 "title": "Texas large-load and data-center grid figures, as of Nov. 10, 2026",
 "publisher": "Power Hopper Team",
 "license": "CC BY 4.0",
 "status": "Source-checked",
 "note": "Different rows describe different populations, dates and measures. Do not add or subtract across groups.",
 "records": [
  {
   "id": "REQ-1",
   "group": "request-snapshots",
   "metric": "Large-load interconnection requests tracked by ERCOT",
   "category": "All large-load requests",
   "value": 438,
   "unit": "GW (more than)",
   "population_or_basis": "All large-load requests ERCOT was tracking; nearly 89% from data centers",
   "as_of": "2026-06-18",
   "source_id": "JUN",
   "source_title": "ERCOT news release on PUCT approval of the Batch Zero process",
   "source_url": "https://www.ercot.com/news/release/06182026-puct-approves-ercots",
   "locator": "Paragraph 3",
   "note": "ERCOT: \"more than 438,000 MW\". Superseded by REQ-6 (about 474 GW as of June 2026, ERCOT Senate B&C July 29); shown as history"
  },
  {
   "id": "REQ-2",
   "group": "request-snapshots",
   "metric": "Data-center share of large-load requests",
   "category": "Data centers",
   "value": 89,
   "unit": "% (nearly)",
   "population_or_basis": "Same population as REQ-1",
   "as_of": "2026-06-18",
   "source_id": "JUN",
   "source_title": "ERCOT news release on PUCT approval of the Batch Zero process",
   "source_url": "https://www.ercot.com/news/release/06182026-puct-approves-ercots",
   "locator": "Paragraph 3",
   "note": "ERCOT: \"nearly 89 percent\"; Power Hopper does not multiply the two rounded figures. Superseded by REQ-7/REQ-8 (about 90%; 420,812 MW, 90.2%); shown as history"
  },
  {
   "id": "REQ-3",
   "group": "request-snapshots",
   "metric": "Large load preliminarily eligible for Batch Zero",
   "category": "Eligible (base, allocated or TBD)",
   "value": 205,
   "unit": "GW (approximately)",
   "population_or_basis": "Batch Zero eligibility screen; preliminary",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3, Key Takeaways",
   "note": "Slide bar labels sum to 204 GW because of rounding. Superseded by ERCOT's Sept. 3 conditional classification (BZ-SEP rows: 191.8 GW conditionally included); shown as history"
  },
  {
   "id": "REQ-4",
   "group": "request-snapshots",
   "metric": "Requested peak interconnection capacity, reviewed RFI dataset",
   "category": "429 reviewed loads",
   "value": 177.4,
   "unit": "GW",
   "population_or_basis": "Community Impact RFI reviewed dataset (243 large, 186 medium loads)",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7, Total",
   "note": "Preliminary, subject to change"
  },
  {
   "id": "REQ-5",
   "group": "request-snapshots",
   "metric": "Data-center requests in Oncor transmission LC&I interconnection queue",
   "category": "Oncor service area",
   "value": 293,
   "unit": "GW (approximately)",
   "population_or_basis": "Oncor active transmission LC&I queue, 795 requests",
   "as_of": "2026-09-30",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Operational Highlights",
   "note": "Company-reported; a utility-level queue, not an ERCOT total"
  },
  {
   "id": "REQ-6",
   "group": "request-snapshots",
   "metric": "Large-load interconnection requests tracked by ERCOT",
   "category": "All large-load requests",
   "value": 474,
   "unit": "GW (approximately)",
   "population_or_basis": "All large Loads seeking interconnection, as of June 2026",
   "as_of": "2026-06",
   "source_id": "SEN",
   "source_title": "ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf",
   "locator": "Slide 6, Key Takeaway",
   "note": "ERCOT: \"approximately 474 GW\"; slide 6 chart totals 474.1 GW (2031) and 474.7 GW (2032-2033)"
  },
  {
   "id": "REQ-7",
   "group": "request-snapshots",
   "metric": "Data-center share of large-load requests",
   "category": "Data centers",
   "value": 90,
   "unit": "% (approximately)",
   "population_or_basis": "Same population as REQ-6",
   "as_of": "2026-06",
   "source_id": "SEN",
   "source_title": "ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf",
   "locator": "Slide 6, Key Takeaway",
   "note": "ERCOT: \"~90% are data centers\""
  },
  {
   "id": "REQ-8",
   "group": "request-snapshots",
   "metric": "Data-center large-load requests (ERCOT pie value)",
   "category": "Data centers",
   "value": 420812,
   "unit": "MW",
   "population_or_basis": "Large Loads by Project Type, as of June 2026",
   "as_of": "2026-06",
   "source_id": "SEN",
   "source_title": "ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf",
   "locator": "Slide 6, pie chart label \"90.2% (420812 MW)\"",
   "note": "ERCOT pie value; implied base ≈466.5 GW differs from 474.7 GW total; not reconciled by ERCOT"
  },
  {
   "id": "REQ-9",
   "group": "request-snapshots",
   "metric": "Large load observed energized",
   "category": "Observed energized",
   "value": 5.9,
   "unit": "GW",
   "population_or_basis": "Actual and projected large-load growth table, 2026 column",
   "as_of": "2026-06",
   "source_id": "SEN",
   "source_title": "ERCOT update to the Texas Senate Committee on Business and Commerce, Panel 1: Assessing the Grid (large-load requests as of June 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf",
   "locator": "Slide 6, table row \"Observed Energized\"",
   "note": "Cumulative observed energized large load shown by ERCOT"
  },
  {
   "id": "BZ-SEP-INC-GW",
   "group": "batch-zero-sept-classification",
   "metric": "Large-load requested capacity by Batch Zero conditional classification",
   "category": "Conditionally included (base + studied)",
   "value": 191.8,
   "unit": "GW",
   "population_or_basis": "Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026; ERCOT Updates presentation, PUCT open meeting (PUCT Project No. 59142, Item 55)",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf; https://interchange.puc.texas.gov/Documents/59142_55_1681987.PDF",
   "locator": "Slides 1, 5, 6; PUCT Project No. 59142, Item 55, Batch Zero eligibility overview slide (Key Takeaways)",
   "note": "ERCOT, PUCT Project No. 59142, Item 55 (Sept. 11, 2026): \"191.8 GW in Batch Zero, combined base and studied load\" (equals slide 6 values 66.4 GW + 125.4 GW); ERCOT slide 5: \"362 Large Loads in either base or studied load categories\"; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes"
  },
  {
   "id": "BZ-SEP-INC-N",
   "group": "batch-zero-sept-classification",
   "metric": "Large loads / projects by Batch Zero conditional classification",
   "category": "Conditionally included (base + studied)",
   "value": 362,
   "unit": "large loads (projects)",
   "population_or_basis": "Same as BZ-SEP GW rows",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 1, 5, 6",
   "note": ""
  },
  {
   "id": "BZ-SEP-BASE-GW",
   "group": "batch-zero-sept-classification",
   "metric": "Large-load requested capacity by Batch Zero conditional classification",
   "category": "Conditionally included as base load",
   "value": 66.4,
   "unit": "GW",
   "population_or_basis": "Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 1, 5, 6",
   "note": "Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes"
  },
  {
   "id": "BZ-SEP-BASE-N",
   "group": "batch-zero-sept-classification",
   "metric": "Large loads / projects by Batch Zero conditional classification",
   "category": "Conditionally included as base load",
   "value": 204,
   "unit": "large loads (projects)",
   "population_or_basis": "Same as BZ-SEP GW rows",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 1, 5, 6",
   "note": ""
  },
  {
   "id": "BZ-SEP-STU-GW",
   "group": "batch-zero-sept-classification",
   "metric": "Large-load requested capacity by Batch Zero conditional classification",
   "category": "Conditionally included as studied load",
   "value": 125.4,
   "unit": "GW",
   "population_or_basis": "Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 1, 5, 6",
   "note": "125.4 GW on slide 6 chart; 127.9 GW in slide 1 key-takeaway text; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes"
  },
  {
   "id": "BZ-SEP-STU-N",
   "group": "batch-zero-sept-classification",
   "metric": "Large loads / projects by Batch Zero conditional classification",
   "category": "Conditionally included as studied load",
   "value": 158,
   "unit": "large loads (projects)",
   "population_or_basis": "Same as BZ-SEP GW rows",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 1, 5, 6",
   "note": ""
  },
  {
   "id": "BZ-SEP-EXC-GW",
   "group": "batch-zero-sept-classification",
   "metric": "Large-load requested capacity by Batch Zero conditional classification",
   "category": "Excluded from Batch Zero",
   "value": 302.2,
   "unit": "GW",
   "population_or_basis": "Batch Zero large loads (75 MW or more), conditional classification sent to TSPs Sept. 3, 2026",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 1, 5, 6",
   "note": "Slide 6: \"This chart omits excluded load (302.2 GW, 373 projects)\"; Final inclusion depends on ERCOT eligibility verification (December); subject to dispute processes"
  },
  {
   "id": "BZ-SEP-EXC-N",
   "group": "batch-zero-sept-classification",
   "metric": "Large loads / projects by Batch Zero conditional classification",
   "category": "Excluded from Batch Zero",
   "value": 373,
   "unit": "large loads (projects)",
   "population_or_basis": "Same as BZ-SEP GW rows",
   "as_of": "2026-09-03",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 1, 5, 6",
   "note": ""
  },
  {
   "id": "PAUSE-75",
   "group": "verification",
   "metric": "Size threshold for ERCOT pause on approvals to energize new data centers and crypto mining facilities",
   "category": "Pause threshold",
   "value": 75,
   "unit": "MW or greater",
   "population_or_basis": "New Large Load data centers and virtual currency mining facilities not yet connected",
   "as_of": "2026-09-14",
   "source_id": "BZB",
   "source_title": "Item 14: Batch Zero Update, Board of Directors meeting Sept. 14-15, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf",
   "locator": "Slides 3-4",
   "note": "Paused until completion of the verification and audit and the community impact review (ERCOT, Sept. 14-15 board)"
  },
  {
   "id": "BZ-GW-150",
   "group": "batch-zero-screen",
   "metric": "Large-load requests by preliminary Batch Zero eligibility",
   "category": "Eligible as base load",
   "value": 65,
   "unit": "GW (rounded slide label)",
   "population_or_basis": "Eligible",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 bar labels",
   "note": ""
  },
  {
   "id": "BZ-N-150",
   "group": "batch-zero-screen",
   "metric": "Projects by preliminary Batch Zero eligibility",
   "category": "Eligible as base load",
   "value": 150,
   "unit": "projects",
   "population_or_basis": "Eligible",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 legend",
   "note": ""
  },
  {
   "id": "BZ-GW-49",
   "group": "batch-zero-screen",
   "metric": "Large-load requests by preliminary Batch Zero eligibility",
   "category": "Eligible, base or allocated to be determined",
   "value": 25,
   "unit": "GW (rounded slide label)",
   "population_or_basis": "Eligible",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 bar labels",
   "note": ""
  },
  {
   "id": "BZ-N-49",
   "group": "batch-zero-screen",
   "metric": "Projects by preliminary Batch Zero eligibility",
   "category": "Eligible, base or allocated to be determined",
   "value": 49,
   "unit": "projects",
   "population_or_basis": "Eligible",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 legend",
   "note": ""
  },
  {
   "id": "BZ-GW-127",
   "group": "batch-zero-screen",
   "metric": "Large-load requests by preliminary Batch Zero eligibility",
   "category": "Eligible as allocated load",
   "value": 114,
   "unit": "GW (rounded slide label)",
   "population_or_basis": "Eligible",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 bar labels",
   "note": ""
  },
  {
   "id": "BZ-N-127",
   "group": "batch-zero-screen",
   "metric": "Projects by preliminary Batch Zero eligibility",
   "category": "Eligible as allocated load",
   "value": 127,
   "unit": "projects",
   "population_or_basis": "Eligible",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 legend",
   "note": ""
  },
  {
   "id": "BZ-GW-47",
   "group": "batch-zero-screen",
   "metric": "Large-load requests by preliminary Batch Zero eligibility",
   "category": "Not included: no dynamic model by July 10",
   "value": 20,
   "unit": "GW (rounded slide label)",
   "population_or_basis": "Not included",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 bar labels",
   "note": ""
  },
  {
   "id": "BZ-N-47",
   "group": "batch-zero-screen",
   "metric": "Projects by preliminary Batch Zero eligibility",
   "category": "Not included: no dynamic model by July 10",
   "value": 47,
   "unit": "projects",
   "population_or_basis": "Not included",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 legend",
   "note": ""
  },
  {
   "id": "BZ-GW-315",
   "group": "batch-zero-screen",
   "metric": "Large-load requests by preliminary Batch Zero eligibility",
   "category": "Not included: no qualifying study",
   "value": 274,
   "unit": "GW (rounded slide label)",
   "population_or_basis": "Not included",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 bar labels",
   "note": ""
  },
  {
   "id": "BZ-N-315",
   "group": "batch-zero-screen",
   "metric": "Projects by preliminary Batch Zero eligibility",
   "category": "Not included: no qualifying study",
   "value": 315,
   "unit": "projects",
   "population_or_basis": "Not included",
   "as_of": "2026-07-28",
   "source_id": "JUL",
   "source_title": "ERCOT Update, House Committee on State Affairs (Batch Zero eligibility, data as of July 28, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf",
   "locator": "Slide 3 legend",
   "note": ""
  },
  {
   "id": "Z-West-GW",
   "group": "rfi-load-zone",
   "metric": "Requested peak interconnection capacity by ERCOT load zone",
   "category": "West",
   "value": 73,
   "unit": "GW (rounded)",
   "population_or_basis": "429 reviewed loads; zone from facility GPS",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": "37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded"
  },
  {
   "id": "Z-West-LL",
   "group": "rfi-load-zone",
   "metric": "Large loads (75 MW or more) by load zone",
   "category": "West",
   "value": 88,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "Z-West-ML",
   "group": "rfi-load-zone",
   "metric": "Medium loads (under 75 MW) by load zone",
   "category": "West",
   "value": 39,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "Z-South-GW",
   "group": "rfi-load-zone",
   "metric": "Requested peak interconnection capacity by ERCOT load zone",
   "category": "South",
   "value": 49,
   "unit": "GW (rounded)",
   "population_or_basis": "429 reviewed loads; zone from facility GPS",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": "37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded"
  },
  {
   "id": "Z-South-LL",
   "group": "rfi-load-zone",
   "metric": "Large loads (75 MW or more) by load zone",
   "category": "South",
   "value": 72,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "Z-South-ML",
   "group": "rfi-load-zone",
   "metric": "Medium loads (under 75 MW) by load zone",
   "category": "South",
   "value": 38,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "Z-North-GW",
   "group": "rfi-load-zone",
   "metric": "Requested peak interconnection capacity by ERCOT load zone",
   "category": "North",
   "value": 45,
   "unit": "GW (rounded)",
   "population_or_basis": "429 reviewed loads; zone from facility GPS",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": "37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded"
  },
  {
   "id": "Z-North-LL",
   "group": "rfi-load-zone",
   "metric": "Large loads (75 MW or more) by load zone",
   "category": "North",
   "value": 69,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "Z-North-ML",
   "group": "rfi-load-zone",
   "metric": "Medium loads (under 75 MW) by load zone",
   "category": "North",
   "value": 85,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "Z-Houston-GW",
   "group": "rfi-load-zone",
   "metric": "Requested peak interconnection capacity by ERCOT load zone",
   "category": "Houston",
   "value": 10,
   "unit": "GW (rounded)",
   "population_or_basis": "429 reviewed loads; zone from facility GPS",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": "37 loads near a zone boundary; actual zone set at interconnection; NOIE zones excluded"
  },
  {
   "id": "Z-Houston-LL",
   "group": "rfi-load-zone",
   "metric": "Large loads (75 MW or more) by load zone",
   "category": "Houston",
   "value": 14,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "Z-Houston-ML",
   "group": "rfi-load-zone",
   "metric": "Medium loads (under 75 MW) by load zone",
   "category": "Houston",
   "value": 24,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 9",
   "note": ""
  },
  {
   "id": "S-43-GW",
   "group": "rfi-size-band",
   "metric": "Requested peak interconnection capacity by request size",
   "category": "Under 50 MW",
   "value": 1.5,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-43-N",
   "group": "rfi-size-band",
   "metric": "Loads by request size",
   "category": "Under 50 MW",
   "value": 43,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-143-GW",
   "group": "rfi-size-band",
   "metric": "Requested peak interconnection capacity by request size",
   "category": "50 to under 75 MW",
   "value": 9.8,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-143-N",
   "group": "rfi-size-band",
   "metric": "Loads by request size",
   "category": "50 to under 75 MW",
   "value": 143,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-47-GW",
   "group": "rfi-size-band",
   "metric": "Requested peak interconnection capacity by request size",
   "category": "75 to under 200 MW",
   "value": 7.2,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-47-N",
   "group": "rfi-size-band",
   "metric": "Loads by request size",
   "category": "75 to under 200 MW",
   "value": 47,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-89-GW",
   "group": "rfi-size-band",
   "metric": "Requested peak interconnection capacity by request size",
   "category": "200 to under 500 MW",
   "value": 31.7,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-89-N",
   "group": "rfi-size-band",
   "metric": "Loads by request size",
   "category": "200 to under 500 MW",
   "value": 89,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-74-GW",
   "group": "rfi-size-band",
   "metric": "Requested peak interconnection capacity by request size",
   "category": "500 to under 1,000 MW",
   "value": 62.7,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-74-N",
   "group": "rfi-size-band",
   "metric": "Loads by request size",
   "category": "500 to under 1,000 MW",
   "value": 74,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-25-GW",
   "group": "rfi-size-band",
   "metric": "Requested peak interconnection capacity by request size",
   "category": "1,000 to 2,000 MW",
   "value": 38.3,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-25-N",
   "group": "rfi-size-band",
   "metric": "Loads by request size",
   "category": "1,000 to 2,000 MW",
   "value": 25,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-8-GW",
   "group": "rfi-size-band",
   "metric": "Requested peak interconnection capacity by request size",
   "category": "Over 2,000 MW",
   "value": 26.2,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "S-8-N",
   "group": "rfi-size-band",
   "metric": "Loads by request size",
   "category": "Over 2,000 MW",
   "value": 8,
   "unit": "loads",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 7",
   "note": ""
  },
  {
   "id": "R-417",
   "group": "rfi-response",
   "metric": "Community Impact RFI response status",
   "category": "Submitted on time",
   "value": 417,
   "unit": "loads",
   "population_or_basis": "465 loads issued the RFI",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slides 2-3",
   "note": ""
  },
  {
   "id": "R-16",
   "group": "rfi-response",
   "metric": "Community Impact RFI response status",
   "category": "Submitted late",
   "value": 16,
   "unit": "loads",
   "population_or_basis": "465 loads issued the RFI",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slides 2-3",
   "note": ""
  },
  {
   "id": "R-32",
   "group": "rfi-response",
   "metric": "Community Impact RFI response status",
   "category": "Not submitted",
   "value": 32,
   "unit": "loads",
   "population_or_basis": "465 loads issued the RFI",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slides 2-3",
   "note": ""
  },
  {
   "id": "E-169",
   "group": "rfi-energization",
   "metric": "Facilities by requested energization date",
   "category": "Requested energization before 2028",
   "value": 169,
   "unit": "facilities",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 5",
   "note": ""
  },
  {
   "id": "E-169-NA",
   "group": "rfi-energization",
   "metric": "Average \"N/A or unable to answer\" responses per RFI",
   "category": "Requested energization before 2028",
   "value": 23,
   "unit": "responses per RFI",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 5",
   "note": ""
  },
  {
   "id": "E-260",
   "group": "rfi-energization",
   "metric": "Facilities by requested energization date",
   "category": "Requested energization January 2028 or later",
   "value": 260,
   "unit": "facilities",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 5",
   "note": ""
  },
  {
   "id": "E-260-NA",
   "group": "rfi-energization",
   "metric": "Average \"N/A or unable to answer\" responses per RFI",
   "category": "Requested energization January 2028 or later",
   "value": 30,
   "unit": "responses per RFI",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 5",
   "note": ""
  },
  {
   "id": "FN-407-175.9",
   "group": "rfi-function",
   "metric": "Requested capacity by facility function",
   "category": "No virtual currency mining",
   "value": 175.9,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 8",
   "note": ""
  },
  {
   "id": "FN-407-N-175.9",
   "group": "rfi-function",
   "metric": "Facilities by function",
   "category": "No virtual currency mining",
   "value": 407,
   "unit": "facilities",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 8",
   "note": ""
  },
  {
   "id": "FN-11-0.8",
   "group": "rfi-function",
   "metric": "Requested capacity by facility function",
   "category": "Partial virtual currency mining",
   "value": 0.8,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 8",
   "note": ""
  },
  {
   "id": "FN-11-N-0.8",
   "group": "rfi-function",
   "metric": "Facilities by function",
   "category": "Partial virtual currency mining",
   "value": 11,
   "unit": "facilities",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 8",
   "note": ""
  },
  {
   "id": "FN-11-0.7",
   "group": "rfi-function",
   "metric": "Requested capacity by facility function",
   "category": "All virtual currency mining",
   "value": 0.7,
   "unit": "GW",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 8",
   "note": ""
  },
  {
   "id": "FN-11-N-0.7",
   "group": "rfi-function",
   "metric": "Facilities by function",
   "category": "All virtual currency mining",
   "value": 11,
   "unit": "facilities",
   "population_or_basis": "429 reviewed loads",
   "as_of": "2026-11-05",
   "source_id": "RFI",
   "source_title": "Data Center State and Community Impact RFI: Preliminary Summary",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf",
   "locator": "Slide 8",
   "note": ""
  },
  {
   "id": "V-1",
   "group": "verification",
   "metric": "Developers whose first-round verification responses ERCOT reviewed",
   "category": "Developers",
   "value": 257,
   "unit": "developers",
   "population_or_basis": "Batch Zero verification",
   "as_of": "2026-11-05",
   "source_id": "AUD",
   "source_title": "Batch Zero Eligibility Verification Process Update",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/ERCOT-Verification-RFI-Update.pdf",
   "locator": "Slide 2",
   "note": ""
  },
  {
   "id": "V-2",
   "group": "verification",
   "metric": "Share of developers ERCOT expects to send second-round RFIs",
   "category": "Developers",
   "value": 80,
   "unit": "%",
   "population_or_basis": "Batch Zero verification",
   "as_of": "2026-11-05",
   "source_id": "AUD",
   "source_title": "Batch Zero Eligibility Verification Process Update",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/ERCOT-Verification-RFI-Update.pdf",
   "locator": "Slide 2",
   "note": ""
  },
  {
   "id": "V-3",
   "group": "verification",
   "metric": "First-round questions reviewed",
   "category": "Questions",
   "value": 5140,
   "unit": "questions (approximately)",
   "population_or_basis": "Batch Zero verification",
   "as_of": "2026-11-05",
   "source_id": "AUD",
   "source_title": "Batch Zero Eligibility Verification Process Update",
   "source_url": "https://www.ercot.com/files/docs/2026/11/05/ERCOT-Verification-RFI-Update.pdf",
   "locator": "Slide 2",
   "note": ""
  },
  {
   "id": "ON-1",
   "group": "oncor",
   "metric": "Customer collateral held for active generation and LC&I transmission POI requests",
   "category": "All",
   "value": 6.0,
   "unit": "US$ billion (approximately)",
   "population_or_basis": "Oncor",
   "as_of": "2026-09-30",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Operational Highlights",
   "note": ""
  },
  {
   "id": "ON-2",
   "group": "oncor",
   "metric": "Large-load customer collateral related to Batch Zero projects (part of ON-1)",
   "category": "Batch Zero",
   "value": 2.0,
   "unit": "US$ billion (approximately)",
   "population_or_basis": "Oncor",
   "as_of": "2026-11-05",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Regulatory Update",
   "note": "Release dated Nov. 5, 2026; holder date not separately stated"
  },
  {
   "id": "ON-3",
   "group": "oncor",
   "metric": "Large load conditionally classified as base load, already energized",
   "category": "Base load, energized",
   "value": 10,
   "unit": "GW (approximately)",
   "population_or_basis": "Oncor as transmission service provider",
   "as_of": "2026-11-05",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Regulatory Update",
   "note": ""
  },
  {
   "id": "ON-4",
   "group": "oncor",
   "metric": "Large load conditionally classified as base load, not yet energized",
   "category": "Base load, other",
   "value": 14,
   "unit": "GW (approximately)",
   "population_or_basis": "Oncor as TSP",
   "as_of": "2026-11-05",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Regulatory Update",
   "note": "Power Hopper subtraction: 24 GW base load minus 10 GW energized"
  },
  {
   "id": "ON-5",
   "group": "oncor",
   "metric": "Large load conditionally classified as studied load",
   "category": "Studied load",
   "value": 21,
   "unit": "GW (approximately)",
   "population_or_basis": "Oncor as TSP",
   "as_of": "2026-11-05",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Regulatory Update",
   "note": ""
  },
  {
   "id": "ON-6",
   "group": "oncor",
   "metric": "Other industrial load requests in Oncor LC&I queue (excluding crypto-mining)",
   "category": "Other industrial",
   "value": 15,
   "unit": "GW (approximately)",
   "population_or_basis": "Oncor LC&I queue",
   "as_of": "2026-09-30",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Operational Highlights",
   "note": "Power Hopper subtraction: ~19 GW other industrial including ~4 GW crypto-mining"
  },
  {
   "id": "ON-7",
   "group": "oncor",
   "metric": "Crypto-mining load requests in Oncor LC&I queue",
   "category": "Crypto-mining",
   "value": 4,
   "unit": "GW (approximately)",
   "population_or_basis": "Oncor LC&I queue",
   "as_of": "2026-09-30",
   "source_id": "ONCOR",
   "source_title": "Oncor Electric Delivery, third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1193311/000119312526448721/d159004dex991.htm",
   "locator": "Operational Highlights",
   "note": ""
  },
  {
   "id": "TX-MUS-ORIG",
   "group": "transmission",
   "metric": "Muscovy and Voss Lake (25RPG009) estimate as submitted by Oncor and LCRA TSC",
   "category": "Submitted",
   "value": 381.83,
   "unit": "US$ million (approximately)",
   "population_or_basis": "RPG submittal",
   "as_of": "2025-04",
   "source_id": "MUS",
   "source_title": "25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/22/5.3-25RPG009-Oncor-and-LCRA-TSC-Muscovy-and-Voss-Lake-345_138-kV-Regional-Planning-Group-RPG-Project.pdf",
   "locator": "EIR executive summary",
   "note": ""
  },
  {
   "id": "TX-MUS-REC",
   "group": "transmission",
   "metric": "Muscovy and Voss Lake Option 7A estimate recommended by ERCOT",
   "category": "ERCOT-recommended",
   "value": 1457,
   "unit": "US$ million (approximately)",
   "population_or_basis": "ERCOT independent review; TAC endorsed May 19, 2026; ERCOT Board endorsed June 1, 2026 (June 1-2 meeting)",
   "as_of": "2026-05-22",
   "source_id": "MUS",
   "source_title": "25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/22/5.3-25RPG009-Oncor-and-LCRA-TSC-Muscovy-and-Voss-Lake-345_138-kV-Regional-Planning-Group-RPG-Project.pdf",
   "locator": "Board item slides 1 and 3",
   "note": "Includes ~$603.33M of upgrades also identified in 25RPG041"
  },
  {
   "id": "TX-MUS-C388",
   "group": "transmission",
   "metric": "Muscovy and Voss Lake Option 7A cost components",
   "category": "Updated initial cost estimate",
   "value": 388.94,
   "unit": "US$ million (approximately)",
   "population_or_basis": "ERCOT board item",
   "as_of": "2026-05-22",
   "source_id": "MUS",
   "source_title": "25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/22/5.3-25RPG009-Oncor-and-LCRA-TSC-Muscovy-and-Voss-Lake-345_138-kV-Regional-Planning-Group-RPG-Project.pdf",
   "locator": "Slide 3",
   "note": "Components sum to $1,457.47M"
  },
  {
   "id": "TX-MUS-C603",
   "group": "transmission",
   "metric": "Muscovy and Voss Lake Option 7A cost components",
   "category": "Upgrades also in Oncor Set 1 project (25RPG041)",
   "value": 603.33,
   "unit": "US$ million (approximately)",
   "population_or_basis": "ERCOT board item",
   "as_of": "2026-05-22",
   "source_id": "MUS",
   "source_title": "25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/22/5.3-25RPG009-Oncor-and-LCRA-TSC-Muscovy-and-Voss-Lake-345_138-kV-Regional-Planning-Group-RPG-Project.pdf",
   "locator": "Slide 3",
   "note": "Components sum to $1,457.47M"
  },
  {
   "id": "TX-MUS-C465",
   "group": "transmission",
   "metric": "Muscovy and Voss Lake Option 7A cost components",
   "category": "Additional upgrades for peak-load violations",
   "value": 465.2,
   "unit": "US$ million (approximately)",
   "population_or_basis": "ERCOT board item",
   "as_of": "2026-05-22",
   "source_id": "MUS",
   "source_title": "25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/22/5.3-25RPG009-Oncor-and-LCRA-TSC-Muscovy-and-Voss-Lake-345_138-kV-Regional-Planning-Group-RPG-Project.pdf",
   "locator": "Slide 3",
   "note": "Components sum to $1,457.47M"
  },
  {
   "id": "TX-MUS-BOARD",
   "group": "transmission",
   "metric": "ERCOT Board endorsement of Muscovy and Voss Lake Option 7A (unanimous voice vote)",
   "category": "Board endorsed",
   "value": 1457,
   "unit": "US$ million (approximately)",
   "population_or_basis": "Option 7A, Williamson and Milam counties (Central Texas)",
   "as_of": "2026-06-01",
   "source_id": "MIN",
   "source_title": "Draft General Session Minutes, ERCOT Board of Directors meeting June 1-2, 2026 (posted Sept. 8, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/09/08/3-June-1-2-2026-Board-of-Directors-General-Session-Meeting-Minutes.pdf",
   "locator": "Agenda Item 5.3",
   "note": "Endorsed at the June 1-2, 2026 board meeting (minutes record the vote in the June 1 session, before the recess to June 2) per draft minutes posted Sept. 8, 2026; endorsement is not a cost approved for rates"
  },
  {
   "id": "TX-MUS-L1",
   "group": "transmission",
   "metric": "Additional load modeled, Oncor area, 2029",
   "category": "Oncor",
   "value": 600,
   "unit": "MW (approximately)",
   "population_or_basis": "EIR Table 2.6",
   "as_of": "2026-05-22",
   "source_id": "MUS",
   "source_title": "25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/22/5.3-25RPG009-Oncor-and-LCRA-TSC-Muscovy-and-Voss-Lake-345_138-kV-Regional-Planning-Group-RPG-Project.pdf",
   "locator": "EIR Table 2.6",
   "note": "Load type not stated"
  },
  {
   "id": "TX-MUS-L2",
   "group": "transmission",
   "metric": "Additional load modeled, LCRA TSC area, 2029",
   "category": "LCRA TSC",
   "value": 3573,
   "unit": "MW (approximately)",
   "population_or_basis": "EIR Table 2.6",
   "as_of": "2026-05-22",
   "source_id": "MUS",
   "source_title": "25RPG009 Oncor and LCRA TSC Muscovy and Voss Lake 345/138-kV RPG Project, Board item 5.3 and EIR (Board meeting June 1-2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/22/5.3-25RPG009-Oncor-and-LCRA-TSC-Muscovy-and-Voss-Lake-345_138-kV-Regional-Planning-Group-RPG-Project.pdf",
   "locator": "EIR Table 2.6",
   "note": "Load type not stated"
  },
  {
   "id": "TX-BRO-ORIG",
   "group": "transmission",
   "metric": "Southeast Brownsville estimate as submitted by STEC",
   "category": "Submitted",
   "value": 96.35,
   "unit": "US$ million (approximately)",
   "population_or_basis": "RPG submittal (Nov. 2025)",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 2",
   "note": ""
  },
  {
   "id": "TX-BRO-REC",
   "group": "transmission",
   "metric": "Southeast Brownsville Option 1 estimate recommended by ERCOT",
   "category": "ERCOT-recommended",
   "value": 96.6,
   "unit": "US$ million (approximately)",
   "population_or_basis": "ERCOT independent review",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slides 14 and 18",
   "note": "Marked \"updated cost estimate from the original estimate\""
  },
  {
   "id": "TX-MED-ORIG",
   "group": "transmission",
   "metric": "Medina Load Project estimate as submitted by STEC",
   "category": "Submitted",
   "value": 492,
   "unit": "US$ million",
   "population_or_basis": "RPG submittal (Dec. 2025); review combined with 25RPG020",
   "as_of": "2026-02-02",
   "source_id": "MED",
   "source_title": "STEC Medina Load Project - ERCOT Independent Review Scope (RPG, Feb. 2, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/01/30/7_EIR-STEC-Medina-County-Large-Load-Project_SCOPE_Feb2026_RPG.pdf",
   "locator": "Slide 2",
   "note": "~1 GW load; June 2031 target; no ERCOT-recommended estimate found by cutoff"
  },
  {
   "id": "BRO-Option 1-C",
   "group": "brownsville-options",
   "metric": "Estimated cost",
   "category": "Option 1 (STEC proposed; ERCOT-recommended)",
   "value": 96.6,
   "unit": "US$ million (approximately)",
   "population_or_basis": "Feasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 14",
   "note": ""
  },
  {
   "id": "BRO-Option 1-MW",
   "group": "brownsville-options",
   "metric": "Incremental long-term load-serving capability (study result)",
   "category": "Option 1 (STEC proposed; ERCOT-recommended)",
   "value": 564,
   "unit": "MW (approximately)",
   "population_or_basis": "Feasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 13",
   "note": ""
  },
  {
   "id": "BRO-Option 1-MI",
   "group": "brownsville-options",
   "metric": "New right-of-way requiring a CCN",
   "category": "Option 1 (STEC proposed; ERCOT-recommended)",
   "value": 19.1,
   "unit": "miles (approximately)",
   "population_or_basis": "Feasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 14",
   "note": ""
  },
  {
   "id": "BRO-Option 2-C",
   "group": "brownsville-options",
   "metric": "Estimated cost",
   "category": "Option 2 (STEC alternative)",
   "value": 191.2,
   "unit": "US$ million (approximately)",
   "population_or_basis": "Feasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 14",
   "note": ""
  },
  {
   "id": "BRO-Option 2-MW",
   "group": "brownsville-options",
   "metric": "Incremental long-term load-serving capability (study result)",
   "category": "Option 2 (STEC alternative)",
   "value": 274,
   "unit": "MW (approximately)",
   "population_or_basis": "Feasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 13",
   "note": ""
  },
  {
   "id": "BRO-Option 2-MI",
   "group": "brownsville-options",
   "metric": "New right-of-way requiring a CCN",
   "category": "Option 2 (STEC alternative)",
   "value": 31.1,
   "unit": "miles (approximately)",
   "population_or_basis": "Feasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 14",
   "note": ""
  },
  {
   "id": "BRO-Option 3-C",
   "group": "brownsville-options",
   "metric": "Estimated cost",
   "category": "Option 3 (ERCOT alternative)",
   "value": 151.2,
   "unit": "US$ million (approximately)",
   "population_or_basis": "Infeasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 14",
   "note": "Option 3 is $151.5M on slide 15"
  },
  {
   "id": "BRO-Option 3-MW",
   "group": "brownsville-options",
   "metric": "Incremental long-term load-serving capability (study result)",
   "category": "Option 3 (ERCOT alternative)",
   "value": 881,
   "unit": "MW (approximately)",
   "population_or_basis": "Infeasible",
   "as_of": "2026-05-11",
   "source_id": "BRO",
   "source_title": "STEC Southeast Brownsville Large Load Project - ERCOT Independent Review Recommendation (RPG, May 11, 2026)",
   "source_url": "https://www.ercot.com/files/docs/2026/05/08/3.-EIR_STEC_Southeast_Brownsville_Large_Load_Project_Recommendation_RPG_May_2026_FINAL.pdf",
   "locator": "Slide 13",
   "note": ""
  },
  {
   "id": "MORA-Natural gas-I",
   "group": "mora-jan-2027",
   "metric": "Installed capacity rating",
   "category": "Natural gas",
   "value": 69601,
   "unit": "MW",
   "population_or_basis": "Operational resources",
   "as_of": "2027-01 (HE 8 a.m. CST, deterministic)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": ""
  },
  {
   "id": "MORA-Natural gas-A",
   "group": "mora-jan-2027",
   "metric": "Expected available capacity, highest-risk hour",
   "category": "Natural gas",
   "value": 56954,
   "unit": "MW",
   "population_or_basis": "Deterministic scenario, normal conditions",
   "as_of": "2027-01 (HE 8 a.m. CST)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": "81.8% of installed"
  },
  {
   "id": "MORA-Coal-I",
   "group": "mora-jan-2027",
   "metric": "Installed capacity rating",
   "category": "Coal",
   "value": 13705,
   "unit": "MW",
   "population_or_basis": "Operational resources",
   "as_of": "2027-01 (HE 8 a.m. CST, deterministic)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": ""
  },
  {
   "id": "MORA-Coal-A",
   "group": "mora-jan-2027",
   "metric": "Expected available capacity, highest-risk hour",
   "category": "Coal",
   "value": 12725,
   "unit": "MW",
   "population_or_basis": "Deterministic scenario, normal conditions",
   "as_of": "2027-01 (HE 8 a.m. CST)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": "92.8% of installed"
  },
  {
   "id": "MORA-Nuclear-I",
   "group": "mora-jan-2027",
   "metric": "Installed capacity rating",
   "category": "Nuclear",
   "value": 5268,
   "unit": "MW",
   "population_or_basis": "Operational resources",
   "as_of": "2027-01 (HE 8 a.m. CST, deterministic)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": ""
  },
  {
   "id": "MORA-Nuclear-A",
   "group": "mora-jan-2027",
   "metric": "Expected available capacity, highest-risk hour",
   "category": "Nuclear",
   "value": 5153,
   "unit": "MW",
   "population_or_basis": "Deterministic scenario, normal conditions",
   "as_of": "2027-01 (HE 8 a.m. CST)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": "97.8% of installed"
  },
  {
   "id": "MORA-Wind-I",
   "group": "mora-jan-2027",
   "metric": "Installed capacity rating",
   "category": "Wind",
   "value": 40819,
   "unit": "MW",
   "population_or_basis": "Operational resources",
   "as_of": "2027-01 (HE 8 a.m. CST, deterministic)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": ""
  },
  {
   "id": "MORA-Wind-A",
   "group": "mora-jan-2027",
   "metric": "Expected available capacity, highest-risk hour",
   "category": "Wind",
   "value": 16151,
   "unit": "MW",
   "population_or_basis": "Deterministic scenario, normal conditions",
   "as_of": "2027-01 (HE 8 a.m. CST)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": "39.6% of installed"
  },
  {
   "id": "MORA-Solar-I",
   "group": "mora-jan-2027",
   "metric": "Installed capacity rating",
   "category": "Solar",
   "value": 41018,
   "unit": "MW",
   "population_or_basis": "Operational resources",
   "as_of": "2027-01 (HE 8 a.m. CST, deterministic)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": ""
  },
  {
   "id": "MORA-Solar-A",
   "group": "mora-jan-2027",
   "metric": "Expected available capacity, highest-risk hour",
   "category": "Solar",
   "value": 27,
   "unit": "MW",
   "population_or_basis": "Deterministic scenario, normal conditions",
   "as_of": "2027-01 (HE 8 a.m. CST)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": "0.1% of installed"
  },
  {
   "id": "MORA-Batteries-I",
   "group": "mora-jan-2027",
   "metric": "Installed capacity rating",
   "category": "Batteries",
   "value": 21528,
   "unit": "MW",
   "population_or_basis": "Operational resources",
   "as_of": "2027-01 (HE 8 a.m. CST, deterministic)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": ""
  },
  {
   "id": "MORA-Batteries-A",
   "group": "mora-jan-2027",
   "metric": "Expected available capacity, highest-risk hour",
   "category": "Batteries",
   "value": 12525,
   "unit": "MW",
   "population_or_basis": "Deterministic scenario, normal conditions",
   "as_of": "2027-01 (HE 8 a.m. CST)",
   "source_id": "MORA",
   "source_title": "Monthly Outlook for Resource Adequacy (MORA), January 2027",
   "source_url": "https://www.ercot.com/files/docs/2026/11/06/MORA_January_2027.pdf",
   "locator": "Page 5",
   "note": "58.2% of installed"
  },
  {
   "id": "NEW-Stor",
   "group": "new-capacity",
   "metric": "New generation capacity added, Oct. 15, 2025 to May 15, 2026",
   "category": "Storage",
   "value": 4942,
   "unit": "MW",
   "population_or_basis": "ERCOT",
   "as_of": "2026-05-15",
   "source_id": "CEO",
   "source_title": "Item 11: CEO Update, Board of Directors meeting June 1-2, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/05/28/11-CEO-Update.pdf",
   "locator": "Slide 6",
   "note": "Storage also 10,536 MWh"
  },
  {
   "id": "NEW-Sola",
   "group": "new-capacity",
   "metric": "New generation capacity added, Oct. 15, 2025 to May 15, 2026",
   "category": "Solar",
   "value": 4243,
   "unit": "MW",
   "population_or_basis": "ERCOT",
   "as_of": "2026-05-15",
   "source_id": "CEO",
   "source_title": "Item 11: CEO Update, Board of Directors meeting June 1-2, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/05/28/11-CEO-Update.pdf",
   "locator": "Slide 6",
   "note": ""
  },
  {
   "id": "NEW-Natu",
   "group": "new-capacity",
   "metric": "New generation capacity added, Oct. 15, 2025 to May 15, 2026",
   "category": "Natural gas / diesel",
   "value": 1515,
   "unit": "MW",
   "population_or_basis": "ERCOT",
   "as_of": "2026-05-15",
   "source_id": "CEO",
   "source_title": "Item 11: CEO Update, Board of Directors meeting June 1-2, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/05/28/11-CEO-Update.pdf",
   "locator": "Slide 6",
   "note": ""
  },
  {
   "id": "NEW-Wind",
   "group": "new-capacity",
   "metric": "New generation capacity added, Oct. 15, 2025 to May 15, 2026",
   "category": "Wind",
   "value": 148,
   "unit": "MW",
   "population_or_basis": "ERCOT",
   "as_of": "2026-05-15",
   "source_id": "CEO",
   "source_title": "Item 11: CEO Update, Board of Directors meeting June 1-2, 2026",
   "source_url": "https://www.ercot.com/files/docs/2026/05/28/11-CEO-Update.pdf",
   "locator": "Slide 6",
   "note": ""
  },
  {
   "id": "Q-SEP-Battery",
   "group": "gen-queue-sep",
   "metric": "Generation interconnection queue capacity by fuel",
   "category": "Battery",
   "value": 166,
   "unit": "GW",
   "population_or_basis": "Excludes inactive projects",
   "as_of": "2026-09 board update",
   "source_id": "GEN",
   "source_title": "Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)",
   "source_url": "https://www.ercot.com/files/docs/2026/09/17/10-Interconnection-and-Grid-Analysis-Update-REVISED.pdf",
   "locator": "Slide 2",
   "note": "Battery also ~398 GWh (ERCOT estimate)"
  },
  {
   "id": "Q-SEP-Solar",
   "group": "gen-queue-sep",
   "metric": "Generation interconnection queue capacity by fuel",
   "category": "Solar",
   "value": 158,
   "unit": "GW",
   "population_or_basis": "Excludes inactive projects",
   "as_of": "2026-09 board update",
   "source_id": "GEN",
   "source_title": "Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)",
   "source_url": "https://www.ercot.com/files/docs/2026/09/17/10-Interconnection-and-Grid-Analysis-Update-REVISED.pdf",
   "locator": "Slide 2",
   "note": ""
  },
  {
   "id": "Q-SEP-Gas",
   "group": "gen-queue-sep",
   "metric": "Generation interconnection queue capacity by fuel",
   "category": "Gas",
   "value": 80,
   "unit": "GW",
   "population_or_basis": "Excludes inactive projects",
   "as_of": "2026-09 board update",
   "source_id": "GEN",
   "source_title": "Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)",
   "source_url": "https://www.ercot.com/files/docs/2026/09/17/10-Interconnection-and-Grid-Analysis-Update-REVISED.pdf",
   "locator": "Slide 2",
   "note": "Up from 65 GW in June update"
  },
  {
   "id": "Q-SEP-Wind",
   "group": "gen-queue-sep",
   "metric": "Generation interconnection queue capacity by fuel",
   "category": "Wind",
   "value": 49,
   "unit": "GW",
   "population_or_basis": "Excludes inactive projects",
   "as_of": "2026-09 board update",
   "source_id": "GEN",
   "source_title": "Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)",
   "source_url": "https://www.ercot.com/files/docs/2026/09/17/10-Interconnection-and-Grid-Analysis-Update-REVISED.pdf",
   "locator": "Slide 2",
   "note": ""
  },
  {
   "id": "Q-SEP-Other",
   "group": "gen-queue-sep",
   "metric": "Generation interconnection queue capacity by fuel",
   "category": "Other",
   "value": 4,
   "unit": "GW",
   "population_or_basis": "Excludes inactive projects",
   "as_of": "2026-09 board update",
   "source_id": "GEN",
   "source_title": "Item 10: Interconnection and Grid Analysis Update, Board of Directors meeting Sept. 14-15, 2026 (revised)",
   "source_url": "https://www.ercot.com/files/docs/2026/09/17/10-Interconnection-and-Grid-Analysis-Update-REVISED.pdf",
   "locator": "Slide 2",
   "note": ""
  },
  {
   "id": "GIS-ALL-Gas",
   "group": "gis-oct-2026",
   "metric": "Generation interconnection requests under study",
   "category": "Gas",
   "value": 95032.2,
   "unit": "MW",
   "population_or_basis": "Large and small generators; excludes inactive",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, TOTAL column",
   "note": ""
  },
  {
   "id": "GIS-IA-Gas",
   "group": "gis-oct-2026",
   "metric": "Large-generator requests with a signed interconnection agreement",
   "category": "Gas",
   "value": 17255.1,
   "unit": "MW",
   "population_or_basis": "Large generators, IA executed",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, large-generator IA columns",
   "note": "Large generators only"
  },
  {
   "id": "GIS-ALL-Wind",
   "group": "gis-oct-2026",
   "metric": "Generation interconnection requests under study",
   "category": "Wind",
   "value": 49781.2,
   "unit": "MW",
   "population_or_basis": "Large and small generators; excludes inactive",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, TOTAL column",
   "note": ""
  },
  {
   "id": "GIS-IA-Wind",
   "group": "gis-oct-2026",
   "metric": "Large-generator requests with a signed interconnection agreement",
   "category": "Wind",
   "value": 20510.1,
   "unit": "MW",
   "population_or_basis": "Large generators, IA executed",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, large-generator IA columns",
   "note": "Large generators only"
  },
  {
   "id": "GIS-ALL-Solar",
   "group": "gis-oct-2026",
   "metric": "Generation interconnection requests under study",
   "category": "Solar",
   "value": 151797.8,
   "unit": "MW",
   "population_or_basis": "Large and small generators; excludes inactive",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, TOTAL column",
   "note": ""
  },
  {
   "id": "GIS-IA-Solar",
   "group": "gis-oct-2026",
   "metric": "Large-generator requests with a signed interconnection agreement",
   "category": "Solar",
   "value": 63132.6,
   "unit": "MW",
   "population_or_basis": "Large generators, IA executed",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, large-generator IA columns",
   "note": "Large generators only"
  },
  {
   "id": "GIS-ALL-Battery",
   "group": "gis-oct-2026",
   "metric": "Generation interconnection requests under study",
   "category": "Battery",
   "value": 160102.3,
   "unit": "MW",
   "population_or_basis": "Large and small generators; excludes inactive",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, TOTAL column",
   "note": ""
  },
  {
   "id": "GIS-IA-Battery",
   "group": "gis-oct-2026",
   "metric": "Large-generator requests with a signed interconnection agreement",
   "category": "Battery",
   "value": 36511.9,
   "unit": "MW",
   "population_or_basis": "Large generators, IA executed",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, large-generator IA columns",
   "note": "Large generators only"
  },
  {
   "id": "GIS-ALL-Other",
   "group": "gis-oct-2026",
   "metric": "Generation interconnection requests under study",
   "category": "Other",
   "value": 4700.1,
   "unit": "MW",
   "population_or_basis": "Large and small generators; excludes inactive",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, TOTAL column",
   "note": ""
  },
  {
   "id": "GIS-IA-Other",
   "group": "gis-oct-2026",
   "metric": "Large-generator requests with a signed interconnection agreement",
   "category": "Other",
   "value": 0,
   "unit": "MW",
   "population_or_basis": "Large generators, IA executed",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, large-generator IA columns",
   "note": "Large generators only"
  },
  {
   "id": "GIS-ALL-Total",
   "group": "gis-oct-2026",
   "metric": "Generation interconnection requests under study",
   "category": "Total",
   "value": 461413.6,
   "unit": "MW",
   "population_or_basis": "Large and small generators; excludes inactive",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, TOTAL column",
   "note": ""
  },
  {
   "id": "GIS-IA-Total",
   "group": "gis-oct-2026",
   "metric": "Large-generator requests with a signed interconnection agreement",
   "category": "Total",
   "value": 137409.7,
   "unit": "MW",
   "population_or_basis": "Large generators, IA executed",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Summary tab, large-generator IA columns",
   "note": "Large generators only; the Summary tab's separate \"Interconnection Agreements Executed\" line shows 138,904.65 MW"
  },
  {
   "id": "GIS-YR-2026-Gas",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2026 or earlier | Gas",
   "value": 81.1,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2026-Wind",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2026 or earlier | Wind",
   "value": 4102.4,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2026-Solar",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2026 or earlier | Solar",
   "value": 10648.2,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2026-Battery",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2026 or earlier | Battery",
   "value": 4173.7,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2026-Other",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2026 or earlier | Other",
   "value": 0.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2027-Gas",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2027 | Gas",
   "value": 1928.2,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2027-Wind",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2027 | Wind",
   "value": 5372.2,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2027-Solar",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2027 | Solar",
   "value": 17421.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2027-Battery",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2027 | Battery",
   "value": 8917.3,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2027-Other",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2027 | Other",
   "value": 0.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2028-Gas",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2028 | Gas",
   "value": 9149.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2028-Wind",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2028 | Wind",
   "value": 5909.7,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2028-Solar",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2028 | Solar",
   "value": 24032.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2028-Battery",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2028 | Battery",
   "value": 15816.4,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2028-Other",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2028 | Other",
   "value": 0.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2029-Gas",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2029 | Gas",
   "value": 1478.7,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2029-Wind",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2029 | Wind",
   "value": 2646.6,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2029-Solar",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2029 | Solar",
   "value": 8709.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2029-Battery",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2029 | Battery",
   "value": 6223.3,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2029-Other",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2029 | Other",
   "value": 0.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2030-Gas",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2030 or later | Gas",
   "value": 4618.1,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2030-Wind",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2030 or later | Wind",
   "value": 2479.2,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2030-Solar",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2030 or later | Solar",
   "value": 2322.4,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2030-Battery",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2030 or later | Battery",
   "value": 1381.1,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "GIS-YR-2030-Other",
   "group": "gis-oct-2026-ia-by-year",
   "metric": "Signed-IA large-generator capacity by developer-projected commercial operation year",
   "category": "2030 or later | Other",
   "value": 0.0,
   "unit": "MW",
   "population_or_basis": "Large generators with IA; year = Projected COD",
   "as_of": "2026-10-31",
   "source_id": "GIS",
   "source_title": "Generator Interconnection Status (GIS) report, October 2026 (data as of Oct. 31, 2026)",
   "source_url": "https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1293955078",
   "locator": "Project Details - Large Gen, Projected COD",
   "note": "2026 bucket includes 5 projects with projected dates in 2025"
  },
  {
   "id": "NP-IREN-S1",
   "group": "named-projects",
   "metric": "Total planned power capacity (gross MW)",
   "category": "IREN Sweetwater 1",
   "value": 1400,
   "unit": "MW (gross planned power)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-06-30",
   "source_id": "IREN10K",
   "source_title": "IREN Form 10-K, fiscal year ended June 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1878848/000187884826000052/iren-20260630.htm",
   "locator": "Item 1, data center projects table",
   "note": ""
  },
  {
   "id": "NP-IREN-S2",
   "group": "named-projects",
   "metric": "Total planned power capacity (gross MW)",
   "category": "IREN Sweetwater 2",
   "value": 600,
   "unit": "MW (gross planned power)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-06-30",
   "source_id": "IREN10K",
   "source_title": "IREN Form 10-K, fiscal year ended June 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1878848/000187884826000052/iren-20260630.htm",
   "locator": "Item 1, data center projects table",
   "note": ""
  },
  {
   "id": "NP-IREN-C",
   "group": "named-projects",
   "metric": "Total planned power capacity (gross MW)",
   "category": "IREN Childress",
   "value": 750,
   "unit": "MW (gross planned power)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-06-30",
   "source_id": "IREN10K",
   "source_title": "IREN Form 10-K, fiscal year ended June 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1878848/000187884826000052/iren-20260630.htm",
   "locator": "Item 1, data center projects table",
   "note": ""
  },
  {
   "id": "NP-IREN-BZ",
   "group": "named-projects",
   "metric": "Sweetwater Hub conditional inclusion in Batch Zero as base load (company-reported)",
   "category": "IREN Sweetwater Hub",
   "value": 2000,
   "unit": "MW (company-reported)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-11-05",
   "source_id": "IREN",
   "source_title": "IREN Reports Q1 FY27 Results (Form 6-K exhibit)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1878848/000187884826000065/irenreportsq1-fy27result.htm",
   "locator": "Development and platform updates",
   "note": ""
  },
  {
   "id": "NP-RIOT-DEV",
   "group": "named-projects",
   "metric": "Developed capacity for Bitcoin mining",
   "category": "Riot Corsicana",
   "value": 400,
   "unit": "MW (developed capacity)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-09-30",
   "source_id": "RIOT",
   "source_title": "Riot Platforms Form 10-Q, quarter ended Sept. 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1167419/000110465926122417/riot-20260930x10q.htm",
   "locator": "Item 2 / business overview",
   "note": ""
  },
  {
   "id": "NP-RIOT-FULL",
   "group": "named-projects",
   "metric": "Expected developed capacity on completion",
   "category": "Riot Corsicana",
   "value": 1000,
   "unit": "MW (approximately)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-09-30",
   "source_id": "RIOT",
   "source_title": "Riot Platforms Form 10-Q, quarter ended Sept. 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1167419/000110465926122417/riot-20260930x10q.htm",
   "locator": "Item 2",
   "note": ""
  },
  {
   "id": "NP-RIOT-Sep",
   "group": "riot-delivery",
   "metric": "Corsicana lease delivery schedule, critical IT capacity",
   "category": "September 2027",
   "value": 400,
   "unit": "MW (critical IT)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-11-04",
   "source_id": "RIOT8K",
   "source_title": "Riot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1167419/000110465926122368/riot-ex99d1.htm",
   "locator": "Delivery Schedule bullet",
   "note": "Critical IT capacity is not metered grid demand"
  },
  {
   "id": "NP-RIOT-Jan",
   "group": "riot-delivery",
   "metric": "Corsicana lease delivery schedule, critical IT capacity",
   "category": "January 2028",
   "value": 200,
   "unit": "MW (critical IT)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-11-04",
   "source_id": "RIOT8K",
   "source_title": "Riot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1167419/000110465926122368/riot-ex99d1.htm",
   "locator": "Delivery Schedule bullet",
   "note": "Critical IT capacity is not metered grid demand"
  },
  {
   "id": "NP-RIOT-Jul",
   "group": "riot-delivery",
   "metric": "Corsicana lease delivery schedule, critical IT capacity",
   "category": "July 2028",
   "value": 310,
   "unit": "MW (critical IT)",
   "population_or_basis": "Company-reported",
   "as_of": "2026-11-04",
   "source_id": "RIOT8K",
   "source_title": "Riot Platforms third-quarter 2026 results release (Form 8-K Exhibit 99.1)",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1167419/000110465926122368/riot-ex99d1.htm",
   "locator": "Delivery Schedule bullet",
   "note": "Critical IT capacity is not metered grid demand"
  },
  {
   "id": "NRG-415",
   "group": "nrg-gas",
   "metric": "NRG Texas gas plant capacity",
   "category": "T.H. Wharton peaker (operating since May 26, 2026)",
   "value": 415,
   "unit": "MW (company-described)",
   "population_or_basis": "Operating",
   "as_of": "2026-09-30",
   "source_id": "NRG",
   "source_title": "NRG Energy Form 10-Q, quarter ended Sept. 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1013871/000101387126000025/nrg-20260930.htm",
   "locator": "Glossary; Texas Energy Fund discussion",
   "note": "No verified link to any data-center load"
  },
  {
   "id": "NRG-689",
   "group": "nrg-gas",
   "metric": "NRG Texas gas plant capacity",
   "category": "Cedar Bayou 5 (under construction)",
   "value": 689,
   "unit": "MW (company-described)",
   "population_or_basis": "Under construction",
   "as_of": "2026-09-30",
   "source_id": "NRG",
   "source_title": "NRG Energy Form 10-Q, quarter ended Sept. 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1013871/000101387126000025/nrg-20260930.htm",
   "locator": "Glossary; Texas Energy Fund discussion",
   "note": "No verified link to any data-center load"
  },
  {
   "id": "NRG-443",
   "group": "nrg-gas",
   "metric": "NRG Texas gas plant capacity",
   "category": "Greens Bayou 6 (under construction)",
   "value": 443,
   "unit": "MW (company-described)",
   "population_or_basis": "Under construction",
   "as_of": "2026-09-30",
   "source_id": "NRG",
   "source_title": "NRG Energy Form 10-Q, quarter ended Sept. 30, 2026",
   "source_url": "https://www.sec.gov/Archives/edgar/data/1013871/000101387126000025/nrg-20260930.htm",
   "locator": "Glossary; Texas Energy Fund discussion",
   "note": "No verified link to any data-center load"
  },
  {
   "id": "SEC-75",
   "group": "security-illustration",
   "metric": "Intermediate financial security at $50,000 per MW (arithmetic illustration)",
   "category": "75 MW requested",
   "value": 3.75,
   "unit": "US$ million",
   "population_or_basis": "Adopted 16 TAC §25.194; 2026 value",
   "as_of": "2026-10-08",
   "source_id": "RULE",
   "source_title": "16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026",
   "source_url": "https://www.sos.state.tx.us/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html",
   "locator": "§25.194 intermediate agreement financial security",
   "note": "Illustration only; applicability, credits and later obligations are project-specific"
  },
  {
   "id": "SEC-100",
   "group": "security-illustration",
   "metric": "Intermediate financial security at $50,000 per MW (arithmetic illustration)",
   "category": "100 MW requested",
   "value": 5.0,
   "unit": "US$ million",
   "population_or_basis": "Adopted 16 TAC §25.194; 2026 value",
   "as_of": "2026-10-08",
   "source_id": "RULE",
   "source_title": "16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026",
   "source_url": "https://www.sos.state.tx.us/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html",
   "locator": "§25.194 intermediate agreement financial security",
   "note": "Illustration only; applicability, credits and later obligations are project-specific"
  },
  {
   "id": "SEC-500",
   "group": "security-illustration",
   "metric": "Intermediate financial security at $50,000 per MW (arithmetic illustration)",
   "category": "500 MW requested",
   "value": 25.0,
   "unit": "US$ million",
   "population_or_basis": "Adopted 16 TAC §25.194; 2026 value",
   "as_of": "2026-10-08",
   "source_id": "RULE",
   "source_title": "16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026",
   "source_url": "https://www.sos.state.tx.us/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html",
   "locator": "§25.194 intermediate agreement financial security",
   "note": "Illustration only; applicability, credits and later obligations are project-specific"
  },
  {
   "id": "SEC-1000",
   "group": "security-illustration",
   "metric": "Intermediate financial security at $50,000 per MW (arithmetic illustration)",
   "category": "1,000 MW requested",
   "value": 50.0,
   "unit": "US$ million",
   "population_or_basis": "Adopted 16 TAC §25.194; 2026 value",
   "as_of": "2026-10-08",
   "source_id": "RULE",
   "source_title": "16 TAC §25.194, Large Load Interconnection Standards, adopted (PUCT Project No. 58481), Texas Register Oct. 2, 2026",
   "source_url": "https://www.sos.state.tx.us/texreg/archive/October22026/Adopted%20Rules/16.ECONOMIC%20REGULATION.html",
   "locator": "§25.194 intermediate agreement financial security",
   "note": "Illustration only; applicability, credits and later obligations are project-specific"
  },
  {
   "id": "LTLF-2029",
   "group": "forecast",
   "metric": "2026 preliminary long-term load forecast, peak",
   "category": "2029",
   "value": 278003,
   "unit": "MW",
   "population_or_basis": "TSP-provided forecast before ERCOT adjustment",
   "as_of": "2026-05-18",
   "source_id": "MNB",
   "source_title": "Market Notice M-B051826-01, Proposal to Adjust 2026 Long-Term Load Forecast",
   "source_url": "https://www.ercot.com/services/comm/mkt_notices/M-B051826-01",
   "locator": "Long description",
   "note": ""
  },
  {
   "id": "LTLF-2032",
   "group": "forecast",
   "metric": "2026 preliminary long-term load forecast, peak",
   "category": "2032",
   "value": 367790,
   "unit": "MW",
   "population_or_basis": "TSP-provided forecast before ERCOT adjustment",
   "as_of": "2026-05-18",
   "source_id": "MNB",
   "source_title": "Market Notice M-B051826-01, Proposal to Adjust 2026 Long-Term Load Forecast",
   "source_url": "https://www.ercot.com/services/comm/mkt_notices/M-B051826-01",
   "locator": "Long description",
   "note": ""
  }
 ]
}