVG of Southeast Brownsville large-load transmission options: cost estimate and modeled load-serving capability
Source: ERCOT, STEC Southeast Brownsville Large Load Project EIR recommendation, RPG meeting May 11, 2026, slides 13-15 and 18.
Cite this chart
Power Hopper Team. "Southeast Brownsville large-load transmission options: cost estimate and modeled load-serving capability." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-southeast-brownsville-transmission-options-cost-and-load-serving-capability-2026. Accessed [date accessed].
Grid and Transmission · 2026
Riot's Corsicana lease schedules 910 MW of critical IT capacity in three phases in 2027 and 2028
Critical IT megawatts by scheduled delivery date, as reported by Riot Platforms on Nov. 4, 2026. Cumulative by date.

Download PNG of Riot Platforms Corsicana lease: critical IT capacity delivery schedule WebP of Riot Platforms Corsicana lease: critical IT capacity delivery schedule SVG of Riot Platforms Corsicana lease: critical IT capacity delivery schedule
Source: Riot Platforms, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 4, 2026; Form 10-Q for the quarter ended Sept. 30, 2026.
Cite this chart
Power Hopper Team. "Riot Platforms Corsicana lease: critical IT capacity delivery schedule." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-riot-corsicana-critical-it-capacity-delivery-schedule-2027-2028. Accessed [date accessed].
Grid and Transmission · 2026
Company-reported megawatts for Texas data-center campuses use different measures, none of them metered grid use
Megawatts as reported in SEC filings. Gross planned power, developed capacity and leased critical IT capacity are different measures and are not comparable.

Download PNG of Company-reported megawatts at four Texas data-center campuses, by type of measure WebP of Company-reported megawatts at four Texas data-center campuses, by type of measure SVG of Company-reported megawatts at four Texas data-center campuses, by type of measure
Sources: IREN Form 10-K for fiscal 2026 (as of June 30, 2026) and Q1 FY27 results (Nov. 5, 2026); Riot Platforms Form 10-Q and results release (Nov. 4, 2026).
Cite this chart
Power Hopper Team. "Company-reported megawatts at four Texas data-center campuses, by type of measure." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-data-center-campuses-company-reported-megawatts-by-measure-2026. Accessed [date accessed].
Grid and Transmission · 2026
NRG reports 415 MW of new Texas gas capacity in operation and 1,132 MW under construction
Megawatts as described in NRG's Form 10-Q for the quarter ended Sept. 30, 2026.

Download PNG of NRG Energy Texas gas plant additions: in operation and under construction WebP of NRG Energy Texas gas plant additions: in operation and under construction SVG of NRG Energy Texas gas plant additions: in operation and under construction
Source: NRG Energy, Form 10-Q for the quarter ended Sept. 30, 2026 (filed Nov. 9, 2026).
Cite this chart
Power Hopper Team. "NRG Energy Texas gas plant additions: in operation and under construction." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-nrg-texas-gas-plants-operating-and-under-construction-2026. Accessed [date accessed].
Grid and Transmission · 2026
At $50,000 per MW, a 1,000 MW request would post $50 million in security under the new Texas rule
Arithmetic illustration of the 2026 value in 16 TAC §25.194 for selected request sizes. Not any project's actual security.

Download PNG of Illustration: intermediate financial security under the adopted Texas large-load rule at $50,000 per MW WebP of Illustration: intermediate financial security under the adopted Texas large-load rule at $50,000 per MW SVG of Illustration: intermediate financial security under the adopted Texas large-load rule at $50,000 per MW
Source: Texas Register, Oct. 2, 2026, adopted 16 TAC §25.194 (PUCT Project No. 58481), effective Oct. 8, 2026; Power Hopper arithmetic.
Cite this chart
Power Hopper Team. "Illustration: intermediate financial security under the adopted Texas large-load rule at $50,000 per MW." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-large-load-interconnection-financial-security-50000-per-mw-illustration. Accessed [date accessed].
Grid and Transmission · 2026
Five records would be needed to calculate any household bill effect of these grid projects; Power Hopper did not find them all public
Status of each input for the three transmission reviews in this story, as of Nov. 10, 2026.

Download PNG of Records needed before a household bill effect of a large-load transmission project can be calculated WebP of Records needed before a household bill effect of a large-load transmission project can be calculated SVG of Records needed before a household bill effect of a large-load transmission project can be calculated
Sources: Texas Register, July 24, 2026 (PUCT Project No. 58000 proposal) and Oct. 2, 2026 (adopted §25.194); NRG Form 10-Q, Q3 2026; ERCOT RPG documents for 25RPG009, 25RPG039 and 25RPG046.
Cite this chart
Power Hopper Team. "Records needed before a household bill effect of a large-load transmission project can be calculated." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-large-load-transmission-cost-allocation-records-not-yet-public. Accessed [date accessed].
Grid and Transmission · 2026
Power Hopper re-checked 111 claims against primary records: 75 verified as written
Status of each claim and figure after re-fetching ERCOT, PUCT, Texas Register and SEC records on Nov. 10, 2026.

Download PNG of Power Hopper fact-check of an incoming research package on Texas data centers and the grid WebP of Power Hopper fact-check of an incoming research package on Texas data centers and the grid SVG of Power Hopper fact-check of an incoming research package on Texas data centers and the grid
Source: Power Hopper review, FACTCHECK.csv (Nov. 10, 2026).
Cite this chart
Power Hopper Team. "Power Hopper fact-check of an incoming research package on Texas data centers and the grid." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-data-center-grid-claims-fact-check-status-2026. Accessed [date accessed].
Methodology
- Populations. Rows superseded by a later ERCOT figure (REQ-1/REQ-2: 438 GW and 89%, June 18; REQ-3 and the
batch-zero-screenrows: July 28 preliminary screen) are kept with a "superseded by" note and shown as history. The current figures are REQ-6 to REQ-9 (ERCOT Senate Business and Commerce update, July 29, 2026, slide 6, data as of June 2026) and thebatch-zero-sept-classificationrows (ERCOT Board item 14, Sept. 14-15, 2026). ERCOT reported the 191.8 GW included total in its Sept. 11, 2026 presentation to the PUCT (Project No. 59142, Item 55); it equals ERCOT's base (66.4 GW) plus studied (125.4 GW) values; ERCOT's key-takeaway text gives studied load as 127.9 GW. ERCOT's 420,812 MW (90.2%) data-center value implies a base of about 466.5 GW, which ERCOT does not reconcile with its 474.7 GW chart total. Every row names its population and date (for example, "all large-load requests tracked by ERCOT, June 18, 2026" or "429 loads reviewed in ERCOT's preliminary survey summary, Nov. 5, 2026"). Rows from different populations are not summed or subtracted. - ERCOT presentations and notices. Values copied from the cited slide or page. Rounded slide values are kept as published; where slide values do not add to a stated total, both are shown.
- Generation queue. Power Hopper totaled ERCOT's October 2026 Generator Interconnection Status workbook (data as of Oct. 31, 2026) by fuel, and by projected commercial operation year for projects whose study phase shows a signed interconnection agreement (IA). The signed-IA total (137,409.7 MW) is the sum of the Summary tab's large-generator IA columns; the tab's separate "Interconnection Agreements Executed" line shows 138,904.65 MW, and the workbook does not explain the difference. "Under study" totals include small generators.
- Company figures. Taken from SEC filings and attributed. Each keeps the company's own measure (gross planned power, developed capacity, critical IT capacity, nameplate MW). None is metered grid demand.
- Illustration. The financial-security rows multiply the 2026 §25.194 rate ($50,000 per MW) by example request sizes. They are not any project's actual security.
Limitations
- ERCOT told its board in September 2026 that it had paused approvals to energize new data centers and crypto mining facilities of 75 MW or more until the verification and community impact reviews are complete (row PAUSE-75).
- Requests, eligibility and survey responses are not load forecasts. ERCOT's verification report and final Batch Zero results were not public as of Nov. 10, 2026.
- ERCOT's 2026 transmission review documents for Muscovy-Voss Lake, Medina and Southeast Brownsville describe large-load or reliability projects and do not identify data centers.
- Transmission estimates are planning estimates, not costs approved for rates. The ERCOT Board endorsed Muscovy-Voss Lake Option 7A (Williamson and Milam counties, Central Texas) at its June 1-2, 2026 meeting; an endorsement is not a cost approved for rates. Cost allocation (PUCT Project No. 58000) was a proposal as of Nov. 10, 2026; its PUCT filings list comments through Oct. 1, 2026 and no adoption order. The §25.194 interconnection rule (Project No. 58481) was adopted Sept. 18, 2026 and took effect Oct. 8.
- The data do not measure effects on household bills, prices or reliability.
- The January 2027 MORA is a single modeled hour under normal conditions; its p. 3 and p. 5 tables show different solar and storage figures (p. 5 used).
Data dictionary
| Field | Description |
|---|---|
id | Row identifier |
group | Group of related figures (one population, date and source per group) |
metric | What the figure measures |
category | Category within the metric |
value | Figure as published by the source (rounded values kept as published) |
unit | Unit, with qualifiers such as 'about' or 'more than' as the source states them |
population_or_basis | Population or basis the figure describes |
as_of | Date the figure describes |
source_id | Source key |
source_title | Source document |
source_url | Link to the source |
locator | Page, slide, table or paragraph in the source |
note | Context, including superseded-by notes |
Power Hopper is not affiliated with or endorsed by the PUCT, ERCOT, the Office of the Texas Governor, the Texas Secretary of State, the State Office of Administrative Hearings, the U.S. Energy Information Administration, the Texas House Committee on State Affairs, the Texas Senate Committee on Business and Commerce, the U.S. Securities and Exchange Commission, Oncor Electric Delivery, Sempra, LCRA Transmission Services Corporation, South Texas Electric Cooperative, CPS Energy, IREN, Riot Platforms, NRG Energy, or any other company, cooperative, utility, project or developer named on this page.
Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility, and is not affiliated with or endorsed by the PUCT, ERCOT or any utility, supplier or data provider named above. This brief was prepared with AI assistance.