The short version. ERCOT told a Texas Senate committee on July 29, 2026 that, as of June 2026, it was tracking about 474 gigawatts (GW) of requests from large electricity users seeking to connect to its grid, and that about 90% of that capacity was from data centers. Its June 18 news release had cited more than 438 GW, nearly 89% from data centers. Those are requests, not demand on the grid. For its first batch study, known as Batch Zero, ERCOT conditionally included 191.8 GW across 362 large loads as of Sept. 3, 2026, and excluded 302.2 GW across 373 projects; final inclusion depends on a verification review that is still under way. ERCOT expects to send follow-up questions to 80% of data center developers in that review and to report to the Public Utility Commission of Texas (PUCT) on Dec. 10, 2026. ERCOT told its board in September that it had paused approvals to energize new data centers and crypto mining facilities of 75 MW or more until that review and a separate community impact review are complete. In one ERCOT planning review in Central Texas, the Muscovy and Voss Lake project, the option ERCOT recommended and its board endorsed in June is estimated at $1.457 billion, compared with $381.83 million originally submitted; the larger scope includes upgrades also listed in another Oncor project. The PUCT rule on how transmission costs are allocated, part of its work to carry out Senate Bill 6 (2025), was still a proposal as of Nov. 10, 2026, and Power Hopper found no public record that shows what, if anything, the three transmission projects in this article would add to household electricity bills.

Four counts, four different groups
The large-load numbers in circulation this year measure different things. They come from different dates and cover different projects, so one cannot be subtracted from another to measure growth or cancellations.
- About 474 GW, June 2026. All large-load interconnection requests ERCOT was tracking, as reported to the Texas Senate Committee on Business and Commerce on July 29. ERCOT said about 90% were data centers. Its June 18 release, issued when the PUCT approved the Batch Zero process, cited more than 438 GW and nearly 89%.
- 191.8 GW, Sept. 3. Large loads ERCOT conditionally included in Batch Zero (362 projects, including 66.4 GW across 204 projects as base load), as reported to the PUCT on Sept. 11 and to ERCOT's board on Sept. 14-15. Final inclusion depends on ERCOT's verification review.
- About 293 GW, Sept. 30. Data center requests in Oncor's transmission queue for large commercial and industrial customers, as reported by Oncor. This is one utility's queue.
- 177.4 GW, Nov. 5. Requested capacity for 429 loads that answered ERCOT's data center survey and were reviewed for a preliminary summary.
The Batch Zero screen
Batch Zero is ERCOT's first group study of large loads under a process the PUCT approved in June. In the July 28 screen, ERCOT counted 65 GW as eligible base load, 114 GW as eligible allocated load and 25 GW as eligible with the type still to be determined. Another 294 GW was not included: 274 GW with no qualifying study and 20 GW without a dynamic model by July 10. ERCOT's slide values are rounded and add to 498 GW.

By project count, ERCOT's slide lists 315 projects with no qualifying study and 47 with no dynamic model; by Power Hopper's count of ERCOT's categories, that is 362 of 688 listed projects (52.6%) not included, and 326 preliminarily eligible. Not being included reflects study readiness on that date. It does not mean a project was canceled. Eligibility was preliminary and subject to later review. ERCOT's Sept. 3 conditional classification superseded this screen. ERCOT conditionally included 362 large loads totaling 191.8 GW (204 projects and 66.4 GW as base load; 158 projects and 125.4 GW as studied load) and excluded 373 projects totaling 302.2 GW. ERCOT said the numbers could change through dispute processes and the eligibility verification.
What the data center survey shows
ERCOT sent a state and community impact survey to 465 data center and crypto mining loads. By Nov. 5, 417 had answered on time, 16 had answered late and 32 medium-sized loads (under 75 MW) had not answered; all 245 large loads (75 MW or more) responded. ERCOT's preliminary summary of 429 reviewed loads, presented at the PUCT's Nov. 5 open meeting, covers 177.4 GW of requested peak capacity.
- Location. West load zone requests total 73 GW (41%), followed by South at 49 GW, North at 45 GW and Houston at 10 GW. Zones are assigned from facility coordinates, and ERCOT noted that 37 loads are near a zone boundary.
- Size. 33 requests of 1 GW or more account for 64.5 GW, about 36% of the total. Requests under 75 MW account for 11.3 GW across 186 loads.
- Timing. 169 facilities requested energization before 2028 and 260 in January 2028 or later. Requested dates are developer milestones, not ERCOT approvals.
- Function. Facilities reporting no cryptocurrency mining account for 175.9 GW. Facilities reporting some or all mining account for 1.5 GW.



Verification is not finished
On Aug. 3, 2026, ERCOT said in a market notice that it had received a letter from Gov. Greg Abbott directing it to conduct a verification process before advancing any data center large loads through the interconnection process. ERCOT told its board in September that it had also paused approvals to energize data centers and crypto mining facilities of 75 MW or more until the verification and a separate community impact review are complete. ERCOT began issuing first-round verification requests for information on Sept. 9. In a Nov. 5 update, ERCOT said its staff and outside counsel had reviewed responses from 257 developers, about 5,140 questions, and that it expected to send tailored second-round requests to 80% of developers, with five business days to respond.
ERCOT described several "emerging, recurring issues" while stressing that its review was not complete. They include missing documentation of affiliate relationships, inability to demonstrate site control, long-lead equipment timing and "difficulty confirming the amount of financial security posted." These are issues ERCOT listed in general. They are not findings about any named project. ERCOT is due to file its verification report with the PUCT on Dec. 10, 2026.

What large-load customers must post
The PUCT adopted a new large-load interconnection rule, 16 Texas Administrative Code §25.194, published in the Texas Register on Oct. 2, 2026 and effective Oct. 8. It applies to new or expanded loads of 75 MW or more. Before being included in an ERCOT interconnection study, a customer must sign an intermediate agreement and post financial security of $50,000 per MW. A 500 MW request, for example, would post $25 million. At the later standard agreement stage, the security is the greater of $50,000 per MW of contracted demand or the system upgrade costs allocated to the customer in a study. The rule also sets terms for withdrawals and for returning security once a load energizes.

Security is posted by the customer and can be returned or forfeited under the rule. It is not a cost charged to other customers. Oncor reported on Nov. 5 that it held about $6.0 billion of customer collateral for active generation and large commercial and industrial interconnection requests as of Sept. 30, about $2.0 billion of it related to Batch Zero large-load projects. Oncor said the collateral is "intended to reduce the risk of rate payers bearing costs for projects that are cancelled."

Upgrade estimates for three large-load projects
ERCOT's Regional Planning Group reviews major transmission projects proposed to serve new load. Three recent reviews involve large loads. The ERCOT documents for these projects describe them as large-load or reliability projects and do not identify the loads as data centers.
- Muscovy and Voss Lake (Oncor and LCRA TSC). ERCOT's recommended option is estimated at about $1.457 billion, compared with $381.83 million in the original submittal. ERCOT's board materials break the estimate into $388.94 million for the updated initial project, $603.33 million of upgrades that also appear in another Oncor project (25RPG041) and $465.20 million of additional upgrades. The project addresses reliability needs in Williamson and Milam counties in Central Texas. ERCOT's Technical Advisory Committee endorsed it May 19, 2026, and the ERCOT Board endorsed Option 7A at its June 1-2, 2026 meeting, according to the board's draft minutes. ERCOT's review modeled about 600 MW of new Oncor load and 3,573 MW of LCRA TSC load in 2029.
- Southeast Brownsville (South Texas Electric Cooperative). ERCOT recommended the cooperative's proposed option at about $96.6 million, compared with about $96.35 million submitted. ERCOT's study found it could serve about 564 MW of additional load.
- Medina (South Texas Electric Cooperative). The cooperative submitted a $492 million project in December 2025 to address reliability concerns from about 1 GW of new load, with a June 2031 in-service date. ERCOT folded its review into a separate CPS Energy large-load review, and no ERCOT estimate had been published by Nov. 10.


These figures are planning estimates. An ERCOT recommendation or board endorsement is not a cost approved for recovery in rates. Projects that need a certificate of convenience and necessity go to the PUCT separately.
Who pays is still being decided
In July 2026, the PUCT proposed changes to how transmission costs are assigned in ERCOT (Project No. 58000), to implement part of Senate Bill 6 (2025). The proposal would replace the current method, based on each utility's load at the four summer monthly peaks (4CP), with one based on all 12 monthly peaks (12CP). It would also require a minimum billing demand for large-load customers, start their billing when service becomes available, and use fees and forfeited security collected under §25.194 to offset utility revenue requirements. As of Nov. 10, it was a proposal, not a final rule; the project's PUCT filings list comments through Oct. 1, 2026 and no adoption order. The §25.194 interconnection rule described above, also adopted to carry out Senate Bill 6, is final.
Calculating any effect on household bills from a specific grid project would take at least five records: a final cost-allocation rule, an approved project cost, the payments and security from the developers involved, a utility rate filing that allocates the cost to customer classes, and residential billing determinants. Power Hopper did not find all of these public for any of the three projects above as of Nov. 10, 2026. For that reason, this article does not estimate a household bill effect. A research package prepared for Power Hopper included a hypothetical household calculation; we removed it because no record supports its inputs.

The supply side
ERCOT's generator interconnection queue and its January 2027 resource adequacy outlook are on our data page. Generation requests, like large-load requests, are not built capacity, and the two queues cannot be netted against each other.
Company megawatts are not grid demand
Companies with Texas data center campuses describe size in different ways. IREN reports gross planned power of 1,400 MW for Sweetwater 1, 600 MW for Sweetwater 2 and 750 MW for Childress. Riot Platforms reports about 400 MW of developed capacity at Corsicana, used today for Bitcoin mining, and a lease for 910 MW of critical IT capacity there scheduled from September 2027 to July 2028. Planned power, developed capacity and critical IT capacity are different measures, and none of them is metered use of the grid. IREN says 2 GW of its Sweetwater hub was conditionally included in Batch Zero as base load; ERCOT had not published final Batch Zero results by Nov. 10.

What the records do not show
- How much of the requested load will be built. Requests, eligibility and survey responses are not forecasts of demand. ERCOT's verification report and final Batch Zero results were not public as of Nov. 10.
- A reconciled data-center total. ERCOT's July 29 slide labels 420,812 MW, or 90.2%, of large-load requests as data centers, but that share implies a smaller base than the slide's 474.7 GW total, and ERCOT did not reconcile the two. Power Hopper found no newer ERCOT total as of Nov. 10.
- Which projects are data centers. ERCOT's 2026 documents for the three transmission reviews above describe large loads without naming the load type.
- Bill effects. No public record reviewed shows a household bill effect from any project in this article. Cost allocation and large-load tariffs are still in rulemaking.
- Cause and effect. The records do not show whether data center demand caused any specific upgrade, price change or reliability event.
How we did this
We started from a two-part research package prepared for Power Hopper and re-checked each figure on Nov. 10, 2026 against primary records: ERCOT board, planning, PUCT-meeting and legislative presentations, ERCOT board minutes, ERCOT market notices, ERCOT's October 2026 generator interconnection workbook (where we computed totals by fuel and year), the January 2027 resource adequacy outlook, the Texas Register, PUCT filings, and company SEC filings. Of 111 claims and chart figures, 75 were verified as written (3 of them superseded figures shown as history), 13 are attributed to the company or agency that reported them, 18 were corrected and 5 were cut. The package's charts were redrawn from the checked data. The full dataset, with each figure's source and page, is on our data page.
Sources.
- ERCOT, news release on PUCT approval of the Batch Zero process (June 18, 2026).
- ERCOT, update to the Texas Senate Committee on Business and Commerce (July 29, 2026; slide 6, data as of June 2026).
- ERCOT, update to the Texas House Committee on State Affairs (Aug. 19, 2026; slide 3, data as of July 28, 2026); ERCOT, Board item 14, Batch Zero Update (Sept. 14-15, 2026; slides 1-6); ERCOT, ERCOT Updates presentation, PUCT open meeting (PUCT Project No. 59142, Item 55; filed Sept. 11, 2026; Batch Zero eligibility overview slide).
- ERCOT, Data Center State and Community Impact RFI: Preliminary Summary (PUCT open meeting Nov. 5, 2026; slides 2-9).
- ERCOT, Batch Zero Eligibility Verification Process Update (Nov. 5, 2026), and Market Notices M-A080326-01 (Aug. 3, 2026) and M-A090926-01 (Sept. 9, 2026).
- Texas Register, adopted 16 TAC §25.194 (PUCT Project No. 58481; Oct. 2, 2026) and proposed amendments to §§25.192-25.193 and new §25.252 (PUCT Project No. 58000; July 24, 2026); PUCT Interchange filing lists for Project No. 58000 and Project No. 58481 (read Nov. 10, 2026).
- Oncor Electric Delivery, third-quarter 2026 results release (SEC Form 8-K, Exhibit 99.1; Nov. 5, 2026).
- ERCOT, Board item 5.3, 25RPG009 Muscovy and Voss Lake project (May 22, 2026); Southeast Brownsville EIR recommendation (RPG May 11, 2026); Medina EIR scope (RPG Feb. 2, 2026); RPG meeting, July 21, 2026; Board draft minutes, June 1-2, 2026 (posted Sept. 8, 2026, Agenda Item 5.3).
- IREN, Form 10-K for fiscal 2026 and Q1 FY27 results (Nov. 5, 2026); Riot Platforms, Form 10-Q and results release (Nov. 4, 2026).
Customers of most city-owned utilities and electric cooperatives in Texas cannot choose a different electricity provider. If you live where retail choice is available, you can compare plans with Power Hopper. Power Hopper is a PUCT-registered broker, BR260201; electricity providers may pay us a commission if you sign up through us. BJW Ventures LLC is paid by the retail electric provider, or by an enrollment platform that is paid by that provider, if you enroll through a path that pays us a commission; you are not charged a broker fee by us.
Power Hopper is not affiliated with or endorsed by the PUCT, ERCOT, the Office of the Texas Governor, the Texas Secretary of State, the Texas House Committee on State Affairs, the Texas Senate Committee on Business and Commerce, the U.S. Securities and Exchange Commission, Oncor Electric Delivery, LCRA Transmission Services Corporation, South Texas Electric Cooperative, CPS Energy, NRG Energy, IREN, Riot Platforms, or any other company, cooperative, utility, project or developer named in this article.
Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility, and is not affiliated with or endorsed by the PUCT, ERCOT or any utility, supplier or data provider named above. This brief was prepared with AI assistance.