Power Plant Financing · Source-checked

Texas Energy Fund loans and grants: awards, disbursements and plant status

The state's awards ledger shows about $2.08 billion of $4.11 billion in Texas Energy Fund generation loans disbursed as of Nov. 2, 2026. Completion bonus grants are paid only after plants complete yearly performance periods, and Outside ERCOT grant payments had reached about $0.2 million. Loan principal, completion-grant maximums and Outside ERCOT grant selections are different kinds of money and are shown separately.

Download CSVDownload JSON Read the article

$2.08B of $4.11B

Texas Energy Fund generation loans disbursed as of Nov. 2, 2026 (state awards ledger)

2025 to Nov 10, 2026 (ledger tables last updated Nov 2, 2026 and June 26, 2026)

Takeaway

  • The state's awards ledger shows about $2.08 billion of $4.11 billion in Texas Energy Fund generation loans disbursed as of Nov. 2, 2026. Completion bonus grants are paid only after plants complete yearly performance periods, and Outside ERCOT grant payments had reached about $0.2 million. Loan principal, completion-grant maximums and Outside ERCOT grant selections are different kinds of money and are shown separately.

Article: Texas Energy Fund has disbursed $2.08 billion of $4.11 billion in power plant loans; two of nine plants are in commercial operation

Data

In-ERCOT Generation Loans (9): award is maximum principal; disbursed is the ledger's amount expended
ProjectCountySponsorLoan awardedDisbursed (ledger)Ledger as ofAnnounced MWEIA status, Sept 2026
CPV Basin Ranch Energy CenterWardCompetitive Power Ventures (OPC Energy affiliate); state ledger recipient is "Competitive Power Ventures and GE Vernova"$1,124.8M$430.8M2026-11-021,350Under construction; 50% or less complete
Vast Sands PowerWardVistra Corp.$583.3M$234.9M2026-11-02860Under construction; 50% or less complete
Cedar Bayou 5ChambersNRG Energy, Inc.$561.9M$385.5M2026-11-02721Under construction; 50% or less complete
Tolivar Power Plant (Pecos Power Plant)ReevesJointly owned by affiliates of Mercuria Energy Group and Continental Resources (Latham & Watkins, Oct. 20, 2026; Governor release Oct. 7, 2026)$459.2M$245.0M2026-11-02452No matching EIA row located; absence is not cancellation
Rayburn Energy Station IIGraysonRayburn Electric Cooperative$411.0M$44.6M2026-11-02570No EIA-860M planned/operating match located; absence is not cancellation
Greens Bayou 6HarrisNRG Energy, Inc.$370.0M$213.5M2026-11-02455Under construction; 50% or less complete
Pin Oak Creek Energy CenterFreestoneCalpine / Constellation Energy$278.3M$273.9M2026-11-02460Operating
NRG T.H. Wharton GT Electric Generating StationHarrisNRG Energy, Inc.$215.6M$210.9M2026-11-02456Operating
Rock Island Generation ProjectColoradoKerrville Public Utility Board$105.0M$38.8M2026-11-02122Regulatory approvals pending; not under construction
Completion Bonus Grant agreements (5): maximum grant over the agreement term, paid yearly after performance periods
ProjectRecipientMaximum grantPaid (ledger)Ledger as ofEIA status, Sept 2026
Timmerman Power Plant Unit 1Lower Colorado River Authority$22.6M$0.0M2026-06-26Operating
Timmerman Power Plant Phase 2Lower Colorado River Authority$22.6M$0.0M2026-06-26Operating
Friendswood Energy Center expansionTejas Power Generation LLC$17.5M$0.0M2026-06-26Operating
Pin Oak Creek Energy CenterCalpine / Pin Oak Creek Energy Center LLC$55.2M$0.0M2026-06-26Operating
T.H. Wharton expansionNRG THW GT LLC$54.7M$0.0M2026-06-26Operating
Outside ERCOT Grant Program selected project lines (29): transmission and distribution upgrades, no generating capacity
RecipientProject linePUCT selectionAgreement amountPaid (ledger)Status
Southwestern Electric Power CompanySWEPCO Texas Small Copper Wire Reliability and Resiliency Upgrades Project$200.0M$200.0M$0.0MExecuted 2026-06-03
El Paso Electric CompanyAPP-381 priority 1 (title not in PUCT order)$17.7MSelected only (no agreement on ledger)
El Paso Electric CompanyAPP-381 priority 2 (title not in PUCT order)$43.5MSelected only (no agreement on ledger)
El Paso Electric CompanyAPP-381 priority 3 (title not in PUCT order)$58.6MSelected only (no agreement on ledger)
El Paso Electric CompanyAPP-381 priority 7 (title not in PUCT order)$2.6MSelected only (no agreement on ledger)
North Plains Electric Cooperative115kV Transmission Loop$20.4M$20.4M$0.0MExecuted 2026-06-23
North Plains Electric CooperativeOchiltree Interchange Expansion$1.9M$1.9M$0.0MExecuted 2026-06-23
Entergy Texas, Inc.ETI Electric Transmission and Distribution Infrastructure Hardening$197.2M$197.2M$0.0MExecuted 2026-06-15
Entergy Texas, Inc.ETI Substation Control Houses Fortification Against Flooding$2.5M$2.5M$0.0MExecuted 2026-06-15
Sam Houston Electric CooperativeOperation Steel Anchor$87.0M$73.0M$0.0MExecuted 2026-06-02
East Texas Electric CooperativeAPP-404 priority 1 (title not in PUCT order)$21.3MWithdrawn 2026-08-27
East Texas Electric CooperativeAPP-404 priority 2 (title not in PUCT order)$30.2MWithdrawn 2026-08-27
East Texas Electric CooperativeAPP-404 priority 4 (title not in PUCT order)$43.3MWithdrawn 2026-08-27
Bailey County Electric CooperativeTransmission Pole Top Conversion$7.5M$7.5M$0.0MExecuted 2026-08-04
Bailey County Electric CooperativePV Substation to Switch 71$0.6M$0.6M$0.0MExecuted 2026-08-04
Greenbelt Electric CooperativeWildfire Mitigation Through Downline SCADA Controlled Devices$2.4M$2.3M$0.0MExecuted 2026-06-23
Rita Blanca Electric CooperativeOutage Defender$29.9M$29.9M$0.2MExecuted 2026-06-29
Rita Blanca Electric Cooperative, Inc.APP-408 priority 1 (title not in PUCT order)$20.0MSelected only (no agreement on ledger)
Deaf Smith Electric CooperativeSystem Improvement for Substation Feeders$0.8M$0.8M$0.0MExecuted 2026-08-18
Lamb County Electric CooperativeHart Camp Transmission Line Rebuild$3.2M$3.2M$0.0MExecuted 2026-06-25
Lamb County Electric CooperativePettit Transmission Line Rebuild$1.8M$1.8M$0.0MExecuted 2026-06-25
Lamb County Electric CooperativeOpdyke Substation Upgrade$3.0M$3.0M$0.0MExecuted 2026-06-25
Lamb County Electric CooperativeSubstation High Side Switches$0.8M$0.8M$0.0MExecuted 2026-06-25
Southwestern Public Service CompanyOverhead Pole Assessment$81.3M$70.0M$0.0MExecuted 2026-06-30
Southwestern Public Service CompanyEnhanced Power Safety Settings$42.1M$20.3M$0.0MExecuted 2026-06-30
Southwestern Public Service CompanyNon-Traditional Fault Location$25.1M$22.8M$0.0MExecuted 2026-06-30
Golden Spread Electric CooperativeAPP-388 priority 2 (title not in PUCT order)$11.4MSelected only (no agreement on ledger)
Golden Spread Electric CooperativeAPP-388 priority 4 (title not in PUCT order)$4.9MSelected only (no agreement on ledger)
Golden Spread Electric CooperativeAPP-470 priority 4 (title not in PUCT order)$3.3MSelected only (no agreement on ledger)

Charts

Power Plant Financing · As of Nov 2, 2026

About $2.08 billion of $4.11 billion in Texas Energy Fund loans had been disbursed by Nov. 2, 2026

Nine executed In-ERCOT Generation Loans. Award is the maximum loan principal; disbursed is the state's 'amount expended' as of Nov. 2, 2026. Millions of dollars.

  • Loan awarded
  • Disbursed to date
CPV Basin Ranch (Ward Co.)
Vistra Permian Power / Vast Sands (Ward Co.)
NRG Cedar Bayou 5 (Chambers Co.)
Pecos Power Plant / Tolivar (Reeves Co.)
Rayburn Energy Station II (Grayson Co.)
NRG Greens Bayou 6 (Harris Co.)
Calpine Pin Oak Creek (Freestone Co.)
NRG T.H. Wharton GT (Harris Co.)
Kerrville PUB Rock Island (Colorado Co.)

Millions of dollars

Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026). Loans are repayable at 3% fixed interest over 20 years where terms are public; terms for the Pecos loan were not located. The ledger's stated total disbursed is $2,077,942,275.67; its rows sum to one cent more.

Chart: Texas Energy Fund In-ERCOT loans: amount awarded and amount disbursed, by project · Methodology for Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Texas Energy Fund In-ERCOT loans: amount awarded and amount disbursed, by project." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loans-awarded-vs-disbursed-by-project-2026. Accessed [date accessed].

Data table
Texas Energy Fund In-ERCOT loans: amount awarded and amount disbursed, by project (Millions of dollars)
ProjectLoan awardedDisbursed to date
CPV Basin Ranch (Ward Co.)$1,125M$431M
Vistra Permian Power / Vast Sands (Ward Co.)$583M$235M
NRG Cedar Bayou 5 (Chambers Co.)$562M$386M
Pecos Power Plant / Tolivar (Reeves Co.)$459M$245M
Rayburn Energy Station II (Grayson Co.)$411M$45M
NRG Greens Bayou 6 (Harris Co.)$370M$214M
Calpine Pin Oak Creek (Freestone Co.)$278M$274M
NRG T.H. Wharton GT (Harris Co.)$216M$211M
Kerrville PUB Rock Island (Colorado Co.)$105M$39M

Power Plant Financing · As of Nov 2, 2026

Texas Energy Fund amounts under agreement and amounts paid, by program, as of Nov. 2, 2026

Amounts under executed agreements on the state awards ledger and amounts the state reports as expended. Loans are repayable; grants are maximums. Millions of dollars.

  • Under executed agreements
  • Paid / disbursed to date
In-ERCOT generation loans (9)
Completion bonus grants (5)
Outside ERCOT grants, executed (18)

Millions of dollars

Source: Texas Energy Fund (PUCT) awards ledger, read Nov. 10, 2026. Loan and Outside ERCOT tables last updated Nov. 2, 2026; completion bonus grant table last updated June 26, 2026. Completion bonus grants are paid in annual installments over 10 years, only after a plant completes a performance period; the ledger showed $0 paid as of June 26, 2026. Outside ERCOT grant payments total $197,250.24. Unlike amounts: do not add the three programs together.

Chart: Texas Energy Fund: amounts under executed agreements and amounts paid, by program · Methodology for Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Texas Energy Fund: amounts under executed agreements and amounts paid, by program." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-committed-vs-paid-by-program-2026. Accessed [date accessed].

Data table
Texas Energy Fund: amounts under executed agreements and amounts paid, by program (Millions of dollars)
ProgramUnder executed agreementsPaid / disbursed to date
In-ERCOT generation loans (9)$4,109M$2,078M
Completion bonus grants (5)$173M$0M
Outside ERCOT grants, executed (18)$658M$0.2M

Power Plant Financing · EIA-860M, September 2026

Two of nine Texas Energy Fund loan projects are in commercial operation: 821.4 MW of 5,446 MW announced

Announced MW from state announcements and the awards ledger; operating MW is EIA nameplate capacity in the September 2026 generator inventory (EIA-860M).

  • Announced MW
  • EIA operating nameplate MW (Sept. 2026)
CPV Basin Ranch (Ward Co.)
Vistra Permian Power / Vast Sands (Ward Co.)
NRG Cedar Bayou 5 (Chambers Co.)
Rayburn Energy Station II (Grayson Co.)
Calpine Pin Oak Creek (Freestone Co.)
NRG T.H. Wharton GT (Harris Co.)
NRG Greens Bayou 6 (Harris Co.)
Pecos Power Plant / Tolivar (Reeves Co.)
Kerrville PUB Rock Island (Colorado Co.)

Megawatts (MW)

Sources: Texas Energy Fund (PUCT) awards ledger and Office of the Texas Governor releases (announced MW); U.S. EIA, Form EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026 (released Oct. 23, 2026). Announced MW and EIA nameplate MW are different measures; EIA nameplate at Wharton (377.4 MW) and Pin Oak (444 MW) is lower than the 456 MW and 460 MW announced. Zero means no EIA operating record, not a cancellation.

Chart: Texas Energy Fund loan projects: announced capacity and capacity EIA lists as operating · Methodology for Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Texas Energy Fund loan projects: announced capacity and capacity EIA lists as operating." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loan-projects-announced-vs-operating-mw-2026. Accessed [date accessed].

Data table
Texas Energy Fund loan projects: announced capacity and capacity EIA lists as operating (Megawatts (MW))
ProjectAnnounced MWEIA operating nameplate MW (Sept. 2026)
CPV Basin Ranch (Ward Co.)1,350 MW0 MW
Vistra Permian Power / Vast Sands (Ward Co.)860 MW0 MW
NRG Cedar Bayou 5 (Chambers Co.)721 MW0 MW
Rayburn Energy Station II (Grayson Co.)570 MW0 MW
Calpine Pin Oak Creek (Freestone Co.)460 MW444 MW
NRG T.H. Wharton GT (Harris Co.)456 MW377.4 MW
NRG Greens Bayou 6 (Harris Co.)455 MW0 MW
Pecos Power Plant / Tolivar (Reeves Co.)452 MW0 MW
Kerrville PUB Rock Island (Colorado Co.)122 MW0 MW

Power Plant Financing · As of Nov 2, 2026

Three sponsors hold 69.5% of Texas Energy Fund loan dollars

Total loan awards by project sponsor, nine executed loans totaling $4.11 billion. NRG's three projects: 27.9%; NRG plus CPV: 55.3%. Millions of dollars.

NRG Energy
CPV (OPC Energy) / GE Vernova
Vistra
Pecos (Mercuria / Continental affiliates)
Rayburn Country Electric Cooperative
Calpine (Constellation)
Kerrville Public Utility Board

Millions of dollars

Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026). Sponsor grouping by Power Hopper from state releases and SEC filings. Calpine is now part of Constellation Energy. Loan concentration describes who borrowed; it does not imply anything about the merits of any award.

Chart: Texas Energy Fund In-ERCOT loan awards by sponsor · Methodology for Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Texas Energy Fund In-ERCOT loan awards by sponsor." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loan-awards-by-sponsor-2026. Accessed [date accessed].

Data table
Texas Energy Fund In-ERCOT loan awards by sponsor (Millions of dollars)
SponsorLoan awards
NRG Energy$1,147M
CPV (OPC Energy) / GE Vernova$1,125M
Vistra$583M
Pecos (Mercuria / Continental affiliates)$459M
Rayburn Country Electric Cooperative$411M
Calpine (Constellation)$278M
Kerrville Public Utility Board$105M

Power Plant Financing · EIA-860M, September 2026

Seven of nine Texas Energy Fund loan projects were not yet operating in EIA's September 2026 inventory

Count of projects by EIA-860M status. No announced target date had passed without operation as of Nov. 10, 2026.

  1. 2OperatingNRG T.H. Wharton GT (EIA: May 2026) and Calpine Pin Oak Creek (EIA: April 2026). 821.4 MW nameplate.
  2. 4Under construction, 50% or less completeCedar Bayou 5, Greens Bayou 6, CPV Basin Ranch, Vast Sands (Vistra). Planned dates May 2027 to Feb. 2029.
  3. 1Approvals pending, not under constructionRock Island (Kerrville PUB). EIA planned Sept. 2027; state release and ERCOT June 1, 2027.
  4. 2No EIA planned-generator recordRayburn Energy Station II and Pecos/Tolivar. Both are in ERCOT's interconnection report with 2027-2028 dates.

Sources: U.S. EIA Form EIA-860M, September 2026; ERCOT Generator Interconnection Status report, October 2026; Office of the Texas Governor releases. EIA, ERCOT and company target dates differ for several projects. The public record does not include each loan's contractual completion deadlines.

Chart: Status of the nine Texas Energy Fund loan projects in EIA's September 2026 inventory · Methodology for Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Status of the nine Texas Energy Fund loan projects in EIA's September 2026 inventory." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loan-projects-status-eia-2026. Accessed [date accessed].

Data table
Status of the nine Texas Energy Fund loan projects in EIA's September 2026 inventory
StepCountNote
Operating2NRG T.H. Wharton GT (EIA: May 2026) and Calpine Pin Oak Creek (EIA: April 2026). 821.4 MW nameplate.
Under construction, 50% or less complete4Cedar Bayou 5, Greens Bayou 6, CPV Basin Ranch, Vast Sands (Vistra). Planned dates May 2027 to Feb. 2029.
Approvals pending, not under construction1Rock Island (Kerrville PUB). EIA planned Sept. 2027; state release and ERCOT June 1, 2027.
No EIA planned-generator record2Rayburn Energy Station II and Pecos/Tolivar. Both are in ERCOT's interconnection report with 2027-2028 dates.

Power Plant Financing · As of Nov 10, 2026

Of 29 Outside ERCOT grant lines the PUCT selected in 2025, 18 had signed agreements by Nov. 2, 2026

PUCT selected 29 lines totaling $964.5 million in four 2025 orders. Status on the state awards ledger and PUCT docket as of Nov. 10, 2026.

  1. 18Executed grant agreements$658.0 million in awards; $197,250.24 paid. Some awards are below the selected amount.
  2. 8Selected, no agreement on the ledger$162.1 million selected: El Paso Electric (4), Golden Spread (3), Rita Blanca (1).
  3. 3Selected, then withdrawn$94.7 million: East Texas Electric Cooperative withdrew its joint applications on Aug. 27, 2026 to refile by member.

Sources: PUCT Project No. 58492, staff memos and orders (items 3-10) and ETEC withdrawal statement (item 11); Texas Energy Fund awards ledger, Outside ERCOT table last updated Nov. 2, 2026. Outside ERCOT grants fund transmission and distribution upgrades outside the ERCOT grid; they do not add generating capacity.

Chart: Outside ERCOT Grant Program: 29 selected project lines by agreement status · Methodology for Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Outside ERCOT Grant Program: 29 selected project lines by agreement status." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-outside-ercot-grants-status-2026. Accessed [date accessed].

Data table
Outside ERCOT Grant Program: 29 selected project lines by agreement status
StepCountNote
Executed grant agreements18$658.0 million in awards; $197,250.24 paid. Some awards are below the selected amount.
Selected, no agreement on the ledger8$162.1 million selected: El Paso Electric (4), Golden Spread (3), Rita Blanca (1).
Selected, then withdrawn3$94.7 million: East Texas Electric Cooperative withdrew its joint applications on Aug. 27, 2026 to refile by member.

More charts and share cards

Power Plant Financing · Additional charts

Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98%

Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).

Chart: Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98% · Methodology for Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98% · CC BY 4.0

Cite this chart

Power Hopper Team. "Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98%." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-share-disbursed-by-project-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026

Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).

Chart: About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026 · Methodology for About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loans-disbursed-and-not-yet-disbursed-by-project-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026

Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).

Chart: Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026 · Methodology for Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-cumulative-loan-awards-by-agreement-date-2025-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026

Source: Texas Energy Fund (PUCT) awards ledger, completion bonus grant table last updated June 26, 2026 (read Nov. 10, 2026).

Chart: Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026 · Methodology for Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-completion-bonus-grants-by-plant-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced

Sources: Texas Energy Fund awards ledger and Office of the Texas Governor releases (announced MW); U.S. EIA Form EIA-860M, September 2026.

Chart: All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced · Methodology for All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced · CC BY 4.0

Cite this chart

Power Hopper Team. "All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-completion-bonus-grant-plants-announced-vs-eia-mw-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements

Source: Texas Energy Fund (PUCT) awards ledger, Outside ERCOT table last updated Nov. 2, 2026; PUCT Project No. 58492 (items 3-11).

Chart: Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements · Methodology for Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements · CC BY 4.0

Cite this chart

Power Hopper Team. "Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-outside-ercot-grant-awards-by-utility-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn

Source: Texas Energy Fund (PUCT) awards ledger, Outside ERCOT table last updated Nov. 2, 2026; PUCT Project No. 58492 (items 3-11).

Chart: Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn · Methodology for Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn · CC BY 4.0

Cite this chart

Power Hopper Team. "Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-outside-ercot-grant-dollars-by-status-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026

Source: U.S. EIA Form EIA-923, 2026 data through August (preliminary).

Chart: The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026 · Methodology for The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026 · CC BY 4.0

Cite this chart

Power Hopper Team. "The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-plants-net-generation-jan-aug-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans

Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).

Chart: Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans · Methodology for Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans · CC BY 4.0

Cite this chart

Power Hopper Team. "Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-awards-by-county-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion

Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).

Chart: All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion · Methodology for All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion · CC BY 4.0

Cite this chart

Power Hopper Team. "All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-awards-by-plant-technology-2026. Accessed [date accessed].

Power Plant Financing · Additional charts

Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans

Sources: Texas Energy Fund awards ledger (In-ERCOT table, Nov. 2, 2026); NRG, Vistra and Constellation Forms 10-Q for Q3 2026.

Chart: Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans · Methodology for Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans · CC BY 4.0

Cite this chart

Power Hopper Team. "Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-draws-state-ledger-vs-company-filings-2026. Accessed [date accessed].

Share cards

Stat card: $2.08B. of $4.11 billion in Texas Energy Fund loans disbursed. 50.6% of the maximum principal on nine executed In-ERCOT Generation Loans, as of Nov. 2, 2026.

Key-number card · 1200 × 675 px

$2.08B: of $4.11 billion in Texas Energy Fund loans disbursed

Source: Texas Energy Fund (PUCT) awards ledger, In-ERCOT table updated Nov. 2, 2026.

Download PNG of $2.08B: of $4.11 billion in Texas Energy Fund loans disbursed WebP of $2.08B: of $4.11 billion in Texas Energy Fund loans disbursed JPG of $2.08B: of $4.11 billion in Texas Energy Fund loans disbursed

Stat card: $2.08B. of $4.11 billion in Texas Energy Fund loans disbursed. 50.6% of the maximum principal on nine executed In-ERCOT Generation Loans, as of Nov. 2, 2026.

Social square · 1080 × 1080 px

$2.08B: of $4.11 billion in Texas Energy Fund loans disbursed

Source: Texas Energy Fund (PUCT) awards ledger, In-ERCOT table updated Nov. 2, 2026.

Download PNG of $2.08B: of $4.11 billion in Texas Energy Fund loans disbursed WebP of $2.08B: of $4.11 billion in Texas Energy Fund loans disbursed JPG of $2.08B: of $4.11 billion in Texas Energy Fund loans disbursed

Stat card: 2 of 9. Texas Energy Fund loan plants in commercial operation. NRG T.H. Wharton GT and Calpine Pin Oak Creek. Seven were not yet operating in EIA's September 2026 inventory.

Key-number card · 1200 × 675 px

2 of 9: Texas Energy Fund loan plants in commercial operation

Sources: Texas Energy Fund awards ledger; U.S. EIA Form EIA-860M, September 2026.

Download PNG of 2 of 9: Texas Energy Fund loan plants in commercial operation WebP of 2 of 9: Texas Energy Fund loan plants in commercial operation JPG of 2 of 9: Texas Energy Fund loan plants in commercial operation

Stat card: 2 of 9. Texas Energy Fund loan plants in commercial operation. NRG T.H. Wharton GT and Calpine Pin Oak Creek. Seven were not yet operating in EIA's September 2026 inventory.

Social square · 1080 × 1080 px

2 of 9: Texas Energy Fund loan plants in commercial operation

Sources: Texas Energy Fund awards ledger; U.S. EIA Form EIA-860M, September 2026.

Download PNG of 2 of 9: Texas Energy Fund loan plants in commercial operation WebP of 2 of 9: Texas Energy Fund loan plants in commercial operation JPG of 2 of 9: Texas Energy Fund loan plants in commercial operation

Stat card: 821.4 MW. EIA operating nameplate at Texas Energy Fund loan plants. Of 5,446 MW announced for the nine loan projects (15.1%). Announced MW and EIA nameplate are different measures.

Key-number card · 1200 × 675 px

821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants

Sources: Texas Energy Fund awards ledger and Governor releases; U.S. EIA Form EIA-860M, September 2026.

Download PNG of 821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants WebP of 821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants JPG of 821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants

Stat card: 821.4 MW. EIA operating nameplate at Texas Energy Fund loan plants. Of 5,446 MW announced for the nine loan projects (15.1%). Announced MW and EIA nameplate are different measures.

Social square · 1080 × 1080 px

821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants

Sources: Texas Energy Fund awards ledger and Governor releases; U.S. EIA Form EIA-860M, September 2026.

Download PNG of 821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants WebP of 821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants JPG of 821.4 MW: EIA operating nameplate at Texas Energy Fund loan plants

Stat card: 69.5%. of Texas Energy Fund loan principal awarded is for projects of three sponsors. NRG 27.9%, CPV (OPC Energy) and GE Vernova 27.4%, and Vistra 14.2% of $4.11 billion in loan principal.

Key-number card · 1200 × 675 px

69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors

Source: Texas Energy Fund (PUCT) awards ledger, In-ERCOT table updated Nov. 2, 2026.

Download PNG of 69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors WebP of 69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors JPG of 69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors

Stat card: 69.5%. of Texas Energy Fund loan principal awarded is for projects of three sponsors. NRG 27.9%, CPV (OPC Energy) and GE Vernova 27.4%, and Vistra 14.2% of $4.11 billion in loan principal.

Social square · 1080 × 1080 px

69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors

Source: Texas Energy Fund (PUCT) awards ledger, In-ERCOT table updated Nov. 2, 2026.

Download PNG of 69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors WebP of 69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors JPG of 69.5%: of Texas Energy Fund loan principal awarded is for projects of three sponsors

Stat card: $0. paid on $172.56 million in Texas Energy Fund completion bonus grants. Five executed grant agreements; grants are paid in annual installments over 10 years after a performance period. Ledger as of June 26, 2026.

Key-number card · 1200 × 675 px

$0: paid on $172.56 million in Texas Energy Fund completion bonus grants

Source: Texas Energy Fund (PUCT) awards ledger, completion bonus grant table last updated June 26, 2026 (read Nov. 10, 2026).

Download PNG of $0: paid on $172.56 million in Texas Energy Fund completion bonus grants WebP of $0: paid on $172.56 million in Texas Energy Fund completion bonus grants JPG of $0: paid on $172.56 million in Texas Energy Fund completion bonus grants

Stat card: $0. paid on $172.56 million in Texas Energy Fund completion bonus grants. Five executed grant agreements; grants are paid in annual installments over 10 years after a performance period. Ledger as of June 26, 2026.

Social square · 1080 × 1080 px

$0: paid on $172.56 million in Texas Energy Fund completion bonus grants

Source: Texas Energy Fund (PUCT) awards ledger, completion bonus grant table last updated June 26, 2026 (read Nov. 10, 2026).

Download PNG of $0: paid on $172.56 million in Texas Energy Fund completion bonus grants WebP of $0: paid on $172.56 million in Texas Energy Fund completion bonus grants JPG of $0: paid on $172.56 million in Texas Energy Fund completion bonus grants

Stat card: 18 of 29. Outside ERCOT grant lines selected in 2025 that have signed agreements. $658.0 million under executed agreements; $197,250.24 paid as of Nov. 2, 2026. 3 of the 29 lines were later withdrawn; 8 have no agreement on the ledger.

Key-number card · 1200 × 675 px

18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements

Source: Texas Energy Fund (PUCT) awards ledger, Outside ERCOT table last updated Nov. 2, 2026; PUCT Project No. 58492 (items 3-11).

Download PNG of 18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements WebP of 18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements JPG of 18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements

Stat card: 18 of 29. Outside ERCOT grant lines selected in 2025 that have signed agreements. $658.0 million under executed agreements; $197,250.24 paid as of Nov. 2, 2026. 3 of the 29 lines were later withdrawn; 8 have no agreement on the ledger.

Social square · 1080 × 1080 px

18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements

Source: Texas Energy Fund (PUCT) awards ledger, Outside ERCOT table last updated Nov. 2, 2026; PUCT Project No. 58492 (items 3-11).

Download PNG of 18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements WebP of 18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements JPG of 18 of 29: Outside ERCOT grant lines selected in 2025 that have signed agreements

Methodology

  1. Awards and payments. Copied from the Texas Energy Fund awards page. That page loads its tables with JavaScript, so we saved a rendered copy on Nov. 10, 2026. The In-ERCOT loan and Outside ERCOT tables were last updated Nov. 2, 2026; the completion bonus grant table was last updated June 26, 2026.
  2. Selections and eligibility. Taken from PUCT staff memos and orders in Project Nos. 57937 (completion bonus grants) and 58492 (Outside ERCOT). Withdrawals and extensions come from Project Nos. 56896 and 58492.
  3. Plant status. Each loan project was matched by plant and generator to EIA's Preliminary Monthly Electric Generator Inventory (September 2026) and ERCOT's Generator Interconnection Status report (October 2026). Generation comes from EIA-923 2026 monthly data through August. The most recent months are preliminary.
  4. Company filings. Draws and balances reported in Q3 2026 SEC filings are shown alongside the ledger. They are not used for totals.
  5. Totals. Each program is summed on its own basis. Shares use loan principal only. The disbursed total is the ledger's stated total ($2,077,942,275.67); the row sum is $0.01 higher because of rounding.

Full methodology

Limitations

  • Loan principal is repayable at 3% where terms are public. It is a loan, not a grant. Completion grants are paid only after completion and over time. Outside ERCOT grants fund wires work, not generation.
  • Outside ERCOT lines withdrawn by East Texas Electric Cooperative on Aug. 27, 2026 are shown with status "Withdrawn" and are excluded from executed and pending totals; ETEC said its members would resubmit standalone applications.
  • Contractual completion deadlines and loan amendments are not public. The records do not show whether any project is on or off schedule against its loan terms.
  • The completion bonus grant table had not been updated since June 26, 2026.
  • Announced, EIA nameplate, EIA net summer and ERCOT MW differ by source and are labeled.
  • The data do not measure effects on reliability, prices or bills.

Data dictionary

FieldDescription
record_idPower Hopper record ID (program prefix + application ID, plus line suffix for Outside ERCOT lines)
programIn-ERCOT Generation Loan / Completion Bonus Grant / Outside ERCOT Grant
record_typeExecuted loan or grant agreement, selected with no agreement on the ledger, or selected then withdrawn
application_idTexas Energy Fund application number
recipientLoan or grant recipient as named on the awards ledger
sponsor_or_parentSponsor or parent company (Power Hopper grouping from state releases and SEC filings)
projectProject name
countyCounty (loan and completion grant projects)
technologyGenerating technology
amount_usdAmount, USD; basis in amount_basis (loan: maximum principal; CBG: maximum grant over the agreement term; OEGP: executed agreement amount, blank if no agreement)
amount_basisWhat amount_usd measures
amount_sourceWhere amount_usd was read, with table and last-updated date
puct_eligibility_or_selection_usdPUCT eligibility notice (CBG) or selection order amount (OEGP), USD
award_or_selection_dateAward, agreement or selection date
state_ledger_expended_usdThe Texas Energy Fund ledger's "amount expended", USD
state_ledger_as_ofLast-updated date of the ledger table read
sec_filing_draw_or_balance_usdCompany-reported draw or balance, USD (attributed; dates differ; not used for totals)
sec_filing_basisFiling, date and basis of the company-reported figure
interest_rate_pctLoan interest rate, % (where terms are public)
loan_term_yearsLoan term, years (where terms are public)
announced_mwAnnounced capacity, MW (state or sponsor)
unique_mw_in_analysisMW counted once in Power Hopper totals
eia_plant_idEIA plant ID
eia_generator_idsEIA generator IDs matched
eia_status_sep2026EIA-860M status, September 2026
eia_operating_nameplate_mwEIA operating nameplate capacity, MW
eia_operating_net_summer_mwEIA operating net summer capacity, MW
eia_operating_monthEIA operating month
eia_planned_nameplate_mwEIA planned nameplate capacity, MW
eia_planned_operationEIA planned operation month
eia923_net_generation_jan_aug_2026_mwhEIA-923 net generation, January-August 2026, MWh (recent months preliminary)
ercot_inrERCOT interconnection request number
ercot_mwCapacity in ERCOT's Generator Interconnection Status report (October 2026), MW
ercot_projected_codDeveloper-projected commercial operation date in ERCOT's report
public_targetAnnounced in-service target (state or company)
objectiveOutside ERCOT grant objective
agreement_statusAgreement status on the ledger or PUCT docket
notesNotes
sourcesSource codes for the record (semicolon-separated)

Power Hopper is not affiliated with or endorsed by the PUCT, the Texas Energy Fund, the Office of the Texas Governor, ERCOT, the U.S. Energy Information Administration, any loan or grant recipient or sponsor listed in this dataset (including NRG Energy, Competitive Power Ventures, OPC Energy, GE Vernova, Vistra, Pecos Power Plant LLC, Mercuria, Continental Resources, Rayburn Electric Cooperative, Calpine, Constellation Energy, the Kerrville Public Utility Board, LCRA, Tejas Power Generation and Shell Energy North America, and every utility and electric cooperative named in the Outside ERCOT records), or any other company, project or plant named on this page.

Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility, and is not affiliated with or endorsed by the PUCT, ERCOT or any utility, supplier or data provider named above. This brief was prepared with AI assistance.