Grid and Transmission · Source-checked

Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues

ERCOT reported about 474 GW of large-load requests as of June 2026, about 90% from data centers; it conditionally included 191.8 GW in Batch Zero as of Sept. 3, after a preliminary July 28 screen found about 205 GW eligible. Requests, eligibility, survey responses and company megawatts are different populations and are labeled, not added or subtracted. Verification results and cost-allocation rules were still pending as of Nov. 10, 2026, and no reviewed record shows a household bill effect.

Download CSVDownload JSON Read the article

About 474 GW

Large-load requests tracked by ERCOT as of June 2026, about 90% from data centers (ERCOT, Senate Business and Commerce update, July 29, 2026)

Figures dated June 18 to Nov 10, 2026

Takeaway

  • ERCOT reported about 474 GW of large-load requests as of June 2026, about 90% from data centers; it conditionally included 191.8 GW in Batch Zero as of Sept. 3, after a preliminary July 28 screen found about 205 GW eligible. Requests, eligibility, survey responses and company megawatts are different populations and are labeled, not added or subtracted. Verification results and cost-allocation rules were still pending as of Nov. 10, 2026, and no reviewed record shows a household bill effect.

Article: Data centers make up about 90% of ERCOT's 474 GW of large-load requests

Data

172 figures in 22 groups. Each group is one population, date and source; rows from different groups are not added or subtracted.

Large-load request totals (9 rows)
Large-load request totals (9 rows)
MetricValuePopulation or basisAs ofSourceNote
Large-load interconnection requests tracked by ERCOTAll large-load requests438 GW (more than)All large-load requests ERCOT was tracking; nearly 89% from data centersERCOT news release on PUCT approval of the Batch Zero processParagraph 3 · REQ-1ERCOT: "more than 438,000 MW". Superseded by REQ-6 (about 474 GW as of June 2026, ERCOT Senate B&C July 29); shown as history
Data-center share of large-load requestsData centers89 % (nearly)Same population as REQ-1ERCOT news release on PUCT approval of the Batch Zero processParagraph 3 · REQ-2ERCOT: "nearly 89 percent"; Power Hopper does not multiply the two rounded figures. Superseded by REQ-7/REQ-8 (about 90%; 420,812 MW, 90.2%); shown as history
Large load preliminarily eligible for Batch ZeroEligible (base, allocated or TBD)205 GW (approximately)Batch Zero eligibility screen; preliminaryERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3, Key Takeaways · REQ-3Slide bar labels sum to 204 GW because of rounding. Superseded by ERCOT's Sept. 3 conditional classification (BZ-SEP rows: 191.8 GW conditionally included); shown as history
Requested peak interconnection capacity, reviewed RFI dataset429 reviewed loads177.4 GWCommunity Impact RFI reviewed dataset (243 large, 186 medium loads)Data Center State and Community Impact RFI: Preliminary SummarySlide 7, Total · REQ-4Preliminary, subject to change
Data-center requests in Oncor transmission LC&I interconnection queueOncor service area293 GW (approximately)Oncor active transmission LC&I queue, 795 requestsOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · REQ-5Company-reported; a utility-level queue, not an ERCOT total
Large-load interconnection requests tracked by ERCOTAll large-load requests474 GW (approximately)All large Loads seeking interconnection, as of June 2026ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, Key Takeaway · REQ-6ERCOT: "approximately 474 GW"; slide 6 chart totals 474.1 GW (2031) and 474.7 GW (2032-2033)
Data-center share of large-load requestsData centers90 % (approximately)Same population as REQ-6ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, Key Takeaway · REQ-7ERCOT: "~90% are data centers"
Data-center large-load requests (ERCOT pie value)Data centers420812 MWLarge Loads by Project Type, as of June 2026ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, pie chart label "90.2% (420812 MW)" · REQ-8ERCOT pie value; implied base ≈466.5 GW differs from 474.7 GW total; not reconciled by ERCOT
Large load observed energizedObserved energized5.9 GWActual and projected large-load growth table, 2026 columnERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)Slide 6, table row "Observed Energized" · REQ-9Cumulative observed energized large load shown by ERCOT
Batch Zero conditional classification, Sept. 3 (8 rows)
Batch Zero conditional classification, Sept. 3 (8 rows)
MetricValuePopulation or basisAs ofSourceNote
Large-load requested capacity by Batch Zero conditional classificationConditionally included (base + studied)191.8 GWBatch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026; ERCOT Updates presentation, PUCT open meeting (PUCT Project No. 59142, Item 55)Slides 1, 5, 6; PUCT Project No. 59142, Item 55, Batch Zero eligibility overview slide (Key Takeaways) · BZ-SEP-INC-GWERCOT, PUCT Project No. 59142, Item 55 (Sept. 11, 2026): "191.8 GW in Batch Zero, combined base and studied load" (equals slide 6 values 66.4 GW + 125.4 GW); ERCOT slide 5: "362 Large Loads in either base or studied load categories"; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes
Large loads / projects by Batch Zero conditional classificationConditionally included (base + studied)362 large loads (projects)Same as BZ-SEP GW rowsItem 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-INC-N
Large-load requested capacity by Batch Zero conditional classificationConditionally included as base load66.4 GWBatch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-BASE-GWFinal inclusion depends on ERCOT eligibility verification (December); subject to dispute processes
Large loads / projects by Batch Zero conditional classificationConditionally included as base load204 large loads (projects)Same as BZ-SEP GW rowsItem 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-BASE-N
Large-load requested capacity by Batch Zero conditional classificationConditionally included as studied load125.4 GWBatch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-STU-GW125.4 GW on slide 6 chart; 127.9 GW in slide 1 key-takeaway text; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes
Large loads / projects by Batch Zero conditional classificationConditionally included as studied load158 large loads (projects)Same as BZ-SEP GW rowsItem 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-STU-N
Large-load requested capacity by Batch Zero conditional classificationExcluded from Batch Zero302.2 GWBatch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-EXC-GWSlide 6: "This chart omits excluded load (302.2 GW, 373 projects)"; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes
Large loads / projects by Batch Zero conditional classificationExcluded from Batch Zero373 large loads (projects)Same as BZ-SEP GW rowsItem 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 1, 5, 6 · BZ-SEP-EXC-N
Batch Zero verification review (4 rows)
Batch Zero verification review (4 rows)
MetricValuePopulation or basisAs ofSourceNote
Size threshold for ERCOT pause on approvals to energize new data centers and crypto mining facilitiesPause threshold75 MW or greaterNew Large Load data centers and virtual currency mining facilities not yet connectedItem 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026Slides 3-4 · PAUSE-75Paused until completion of the verification and audit and the community impact review (ERCOT, Sept. 14-15 board)
Developers whose first-round verification responses ERCOT reviewedDevelopers257 developersBatch Zero verificationBatch Zero Eligibility Verification Process UpdateSlide 2 · V-1
Share of developers ERCOT expects to send second-round RFIsDevelopers80 %Batch Zero verificationBatch Zero Eligibility Verification Process UpdateSlide 2 · V-2
First-round questions reviewedQuestions5140 questions (approximately)Batch Zero verificationBatch Zero Eligibility Verification Process UpdateSlide 2 · V-3
Batch Zero preliminary screen, July 28 (superseded) (10 rows)
Batch Zero preliminary screen, July 28 (superseded) (10 rows)
MetricValuePopulation or basisAs ofSourceNote
Large-load requests by preliminary Batch Zero eligibilityEligible as base load65 GW (rounded slide label)EligibleERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-150
Projects by preliminary Batch Zero eligibilityEligible as base load150 projectsEligibleERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-150
Large-load requests by preliminary Batch Zero eligibilityEligible, base or allocated to be determined25 GW (rounded slide label)EligibleERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-49
Projects by preliminary Batch Zero eligibilityEligible, base or allocated to be determined49 projectsEligibleERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-49
Large-load requests by preliminary Batch Zero eligibilityEligible as allocated load114 GW (rounded slide label)EligibleERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-127
Projects by preliminary Batch Zero eligibilityEligible as allocated load127 projectsEligibleERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-127
Large-load requests by preliminary Batch Zero eligibilityNot included: no dynamic model by July 1020 GW (rounded slide label)Not includedERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-47
Projects by preliminary Batch Zero eligibilityNot included: no dynamic model by July 1047 projectsNot includedERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-47
Large-load requests by preliminary Batch Zero eligibilityNot included: no qualifying study274 GW (rounded slide label)Not includedERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 bar labels · BZ-GW-315
Projects by preliminary Batch Zero eligibilityNot included: no qualifying study315 projectsNot includedERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)Slide 3 legend · BZ-N-315
Data center survey: by load zone (12 rows)
Data center survey: by load zone (12 rows)
MetricValuePopulation or basisAs ofSourceNote
Requested peak interconnection capacity by ERCOT load zoneWest73 GW (rounded)429 reviewed loads; zone from facility GPSData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-West-GW37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded
Large loads (75 MW or more) by load zoneWest88 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-West-LL
Medium loads (under 75 MW) by load zoneWest39 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-West-ML
Requested peak interconnection capacity by ERCOT load zoneSouth49 GW (rounded)429 reviewed loads; zone from facility GPSData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-South-GW37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded
Large loads (75 MW or more) by load zoneSouth72 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-South-LL
Medium loads (under 75 MW) by load zoneSouth38 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-South-ML
Requested peak interconnection capacity by ERCOT load zoneNorth45 GW (rounded)429 reviewed loads; zone from facility GPSData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-North-GW37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded
Large loads (75 MW or more) by load zoneNorth69 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-North-LL
Medium loads (under 75 MW) by load zoneNorth85 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-North-ML
Requested peak interconnection capacity by ERCOT load zoneHouston10 GW (rounded)429 reviewed loads; zone from facility GPSData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-Houston-GW37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded
Large loads (75 MW or more) by load zoneHouston14 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-Houston-LL
Medium loads (under 75 MW) by load zoneHouston24 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 9 · Z-Houston-ML
Data center survey: by request size (14 rows)
Data center survey: by request size (14 rows)
MetricValuePopulation or basisAs ofSourceNote
Requested peak interconnection capacity by request sizeUnder 50 MW1.5 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-43-GW
Loads by request sizeUnder 50 MW43 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-43-N
Requested peak interconnection capacity by request size50 to under 75 MW9.8 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-143-GW
Loads by request size50 to under 75 MW143 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-143-N
Requested peak interconnection capacity by request size75 to under 200 MW7.2 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-47-GW
Loads by request size75 to under 200 MW47 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-47-N
Requested peak interconnection capacity by request size200 to under 500 MW31.7 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-89-GW
Loads by request size200 to under 500 MW89 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-89-N
Requested peak interconnection capacity by request size500 to under 1,000 MW62.7 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-74-GW
Loads by request size500 to under 1,000 MW74 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-74-N
Requested peak interconnection capacity by request size1,000 to 2,000 MW38.3 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-25-GW
Loads by request size1,000 to 2,000 MW25 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-25-N
Requested peak interconnection capacity by request sizeOver 2,000 MW26.2 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-8-GW
Loads by request sizeOver 2,000 MW8 loads429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 7 · S-8-N
Data center survey: responses (3 rows)
Data center survey: responses (3 rows)
MetricValuePopulation or basisAs ofSourceNote
Community Impact RFI response statusSubmitted on time417 loads465 loads issued the RFIData Center State and Community Impact RFI: Preliminary SummarySlides 2-3 · R-417
Community Impact RFI response statusSubmitted late16 loads465 loads issued the RFIData Center State and Community Impact RFI: Preliminary SummarySlides 2-3 · R-16
Community Impact RFI response statusNot submitted32 loads465 loads issued the RFIData Center State and Community Impact RFI: Preliminary SummarySlides 2-3 · R-32
Data center survey: requested energization (4 rows)
Data center survey: requested energization (4 rows)
MetricValuePopulation or basisAs ofSourceNote
Facilities by requested energization dateRequested energization before 2028169 facilities429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-169
Average "N/A or unable to answer" responses per RFIRequested energization before 202823 responses per RFI429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-169-NA
Facilities by requested energization dateRequested energization January 2028 or later260 facilities429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-260
Average "N/A or unable to answer" responses per RFIRequested energization January 2028 or later30 responses per RFI429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 5 · E-260-NA
Data center survey: by function (6 rows)
Data center survey: by function (6 rows)
MetricValuePopulation or basisAs ofSourceNote
Requested capacity by facility functionNo virtual currency mining175.9 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-407-175.9
Facilities by functionNo virtual currency mining407 facilities429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-407-N-175.9
Requested capacity by facility functionPartial virtual currency mining0.8 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-0.8
Facilities by functionPartial virtual currency mining11 facilities429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-N-0.8
Requested capacity by facility functionAll virtual currency mining0.7 GW429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-0.7
Facilities by functionAll virtual currency mining11 facilities429 reviewed loadsData Center State and Community Impact RFI: Preliminary SummarySlide 8 · FN-11-N-0.7
Oncor-reported figures (7 rows)
Oncor-reported figures (7 rows)
MetricValuePopulation or basisAs ofSourceNote
Customer collateral held for active generation and LC&I transmission POI requestsAll6.0 US$ billion (approximately)OncorOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · ON-1
Large-load customer collateral related to Batch Zero projects (part of ON-1)Batch Zero2.0 US$ billion (approximately)OncorOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-2Release dated Nov. 5, 2026; holder date not separately stated
Large load conditionally classified as base load, already energizedBase load, energized10 GW (approximately)Oncor as transmission service providerOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-3
Large load conditionally classified as base load, not yet energizedBase load, other14 GW (approximately)Oncor as TSPOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-4Power Hopper subtraction: 24 GW base load minus 10 GW energized
Large load conditionally classified as studied loadStudied load21 GW (approximately)Oncor as TSPOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Regulatory Update · ON-5
Other industrial load requests in Oncor LC&I queue (excluding crypto-mining)Other industrial15 GW (approximately)Oncor LC&I queueOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · ON-6Power Hopper subtraction: ~19 GW other industrial including ~4 GW crypto-mining
Crypto-mining load requests in Oncor LC&I queueCrypto-mining4 GW (approximately)Oncor LC&I queueOncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)Operational Highlights · ON-7
Transmission project estimates (11 rows)
Transmission project estimates (11 rows)
MetricValuePopulation or basisAs ofSourceNote
Muscovy and Voss Lake (25RPG009) estimate as submitted by Oncor and LCRA TSCSubmitted381.83 US$ million (approximately)RPG submittal25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)EIR executive summary · TX-MUS-ORIG
Muscovy and Voss Lake Option 7A estimate recommended by ERCOTERCOT-recommended1457 US$ million (approximately)ERCOT independent review; TAC endorsed May 19, 2026; ERCOT Board endorsed June 1, 2026 (June 1-2 meeting)25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Board item slides 1 and 3 · TX-MUS-RECIncludes ~$603.33M of upgrades also identified in 25RPG041
Muscovy and Voss Lake Option 7A cost componentsUpdated initial cost estimate388.94 US$ million (approximately)ERCOT board item25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Slide 3 · TX-MUS-C388Components sum to $1,457.47M
Muscovy and Voss Lake Option 7A cost componentsUpgrades also in Oncor Set 1 project (25RPG041)603.33 US$ million (approximately)ERCOT board item25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Slide 3 · TX-MUS-C603Components sum to $1,457.47M
Muscovy and Voss Lake Option 7A cost componentsAdditional upgrades for peak-load violations465.2 US$ million (approximately)ERCOT board item25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)Slide 3 · TX-MUS-C465Components sum to $1,457.47M
ERCOT Board endorsement of Muscovy and Voss Lake Option 7A (unanimous voice vote)Board endorsed1457 US$ million (approximately)Option 7A, Williamson and Milam counties (Central Texas)Draft General Session Minutes, ERCOT Board of Directors meeting June 1-2, 2026 (posted Sept. 8, 2026)Agenda Item 5.3 · TX-MUS-BOARDEndorsed at the June 1-2, 2026 board meeting (minutes record the vote in the June 1 session, before the recess to June 2) per draft minutes posted Sept. 8, 2026; endorsement is not a cost approved for rates
Additional load modeled, Oncor area, 2029Oncor600 MW (approximately)EIR Table 2.625RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)EIR Table 2.6 · TX-MUS-L1Load type not stated
Additional load modeled, LCRA TSC area, 2029LCRA TSC3573 MW (approximately)EIR Table 2.625RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)EIR Table 2.6 · TX-MUS-L2Load type not stated
Southeast Brownsville estimate as submitted by STECSubmitted96.35 US$ million (approximately)RPG submittal (Nov. 2025)STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 2 · TX-BRO-ORIG
Southeast Brownsville Option 1 estimate recommended by ERCOTERCOT-recommended96.6 US$ million (approximately)ERCOT independent reviewSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slides 14 and 18 · TX-BRO-RECMarked "updated cost estimate from the original estimate"
Medina Load Project estimate as submitted by STECSubmitted492 US$ millionRPG submittal (Dec. 2025); review combined with 25RPG020STEC Medina Load Project - ERCOT Independent Review Scope (RPG, Feb. 2, 2026)Slide 2 · TX-MED-ORIG~1 GW load; June 2031 target; no ERCOT-recommended estimate found by cutoff
Southeast Brownsville options (8 rows)
Southeast Brownsville options (8 rows)
MetricValuePopulation or basisAs ofSourceNote
Estimated costOption 1 (STEC proposed; ERCOT-recommended)96.6 US$ million (approximately)FeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 1-C
Incremental long-term load-serving capability (study result)Option 1 (STEC proposed; ERCOT-recommended)564 MW (approximately)FeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 13 · BRO-Option 1-MW
New right-of-way requiring a CCNOption 1 (STEC proposed; ERCOT-recommended)19.1 miles (approximately)FeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 1-MI
Estimated costOption 2 (STEC alternative)191.2 US$ million (approximately)FeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 2-C
Incremental long-term load-serving capability (study result)Option 2 (STEC alternative)274 MW (approximately)FeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 13 · BRO-Option 2-MW
New right-of-way requiring a CCNOption 2 (STEC alternative)31.1 miles (approximately)FeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 2-MI
Estimated costOption 3 (ERCOT alternative)151.2 US$ million (approximately)InfeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 14 · BRO-Option 3-COption 3 is $151.5M on slide 15
Incremental long-term load-serving capability (study result)Option 3 (ERCOT alternative)881 MW (approximately)InfeasibleSTEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)Slide 13 · BRO-Option 3-MW
January 2027 resource adequacy (MORA) (12 rows)
January 2027 resource adequacy (MORA) (12 rows)
MetricValuePopulation or basisAs ofSourceNote
Installed capacity ratingNatural gas69601 MWOperational resourcesMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Natural gas-I
Expected available capacity, highest-risk hourNatural gas56954 MWDeterministic scenario, normal conditionsMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Natural gas-A81.8% of installed
Installed capacity ratingCoal13705 MWOperational resourcesMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Coal-I
Expected available capacity, highest-risk hourCoal12725 MWDeterministic scenario, normal conditionsMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Coal-A92.8% of installed
Installed capacity ratingNuclear5268 MWOperational resourcesMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Nuclear-I
Expected available capacity, highest-risk hourNuclear5153 MWDeterministic scenario, normal conditionsMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Nuclear-A97.8% of installed
Installed capacity ratingWind40819 MWOperational resourcesMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Wind-I
Expected available capacity, highest-risk hourWind16151 MWDeterministic scenario, normal conditionsMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Wind-A39.6% of installed
Installed capacity ratingSolar41018 MWOperational resourcesMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Solar-I
Expected available capacity, highest-risk hourSolar27 MWDeterministic scenario, normal conditionsMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Solar-A0.1% of installed
Installed capacity ratingBatteries21528 MWOperational resourcesMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Batteries-I
Expected available capacity, highest-risk hourBatteries12525 MWDeterministic scenario, normal conditionsMonthly Outlook for Resource Adequacy (MORA), January 2027Page 5 · MORA-Batteries-A58.2% of installed
New generating capacity (4 rows)
New generating capacity (4 rows)
MetricValuePopulation or basisAs ofSourceNote
New generation capacity added, Oct. 15, 2025 to May 15, 2026Storage4942 MWERCOTItem 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-StorStorage also 10,536 MWh
New generation capacity added, Oct. 15, 2025 to May 15, 2026Solar4243 MWERCOTItem 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-Sola
New generation capacity added, Oct. 15, 2025 to May 15, 2026Natural gas / diesel1515 MWERCOTItem 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-Natu
New generation capacity added, Oct. 15, 2025 to May 15, 2026Wind148 MWERCOTItem 11: CEO Update, Board of Directors meeting June 1-2, 2026Slide 6 · NEW-Wind
Generation queue, September (5 rows)
Generation queue, September (5 rows)
MetricValuePopulation or basisAs ofSourceNote
Generation interconnection queue capacity by fuelBattery166 GWExcludes inactive projectsItem 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-BatteryBattery also ~398 GWh (ERCOT estimate)
Generation interconnection queue capacity by fuelSolar158 GWExcludes inactive projectsItem 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Solar
Generation interconnection queue capacity by fuelGas80 GWExcludes inactive projectsItem 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-GasUp from 65 GW in June update
Generation interconnection queue capacity by fuelWind49 GWExcludes inactive projectsItem 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Wind
Generation interconnection queue capacity by fuelOther4 GWExcludes inactive projectsItem 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)Slide 2 · Q-SEP-Other
Generation interconnection status, October (12 rows)
Generation interconnection status, October (12 rows)
MetricValuePopulation or basisAs ofSourceNote
Generation interconnection requests under studyGas95032.2 MWLarge and small generators; excludes inactiveGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Gas
Large-generator requests with a signed interconnection agreementGas17255.1 MWLarge generators, IA executedGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-GasLarge generators only
Generation interconnection requests under studyWind49781.2 MWLarge and small generators; excludes inactiveGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Wind
Large-generator requests with a signed interconnection agreementWind20510.1 MWLarge generators, IA executedGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-WindLarge generators only
Generation interconnection requests under studySolar151797.8 MWLarge and small generators; excludes inactiveGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Solar
Large-generator requests with a signed interconnection agreementSolar63132.6 MWLarge generators, IA executedGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-SolarLarge generators only
Generation interconnection requests under studyBattery160102.3 MWLarge and small generators; excludes inactiveGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Battery
Large-generator requests with a signed interconnection agreementBattery36511.9 MWLarge generators, IA executedGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-BatteryLarge generators only
Generation interconnection requests under studyOther4700.1 MWLarge and small generators; excludes inactiveGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Other
Large-generator requests with a signed interconnection agreementOther0 MWLarge generators, IA executedGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-OtherLarge generators only
Generation interconnection requests under studyTotal461413.6 MWLarge and small generators; excludes inactiveGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, TOTAL column · GIS-ALL-Total
Large-generator requests with a signed interconnection agreementTotal137409.7 MWLarge generators, IA executedGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Summary tab, large-generator IA columns · GIS-IA-TotalLarge generators only; the Summary tab's separate "Interconnection Agreements Executed" line shows 138,904.65 MW
Signed interconnection agreements by projected year (25 rows)
Signed interconnection agreements by projected year (25 rows)
MetricValuePopulation or basisAs ofSourceNote
Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Gas81.1 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Gas2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Wind4102.4 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Wind2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Solar10648.2 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Solar2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Battery4173.7 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Battery2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2026 or earlier | Other0.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2026-Other2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Gas1928.2 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Gas2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Wind5372.2 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Wind2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Solar17421.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Solar2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Battery8917.3 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Battery2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2027 | Other0.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2027-Other2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Gas9149.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Gas2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Wind5909.7 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Wind2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Solar24032.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Solar2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Battery15816.4 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Battery2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2028 | Other0.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2028-Other2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Gas1478.7 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Gas2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Wind2646.6 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Wind2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Solar8709.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Solar2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Battery6223.3 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Battery2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2029 | Other0.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2029-Other2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Gas4618.1 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Gas2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Wind2479.2 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Wind2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Solar2322.4 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Solar2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Battery1381.1 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Battery2026 bucket includes 5 projects with projected dates in 2025
Signed-IA large-generator capacity by developer-projected commercial operation year2030 or later | Other0.0 MWLarge generators with IA; year = Projected CODGenerator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)Project Details - Large Gen, Projected COD · GIS-YR-2030-Other2026 bucket includes 5 projects with projected dates in 2025
Company-reported campus megawatts (6 rows)
Company-reported campus megawatts (6 rows)
MetricValuePopulation or basisAs ofSourceNote
Total planned power capacity (gross MW)IREN Sweetwater 11400 MW (gross planned power)Company-reportedIREN Form 10-K, fiscal year ended June 30, 2026Item 1, data center projects table · NP-IREN-S1
Total planned power capacity (gross MW)IREN Sweetwater 2600 MW (gross planned power)Company-reportedIREN Form 10-K, fiscal year ended June 30, 2026Item 1, data center projects table · NP-IREN-S2
Total planned power capacity (gross MW)IREN Childress750 MW (gross planned power)Company-reportedIREN Form 10-K, fiscal year ended June 30, 2026Item 1, data center projects table · NP-IREN-C
Sweetwater Hub conditional inclusion in Batch Zero as base load (company-reported)IREN Sweetwater Hub2000 MW (company-reported)Company-reportedIREN Reports Q1 FY27 Results (Form 6-K exhibit)Development and platform updates · NP-IREN-BZ
Developed capacity for Bitcoin miningRiot Corsicana400 MW (developed capacity)Company-reportedRiot Platforms Form 10-Q, quarter ended Sept. 30, 2026Item 2 / business overview · NP-RIOT-DEV
Expected developed capacity on completionRiot Corsicana1000 MW (approximately)Company-reportedRiot Platforms Form 10-Q, quarter ended Sept. 30, 2026Item 2 · NP-RIOT-FULL
Riot Platforms Corsicana delivery schedule (3 rows)
Riot Platforms Corsicana delivery schedule (3 rows)
MetricValuePopulation or basisAs ofSourceNote
Corsicana lease delivery schedule, critical IT capacitySeptember 2027400 MW (critical IT)Company-reportedRiot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)Delivery Schedule bullet · NP-RIOT-SepCritical IT capacity is not metered grid demand
Corsicana lease delivery schedule, critical IT capacityJanuary 2028200 MW (critical IT)Company-reportedRiot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)Delivery Schedule bullet · NP-RIOT-JanCritical IT capacity is not metered grid demand
Corsicana lease delivery schedule, critical IT capacityJuly 2028310 MW (critical IT)Company-reportedRiot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)Delivery Schedule bullet · NP-RIOT-JulCritical IT capacity is not metered grid demand
NRG Texas gas plants (data page only) (3 rows)
NRG Texas gas plants (data page only) (3 rows)
MetricValuePopulation or basisAs ofSourceNote
NRG Texas gas plant capacityT.H. Wharton peaker (operating since May 26, 2026)415 MW (company-described)OperatingNRG Energy Form 10-Q, quarter ended Sept. 30, 2026Glossary; Texas Energy Fund discussion · NRG-415No verified link to any data-center load
NRG Texas gas plant capacityCedar Bayou 5 (under construction)689 MW (company-described)Under constructionNRG Energy Form 10-Q, quarter ended Sept. 30, 2026Glossary; Texas Energy Fund discussion · NRG-689No verified link to any data-center load
NRG Texas gas plant capacityGreens Bayou 6 (under construction)443 MW (company-described)Under constructionNRG Energy Form 10-Q, quarter ended Sept. 30, 2026Glossary; Texas Energy Fund discussion · NRG-443No verified link to any data-center load
Financial security illustration (§25.194) (4 rows)
Financial security illustration (§25.194) (4 rows)
MetricValuePopulation or basisAs ofSourceNote
Intermediate financial security at $50,000 per MW (arithmetic illustration)75 MW requested3.75 US$ millionAdopted 16 TAC §25.194; 2026 value16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-75Illustration only; applicability, credits and later obligations are project-specific
Intermediate financial security at $50,000 per MW (arithmetic illustration)100 MW requested5.0 US$ millionAdopted 16 TAC §25.194; 2026 value16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-100Illustration only; applicability, credits and later obligations are project-specific
Intermediate financial security at $50,000 per MW (arithmetic illustration)500 MW requested25.0 US$ millionAdopted 16 TAC §25.194; 2026 value16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-500Illustration only; applicability, credits and later obligations are project-specific
Intermediate financial security at $50,000 per MW (arithmetic illustration)1,000 MW requested50.0 US$ millionAdopted 16 TAC §25.194; 2026 value16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026§25.194 intermediate agreement financial security · SEC-1000Illustration only; applicability, credits and later obligations are project-specific
Forecasts (2 rows)
Forecasts (2 rows)
MetricValuePopulation or basisAs ofSourceNote
2026 preliminary long-term load forecast, peak2029278003 MWTSP-provided forecast before ERCOT adjustmentMarket Notice M-B051826-01, Proposal to Adjust 2026 Long-Term Load ForecastLong description · LTLF-2029
2026 preliminary long-term load forecast, peak2032367790 MWTSP-provided forecast before ERCOT adjustmentMarket Notice M-B051826-01, Proposal to Adjust 2026 Long-Term Load ForecastLong description · LTLF-2032

Charts

Grid and Transmission · 2026

Four 2026 counts of large-load requests describe four different groups of projects

Gigawatts (GW) requested. Each bar has a different scope and date, so the bars cannot be subtracted to measure cancellations or growth.

Sources: ERCOT update to the Texas Senate Committee on Business and Commerce, July 29, 2026, slide 6; ERCOT presentation to the PUCT open meeting, Sept. 11, 2026 (PUCT Project No. 59142, Item 55), Batch Zero eligibility overview slide; Oncor Q3 2026 results release, Nov. 5, 2026; ERCOT Community Impact RFI summary, Nov. 5, 2026, slide 7.

Chart: Large-load interconnection request totals reported in 2026, by population and date · Methodology for Large-load interconnection request totals reported in 2026, by population and date · CC BY 4.0

Cite this chart

Power Hopper Team. "Large-load interconnection request totals reported in 2026, by population and date." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-large-load-requests-four-snapshots-2026. Accessed [date accessed].

Grid and Transmission · 2026

About 205 GW of large-load requests passed ERCOT's preliminary Batch Zero screen; about 294 GW did not

Requested GW by preliminary category, data as of July 28, 2026. Eligibility was preliminary; final inclusion depends on ERCOT's later review and verification. Preliminary July 28 screen, superseded by ERCOT's Sept. 3 conditional classification (191.8 GW included).

Source: ERCOT, update to the Texas House Committee on State Affairs, Aug. 19, 2026, slide 3 (preliminary; data as of July 28, 2026); superseded by ERCOT Board item 14, Sept. 14-15, 2026.

Chart: ERCOT preliminary Batch Zero eligibility screen, by requested gigawatts, July 28, 2026 · Methodology for ERCOT preliminary Batch Zero eligibility screen, by requested gigawatts, July 28, 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "ERCOT preliminary Batch Zero eligibility screen, by requested gigawatts, July 28, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-batch-zero-eligibility-by-gigawatts-july-2026. Accessed [date accessed].

Grid and Transmission · 2026

362 of 688 large-load projects were not included in ERCOT's preliminary Batch Zero screen

Number of projects by preliminary category, data as of July 28, 2026. Not being included reflects study readiness on that date, not cancellation. Preliminary July 28 screen, superseded by ERCOT's Sept. 3 conditional classification (191.8 GW included).

Source: ERCOT, update to the Texas House Committee on State Affairs, Aug. 19, 2026, slide 3 (preliminary; data as of July 28, 2026).

Chart: ERCOT preliminary Batch Zero eligibility screen, by number of projects, July 28, 2026 · Methodology for ERCOT preliminary Batch Zero eligibility screen, by number of projects, July 28, 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "ERCOT preliminary Batch Zero eligibility screen, by number of projects, July 28, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-batch-zero-eligibility-by-project-count-july-2026. Accessed [date accessed].

Grid and Transmission · 2026

West Texas accounts for 73 GW, or 41%, of the capacity requested in ERCOT's data center survey

Requested peak interconnection capacity of 429 reviewed loads (177.4 GW), by ERCOT load zone. Preliminary as of Nov. 5, 2026.

Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 9.

Chart: Requested data-center interconnection capacity by ERCOT load zone, Nov. 2026 survey · Methodology for Requested data-center interconnection capacity by ERCOT load zone, Nov. 2026 survey · CC BY 4.0

Cite this chart

Power Hopper Team. "Requested data-center interconnection capacity by ERCOT load zone, Nov. 2026 survey." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-capacity-by-load-zone-2026. Accessed [date accessed].

Grid and Transmission · 2026

North has the most surveyed data-center facilities; West has the most requested capacity

Number of reviewed loads by load zone: large loads (75 MW or more) and medium loads (under 75 MW). 429 loads, preliminary as of Nov. 5, 2026.

Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 9.

Chart: Surveyed data-center facilities by ERCOT load zone and load size, Nov. 2026 · Methodology for Surveyed data-center facilities by ERCOT load zone and load size, Nov. 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Surveyed data-center facilities by ERCOT load zone and load size, Nov. 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-facilities-by-load-zone-and-size-2026. Accessed [date accessed].

Grid and Transmission · 2026

33 requests of 1 GW or more account for 64.5 GW, or 36%, of capacity in ERCOT's data center survey

Requested peak interconnection capacity of 429 reviewed loads, by size of each request. Number of loads in parentheses.

Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 7.

Chart: Requested data-center interconnection capacity by request size, Nov. 2026 survey · Methodology for Requested data-center interconnection capacity by request size, Nov. 2026 survey · CC BY 4.0

Cite this chart

Power Hopper Team. "Requested data-center interconnection capacity by request size, Nov. 2026 survey." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-capacity-by-request-size-2026. Accessed [date accessed].

Grid and Transmission · 2026

433 of 465 loads answered ERCOT's data center community impact survey; 32 had not

Response status as of Nov. 5, 2026 (preliminary). All large loads (75 MW or more) responded; the 32 not submitted are medium loads.

Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slides 2-3.

Chart: Response status of ERCOT's data center community impact survey, Nov. 2026 · Methodology for Response status of ERCOT's data center community impact survey, Nov. 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Response status of ERCOT's data center community impact survey, Nov. 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-survey-response-status-2026. Accessed [date accessed].

Grid and Transmission · 2026

Six in 10 surveyed data-center facilities request power in 2028 or later

Reviewed facilities by requested energization date. Later projects answered "N/A or unable to answer" more often (30 vs. 23 per survey on average).

Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 5.

Chart: Surveyed data-center facilities by requested energization date · Methodology for Surveyed data-center facilities by requested energization date · CC BY 4.0

Cite this chart

Power Hopper Team. "Surveyed data-center facilities by requested energization date." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-energization-before-and-after-2028. Accessed [date accessed].

Grid and Transmission · 2026

Facilities with no crypto mining account for 175.9 GW of the 177.4 GW surveyed

Requested peak interconnection capacity by reported computation function, 429 reviewed loads. Facilities in parentheses.

Source: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUCT open meeting Nov. 5, 2026, slide 8.

Chart: Requested capacity in ERCOT's data center survey by crypto-mining function · Methodology for Requested capacity in ERCOT's data center survey by crypto-mining function · CC BY 4.0

Cite this chart

Power Hopper Team. "Requested capacity in ERCOT's data center survey by crypto-mining function." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-data-center-requested-capacity-by-crypto-mining-function-2026. Accessed [date accessed].

Grid and Transmission · 2026

ERCOT expects to send follow-up questions to 80% of developers in its data center verification review

Batch Zero eligibility verification ordered after the Governor's Aug. 3, 2026 letter. ERCOT says it must finish the review to report to the PUCT on Dec. 10, 2026.

Sources: ERCOT, Batch Zero Eligibility Verification Process Update, Nov. 5, 2026, slide 2; ERCOT Market Notices M-A080326-01 and M-A090926-01; ERCOT Board item 14, Sept. 14-15, 2026, slides 3-4.

Chart: Status of ERCOT's Batch Zero eligibility verification, Nov. 5, 2026 · Methodology for Status of ERCOT's Batch Zero eligibility verification, Nov. 5, 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Status of ERCOT's Batch Zero eligibility verification, Nov. 5, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-batch-zero-verification-review-status-nov-2026. Accessed [date accessed].

Grid and Transmission · 2026

Oncor reports about $2 billion of its $6 billion in customer collateral relates to Batch Zero large loads

Customer collateral Oncor holds for active generation and large commercial and industrial transmission interconnection requests, billions of dollars.

Source: Oncor Electric Delivery, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 5, 2026.

Chart: Oncor customer collateral for interconnection requests, and the part tied to Batch Zero large loads · Methodology for Oncor customer collateral for interconnection requests, and the part tied to Batch Zero large loads · CC BY 4.0

Cite this chart

Power Hopper Team. "Oncor customer collateral for interconnection requests, and the part tied to Batch Zero large loads." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-oncor-customer-collateral-batch-zero-large-loads-2026. Accessed [date accessed].

Grid and Transmission · 2026

Oncor reports 45 GW of large load conditionally classified in Batch Zero in its area, 10 GW already energized

Gigawatts conditionally classified by ERCOT, as reported by Oncor on Nov. 5, 2026. Classification is conditional pending ERCOT's audit.

Source: Oncor Electric Delivery, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 5, 2026.

Chart: Large load conditionally classified in ERCOT's Batch Zero where Oncor is the transmission provider · Methodology for Large load conditionally classified in ERCOT's Batch Zero where Oncor is the transmission provider · CC BY 4.0

Cite this chart

Power Hopper Team. "Large load conditionally classified in ERCOT's Batch Zero where Oncor is the transmission provider." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-oncor-batch-zero-conditional-classification-gigawatts-2026. Accessed [date accessed].

Grid and Transmission · 2026

Data centers make up about 293 GW of the load in Oncor's large-customer interconnection queue

Requested load in Oncor's active transmission LC&I interconnection queue (795 requests), gigawatts, as of Sept. 30, 2026.

Source: Oncor Electric Delivery, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 5, 2026.

Chart: Oncor transmission large commercial and industrial interconnection queue by load type, Sept. 30, 2026 · Methodology for Oncor transmission large commercial and industrial interconnection queue by load type, Sept. 30, 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Oncor transmission large commercial and industrial interconnection queue by load type, Sept. 30, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-oncor-large-load-queue-data-centers-vs-other-industries-2026. Accessed [date accessed].

Grid and Transmission · 2026

ERCOT's generation queue held 461 GW in October; 137 GW of large-generator projects had signed interconnection agreements

Gigawatts of generation interconnection requests under study (excluding inactive projects) and large-generator capacity with a signed interconnection agreement.

Source: ERCOT Generator Interconnection Status report, October 2026 (data as of Oct. 31, 2026); Power Hopper totals.

Chart: ERCOT generation interconnection queue and capacity with signed interconnection agreements, by fuel, October 2026 · Methodology for ERCOT generation interconnection queue and capacity with signed interconnection agreements, by fuel, October 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "ERCOT generation interconnection queue and capacity with signed interconnection agreements, by fuel, October 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-generation-interconnection-queue-signed-agreements-by-fuel-oct-2026. Accessed [date accessed].

Grid and Transmission · 2026

Generators with signed ERCOT agreements project 54.9 GW for 2028, the largest year

Gigawatts of large-generator capacity with a signed interconnection agreement, by projected commercial operation date in ERCOT's October 2026 report.

Source: ERCOT Generator Interconnection Status report, October 2026 (data as of Oct. 31, 2026); Power Hopper totals.

Chart: Generation capacity with signed ERCOT interconnection agreements, by developer-projected commercial operation year and fuel · Methodology for Generation capacity with signed ERCOT interconnection agreements, by developer-projected commercial operation year and fuel · CC BY 4.0

Cite this chart

Power Hopper Team. "Generation capacity with signed ERCOT interconnection agreements, by developer-projected commercial operation year and fuel." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-signed-generation-agreements-by-projected-year-and-fuel-2026. Accessed [date accessed].

Grid and Transmission · 2026

ERCOT's January 2027 outlook expects 82% of gas capacity but under 1% of solar to be available at 8 a.m.

Installed capacity rating and expected available capacity, hour ending 8 a.m. CST, deterministic scenario under normal conditions. Gigawatts.

Source: ERCOT, Monthly Outlook for Resource Adequacy, January 2027 (published Nov. 6, 2026), p. 5.

Chart: ERCOT January 2027 outlook: installed and expected available capacity by fuel in the highest-risk hour · Methodology for ERCOT January 2027 outlook: installed and expected available capacity by fuel in the highest-risk hour · CC BY 4.0

Cite this chart

Power Hopper Team. "ERCOT January 2027 outlook: installed and expected available capacity by fuel in the highest-risk hour." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-january-2027-installed-vs-expected-available-capacity-by-fuel. Accessed [date accessed].

Grid and Transmission · 2026

ERCOT added more than 10,800 MW of new generating capacity from October 2025 to May 2026, led by batteries

Megawatts of new capacity by fuel, Oct. 15, 2025 to May 15, 2026, as reported to ERCOT's board.

Source: ERCOT, CEO Update, Board of Directors meeting June 1-2, 2026, slide 6.

Chart: New generation capacity added to the ERCOT grid by fuel, Oct. 15, 2025 to May 15, 2026 · Methodology for New generation capacity added to the ERCOT grid by fuel, Oct. 15, 2025 to May 15, 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "New generation capacity added to the ERCOT grid by fuel, Oct. 15, 2025 to May 15, 2026." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-ercot-new-generation-capacity-by-fuel-oct-2025-may-2026. Accessed [date accessed].

Grid and Transmission · 2026

About $603 million of the $1.457 billion Muscovy-Voss Lake estimate is work also listed in another Oncor project

Cost components of Option 7A as listed in ERCOT's board materials, millions of dollars (approximate).

Source: ERCOT, Board item 5.3: 25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, slide 3 (Board meeting June 1-2, 2026).

Chart: Components of ERCOT's $1.457 billion estimate for the Muscovy and Voss Lake project (Option 7A) · Methodology for Components of ERCOT's $1.457 billion estimate for the Muscovy and Voss Lake project (Option 7A) · CC BY 4.0

Cite this chart

Power Hopper Team. "Components of ERCOT's $1.457 billion estimate for the Muscovy and Voss Lake project (Option 7A)." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-muscovy-voss-lake-transmission-project-cost-components-2026. Accessed [date accessed].

Grid and Transmission · 2026

ERCOT recommended the least-cost Southeast Brownsville option, estimated at about $96.6 million

Estimated cost by option, millions of dollars. Labels show ERCOT's modeled incremental load-serving capability and feasibility.

Source: ERCOT, STEC Southeast Brownsville Large Load Project EIR recommendation, RPG meeting May 11, 2026, slides 13-15 and 18.

Chart: Southeast Brownsville large-load transmission options: cost estimate and modeled load-serving capability · Methodology for Southeast Brownsville large-load transmission options: cost estimate and modeled load-serving capability · CC BY 4.0

Cite this chart

Power Hopper Team. "Southeast Brownsville large-load transmission options: cost estimate and modeled load-serving capability." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-southeast-brownsville-transmission-options-cost-and-load-serving-capability-2026. Accessed [date accessed].

Grid and Transmission · 2026

Riot's Corsicana lease schedules 910 MW of critical IT capacity in three phases in 2027 and 2028

Critical IT megawatts by scheduled delivery date, as reported by Riot Platforms on Nov. 4, 2026. Cumulative by date.

Source: Riot Platforms, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1), Nov. 4, 2026; Form 10-Q for the quarter ended Sept. 30, 2026.

Chart: Riot Platforms Corsicana lease: critical IT capacity delivery schedule · Methodology for Riot Platforms Corsicana lease: critical IT capacity delivery schedule · CC BY 4.0

Cite this chart

Power Hopper Team. "Riot Platforms Corsicana lease: critical IT capacity delivery schedule." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-riot-corsicana-critical-it-capacity-delivery-schedule-2027-2028. Accessed [date accessed].

Grid and Transmission · 2026

Company-reported megawatts for Texas data-center campuses use different measures, none of them metered grid use

Megawatts as reported in SEC filings. Gross planned power, developed capacity and leased critical IT capacity are different measures and are not comparable.

Sources: IREN Form 10-K for fiscal 2026 (as of June 30, 2026) and Q1 FY27 results (Nov. 5, 2026); Riot Platforms Form 10-Q and results release (Nov. 4, 2026).

Chart: Company-reported megawatts at four Texas data-center campuses, by type of measure · Methodology for Company-reported megawatts at four Texas data-center campuses, by type of measure · CC BY 4.0

Cite this chart

Power Hopper Team. "Company-reported megawatts at four Texas data-center campuses, by type of measure." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-data-center-campuses-company-reported-megawatts-by-measure-2026. Accessed [date accessed].

Grid and Transmission · 2026

NRG reports 415 MW of new Texas gas capacity in operation and 1,132 MW under construction

Megawatts as described in NRG's Form 10-Q for the quarter ended Sept. 30, 2026.

Source: NRG Energy, Form 10-Q for the quarter ended Sept. 30, 2026 (filed Nov. 9, 2026).

Chart: NRG Energy Texas gas plant additions: in operation and under construction · Methodology for NRG Energy Texas gas plant additions: in operation and under construction · CC BY 4.0

Cite this chart

Power Hopper Team. "NRG Energy Texas gas plant additions: in operation and under construction." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-nrg-texas-gas-plants-operating-and-under-construction-2026. Accessed [date accessed].

Grid and Transmission · 2026

At $50,000 per MW, a 1,000 MW request would post $50 million in security under the new Texas rule

Arithmetic illustration of the 2026 value in 16 TAC §25.194 for selected request sizes. Not any project's actual security.

Source: Texas Register, Oct. 2, 2026, adopted 16 TAC §25.194 (PUCT Project No. 58481), effective Oct. 8, 2026; Power Hopper arithmetic.

Chart: Illustration: intermediate financial security under the adopted Texas large-load rule at $50,000 per MW · Methodology for Illustration: intermediate financial security under the adopted Texas large-load rule at $50,000 per MW · CC BY 4.0

Cite this chart

Power Hopper Team. "Illustration: intermediate financial security under the adopted Texas large-load rule at $50,000 per MW." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-large-load-interconnection-financial-security-50000-per-mw-illustration. Accessed [date accessed].

Grid and Transmission · 2026

Five records would be needed to calculate any household bill effect of these grid projects; Power Hopper did not find them all public

Status of each input for the three transmission reviews in this story, as of Nov. 10, 2026.

Sources: Texas Register, July 24, 2026 (PUCT Project No. 58000 proposal) and Oct. 2, 2026 (adopted §25.194); NRG Form 10-Q, Q3 2026; ERCOT RPG documents for 25RPG009, 25RPG039 and 25RPG046.

Chart: Records needed before a household bill effect of a large-load transmission project can be calculated · Methodology for Records needed before a household bill effect of a large-load transmission project can be calculated · CC BY 4.0

Cite this chart

Power Hopper Team. "Records needed before a household bill effect of a large-load transmission project can be calculated." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-large-load-transmission-cost-allocation-records-not-yet-public. Accessed [date accessed].

Grid and Transmission · 2026

Power Hopper re-checked 111 claims against primary records: 75 verified as written

Status of each claim and figure after re-fetching ERCOT, PUCT, Texas Register and SEC records on Nov. 10, 2026.

Source: Power Hopper review, FACTCHECK.csv (Nov. 10, 2026).

Chart: Power Hopper fact-check of an incoming research package on Texas data centers and the grid · Methodology for Power Hopper fact-check of an incoming research package on Texas data centers and the grid · CC BY 4.0

Cite this chart

Power Hopper Team. "Power Hopper fact-check of an incoming research package on Texas data centers and the grid." Chart. Texas data center large-load grid figures: ERCOT requests, survey results, upgrade estimates and generation queues, 2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-data-center-large-load-grid-data#chart-texas-data-center-grid-claims-fact-check-status-2026. Accessed [date accessed].

Methodology

  1. Populations. Rows superseded by a later ERCOT figure (REQ-1/REQ-2: 438 GW and 89%, June 18; REQ-3 and the batch-zero-screen rows: July 28 preliminary screen) are kept with a "superseded by" note and shown as history. The current figures are REQ-6 to REQ-9 (ERCOT Senate Business and Commerce update, July 29, 2026, slide 6, data as of June 2026) and the batch-zero-sept-classification rows (ERCOT Board item 14, Sept. 14-15, 2026). ERCOT reported the 191.8 GW included total in its Sept. 11, 2026 presentation to the PUCT (Project No. 59142, Item 55); it equals ERCOT's base (66.4 GW) plus studied (125.4 GW) values; ERCOT's key-takeaway text gives studied load as 127.9 GW. ERCOT's 420,812 MW (90.2%) data-center value implies a base of about 466.5 GW, which ERCOT does not reconcile with its 474.7 GW chart total. Every row names its population and date (for example, "all large-load requests tracked by ERCOT, June 18, 2026" or "429 loads reviewed in ERCOT's preliminary survey summary, Nov. 5, 2026"). Rows from different populations are not summed or subtracted.
  2. ERCOT presentations and notices. Values copied from the cited slide or page. Rounded slide values are kept as published; where slide values do not add to a stated total, both are shown.
  3. Generation queue. Power Hopper totaled ERCOT's October 2026 Generator Interconnection Status workbook (data as of Oct. 31, 2026) by fuel, and by projected commercial operation year for projects whose study phase shows a signed interconnection agreement (IA). The signed-IA total (137,409.7 MW) is the sum of the Summary tab's large-generator IA columns; the tab's separate "Interconnection Agreements Executed" line shows 138,904.65 MW, and the workbook does not explain the difference. "Under study" totals include small generators.
  4. Company figures. Taken from SEC filings and attributed. Each keeps the company's own measure (gross planned power, developed capacity, critical IT capacity, nameplate MW). None is metered grid demand.
  5. Illustration. The financial-security rows multiply the 2026 §25.194 rate ($50,000 per MW) by example request sizes. They are not any project's actual security.

Full methodology

Limitations

  • ERCOT told its board in September 2026 that it had paused approvals to energize new data centers and crypto mining facilities of 75 MW or more until the verification and community impact reviews are complete (row PAUSE-75).
  • Requests, eligibility and survey responses are not load forecasts. ERCOT's verification report and final Batch Zero results were not public as of Nov. 10, 2026.
  • ERCOT's 2026 transmission review documents for Muscovy-Voss Lake, Medina and Southeast Brownsville describe large-load or reliability projects and do not identify data centers.
  • Transmission estimates are planning estimates, not costs approved for rates. The ERCOT Board endorsed Muscovy-Voss Lake Option 7A (Williamson and Milam counties, Central Texas) at its June 1-2, 2026 meeting; an endorsement is not a cost approved for rates. Cost allocation (PUCT Project No. 58000) was a proposal as of Nov. 10, 2026; its PUCT filings list comments through Oct. 1, 2026 and no adoption order. The §25.194 interconnection rule (Project No. 58481) was adopted Sept. 18, 2026 and took effect Oct. 8.
  • The data do not measure effects on household bills, prices or reliability.
  • The January 2027 MORA is a single modeled hour under normal conditions; its p. 3 and p. 5 tables show different solar and storage figures (p. 5 used).

Data dictionary

Data dictionary
FieldDescription
idRow identifier
groupGroup of related figures (one population, date and source per group)
metricWhat the figure measures
categoryCategory within the metric
valueFigure as published by the source (rounded values kept as published)
unitUnit, with qualifiers such as 'about' or 'more than' as the source states them
population_or_basisPopulation or basis the figure describes
as_ofDate the figure describes
source_idSource key
source_titleSource document
source_urlLink to the source
locatorPage, slide, table or paragraph in the source
noteContext, including superseded-by notes

Power Hopper is not affiliated with or endorsed by the PUCT, ERCOT, the Office of the Texas Governor, the Texas Secretary of State, the State Office of Administrative Hearings, the U.S. Energy Information Administration, the Texas House Committee on State Affairs, the Texas Senate Committee on Business and Commerce, the U.S. Securities and Exchange Commission, Oncor Electric Delivery, Sempra, LCRA Transmission Services Corporation, South Texas Electric Cooperative, CPS Energy, IREN, Riot Platforms, NRG Energy, or any other company, cooperative, utility, project or developer named on this page.

Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility, and is not affiliated with or endorsed by the PUCT, ERCOT or any utility, supplier or data provider named above. This brief was prepared with AI assistance.