Power Plant Financing · Source-checked
Texas Energy Fund loans and grants: awards, disbursements and plant status
The state's awards ledger shows about $2.08 billion of $4.11 billion in Texas Energy Fund generation loans disbursed as of Nov. 2, 2026. Completion bonus grants are paid only after plants complete yearly performance periods, and Outside ERCOT grant payments had reached about $0.2 million. Loan principal, completion-grant maximums and Outside ERCOT grant selections are different kinds of money and are shown separately.
$2.08B of $4.11B
Texas Energy Fund generation loans disbursed as of Nov. 2, 2026 (state awards ledger)
Takeaway
- The state's awards ledger shows about $2.08 billion of $4.11 billion in Texas Energy Fund generation loans disbursed as of Nov. 2, 2026. Completion bonus grants are paid only after plants complete yearly performance periods, and Outside ERCOT grant payments had reached about $0.2 million. Loan principal, completion-grant maximums and Outside ERCOT grant selections are different kinds of money and are shown separately.
Data
| Project | County | Sponsor | Loan awarded | Disbursed (ledger) | Ledger as of | Announced MW | EIA status, Sept 2026 |
|---|---|---|---|---|---|---|---|
| CPV Basin Ranch Energy Center | Ward | Competitive Power Ventures (OPC Energy affiliate); state ledger recipient is "Competitive Power Ventures and GE Vernova" | $1,124.8M | $430.8M | 2026-11-02 | 1,350 | Under construction; 50% or less complete |
| Vast Sands Power | Ward | Vistra Corp. | $583.3M | $234.9M | 2026-11-02 | 860 | Under construction; 50% or less complete |
| Cedar Bayou 5 | Chambers | NRG Energy, Inc. | $561.9M | $385.5M | 2026-11-02 | 721 | Under construction; 50% or less complete |
| Tolivar Power Plant (Pecos Power Plant) | Reeves | Jointly owned by affiliates of Mercuria Energy Group and Continental Resources (Latham & Watkins, Oct. 20, 2026; Governor release Oct. 7, 2026) | $459.2M | $245.0M | 2026-11-02 | 452 | No matching EIA row located; absence is not cancellation |
| Rayburn Energy Station II | Grayson | Rayburn Electric Cooperative | $411.0M | $44.6M | 2026-11-02 | 570 | No EIA-860M planned/operating match located; absence is not cancellation |
| Greens Bayou 6 | Harris | NRG Energy, Inc. | $370.0M | $213.5M | 2026-11-02 | 455 | Under construction; 50% or less complete |
| Pin Oak Creek Energy Center | Freestone | Calpine / Constellation Energy | $278.3M | $273.9M | 2026-11-02 | 460 | Operating |
| NRG T.H. Wharton GT Electric Generating Station | Harris | NRG Energy, Inc. | $215.6M | $210.9M | 2026-11-02 | 456 | Operating |
| Rock Island Generation Project | Colorado | Kerrville Public Utility Board | $105.0M | $38.8M | 2026-11-02 | 122 | Regulatory approvals pending; not under construction |
| Project | Recipient | Maximum grant | Paid (ledger) | Ledger as of | EIA status, Sept 2026 |
|---|---|---|---|---|---|
| Timmerman Power Plant Unit 1 | Lower Colorado River Authority | $22.6M | $0.0M | 2026-06-26 | Operating |
| Timmerman Power Plant Phase 2 | Lower Colorado River Authority | $22.6M | $0.0M | 2026-06-26 | Operating |
| Friendswood Energy Center expansion | Tejas Power Generation LLC | $17.5M | $0.0M | 2026-06-26 | Operating |
| Pin Oak Creek Energy Center | Calpine / Pin Oak Creek Energy Center LLC | $55.2M | $0.0M | 2026-06-26 | Operating |
| T.H. Wharton expansion | NRG THW GT LLC | $54.7M | $0.0M | 2026-06-26 | Operating |
| Recipient | Project line | PUCT selection | Agreement amount | Paid (ledger) | Status |
|---|---|---|---|---|---|
| Southwestern Electric Power Company | SWEPCO Texas Small Copper Wire Reliability and Resiliency Upgrades Project | $200.0M | $200.0M | $0.0M | Executed 2026-06-03 |
| El Paso Electric Company | APP-381 priority 1 (title not in PUCT order) | $17.7M | Selected only (no agreement on ledger) | ||
| El Paso Electric Company | APP-381 priority 2 (title not in PUCT order) | $43.5M | Selected only (no agreement on ledger) | ||
| El Paso Electric Company | APP-381 priority 3 (title not in PUCT order) | $58.6M | Selected only (no agreement on ledger) | ||
| El Paso Electric Company | APP-381 priority 7 (title not in PUCT order) | $2.6M | Selected only (no agreement on ledger) | ||
| North Plains Electric Cooperative | 115kV Transmission Loop | $20.4M | $20.4M | $0.0M | Executed 2026-06-23 |
| North Plains Electric Cooperative | Ochiltree Interchange Expansion | $1.9M | $1.9M | $0.0M | Executed 2026-06-23 |
| Entergy Texas, Inc. | ETI Electric Transmission and Distribution Infrastructure Hardening | $197.2M | $197.2M | $0.0M | Executed 2026-06-15 |
| Entergy Texas, Inc. | ETI Substation Control Houses Fortification Against Flooding | $2.5M | $2.5M | $0.0M | Executed 2026-06-15 |
| Sam Houston Electric Cooperative | Operation Steel Anchor | $87.0M | $73.0M | $0.0M | Executed 2026-06-02 |
| East Texas Electric Cooperative | APP-404 priority 1 (title not in PUCT order) | $21.3M | Withdrawn 2026-08-27 | ||
| East Texas Electric Cooperative | APP-404 priority 2 (title not in PUCT order) | $30.2M | Withdrawn 2026-08-27 | ||
| East Texas Electric Cooperative | APP-404 priority 4 (title not in PUCT order) | $43.3M | Withdrawn 2026-08-27 | ||
| Bailey County Electric Cooperative | Transmission Pole Top Conversion | $7.5M | $7.5M | $0.0M | Executed 2026-08-04 |
| Bailey County Electric Cooperative | PV Substation to Switch 71 | $0.6M | $0.6M | $0.0M | Executed 2026-08-04 |
| Greenbelt Electric Cooperative | Wildfire Mitigation Through Downline SCADA Controlled Devices | $2.4M | $2.3M | $0.0M | Executed 2026-06-23 |
| Rita Blanca Electric Cooperative | Outage Defender | $29.9M | $29.9M | $0.2M | Executed 2026-06-29 |
| Rita Blanca Electric Cooperative, Inc. | APP-408 priority 1 (title not in PUCT order) | $20.0M | Selected only (no agreement on ledger) | ||
| Deaf Smith Electric Cooperative | System Improvement for Substation Feeders | $0.8M | $0.8M | $0.0M | Executed 2026-08-18 |
| Lamb County Electric Cooperative | Hart Camp Transmission Line Rebuild | $3.2M | $3.2M | $0.0M | Executed 2026-06-25 |
| Lamb County Electric Cooperative | Pettit Transmission Line Rebuild | $1.8M | $1.8M | $0.0M | Executed 2026-06-25 |
| Lamb County Electric Cooperative | Opdyke Substation Upgrade | $3.0M | $3.0M | $0.0M | Executed 2026-06-25 |
| Lamb County Electric Cooperative | Substation High Side Switches | $0.8M | $0.8M | $0.0M | Executed 2026-06-25 |
| Southwestern Public Service Company | Overhead Pole Assessment | $81.3M | $70.0M | $0.0M | Executed 2026-06-30 |
| Southwestern Public Service Company | Enhanced Power Safety Settings | $42.1M | $20.3M | $0.0M | Executed 2026-06-30 |
| Southwestern Public Service Company | Non-Traditional Fault Location | $25.1M | $22.8M | $0.0M | Executed 2026-06-30 |
| Golden Spread Electric Cooperative | APP-388 priority 2 (title not in PUCT order) | $11.4M | Selected only (no agreement on ledger) | ||
| Golden Spread Electric Cooperative | APP-388 priority 4 (title not in PUCT order) | $4.9M | Selected only (no agreement on ledger) | ||
| Golden Spread Electric Cooperative | APP-470 priority 4 (title not in PUCT order) | $3.3M | Selected only (no agreement on ledger) |
Charts
Power Plant Financing · As of Nov 2, 2026
About $2.08 billion of $4.11 billion in Texas Energy Fund loans had been disbursed by Nov. 2, 2026
Nine executed In-ERCOT Generation Loans. Award is the maximum loan principal; disbursed is the state's 'amount expended' as of Nov. 2, 2026. Millions of dollars.
- Loan awarded
- Disbursed to date
Millions of dollars

Chart image 2,400 × 1,848 px, with headline, source and credit
Download PNG of Texas Energy Fund In-ERCOT loans: amount awarded and amount disbursed, by project WebP of Texas Energy Fund In-ERCOT loans: amount awarded and amount disbursed, by project SVG of Texas Energy Fund In-ERCOT loans: amount awarded and amount disbursed, by project
Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026). Loans are repayable at 3% fixed interest over 20 years where terms are public; terms for the Pecos loan were not located. The ledger's stated total disbursed is $2,077,942,275.67; its rows sum to one cent more.
Cite this chart
Power Hopper Team. "Texas Energy Fund In-ERCOT loans: amount awarded and amount disbursed, by project." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loans-awarded-vs-disbursed-by-project-2026. Accessed [date accessed].
Data table
| Project | Loan awarded | Disbursed to date |
|---|---|---|
| CPV Basin Ranch (Ward Co.) | $1,125M | $431M |
| Vistra Permian Power / Vast Sands (Ward Co.) | $583M | $235M |
| NRG Cedar Bayou 5 (Chambers Co.) | $562M | $386M |
| Pecos Power Plant / Tolivar (Reeves Co.) | $459M | $245M |
| Rayburn Energy Station II (Grayson Co.) | $411M | $45M |
| NRG Greens Bayou 6 (Harris Co.) | $370M | $214M |
| Calpine Pin Oak Creek (Freestone Co.) | $278M | $274M |
| NRG T.H. Wharton GT (Harris Co.) | $216M | $211M |
| Kerrville PUB Rock Island (Colorado Co.) | $105M | $39M |
Power Plant Financing · As of Nov 2, 2026
Texas Energy Fund amounts under agreement and amounts paid, by program, as of Nov. 2, 2026
Amounts under executed agreements on the state awards ledger and amounts the state reports as expended. Loans are repayable; grants are maximums. Millions of dollars.
- Under executed agreements
- Paid / disbursed to date
Millions of dollars

Chart image 2,400 × 1,568 px, with headline, source and credit
Download PNG of Texas Energy Fund: amounts under executed agreements and amounts paid, by program WebP of Texas Energy Fund: amounts under executed agreements and amounts paid, by program SVG of Texas Energy Fund: amounts under executed agreements and amounts paid, by program
Source: Texas Energy Fund (PUCT) awards ledger, read Nov. 10, 2026. Loan and Outside ERCOT tables last updated Nov. 2, 2026; completion bonus grant table last updated June 26, 2026. Completion bonus grants are paid in annual installments over 10 years, only after a plant completes a performance period; the ledger showed $0 paid as of June 26, 2026. Outside ERCOT grant payments total $197,250.24. Unlike amounts: do not add the three programs together.
Cite this chart
Power Hopper Team. "Texas Energy Fund: amounts under executed agreements and amounts paid, by program." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-committed-vs-paid-by-program-2026. Accessed [date accessed].
Data table
| Program | Under executed agreements | Paid / disbursed to date |
|---|---|---|
| In-ERCOT generation loans (9) | $4,109M | $2,078M |
| Completion bonus grants (5) | $173M | $0M |
| Outside ERCOT grants, executed (18) | $658M | $0.2M |
Power Plant Financing · EIA-860M, September 2026
Two of nine Texas Energy Fund loan projects are in commercial operation: 821.4 MW of 5,446 MW announced
Announced MW from state announcements and the awards ledger; operating MW is EIA nameplate capacity in the September 2026 generator inventory (EIA-860M).
- Announced MW
- EIA operating nameplate MW (Sept. 2026)
Megawatts (MW)

Chart image 2,400 × 1,848 px, with headline, source and credit
Download PNG of Texas Energy Fund loan projects: announced capacity and capacity EIA lists as operating WebP of Texas Energy Fund loan projects: announced capacity and capacity EIA lists as operating SVG of Texas Energy Fund loan projects: announced capacity and capacity EIA lists as operating
Sources: Texas Energy Fund (PUCT) awards ledger and Office of the Texas Governor releases (announced MW); U.S. EIA, Form EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026 (released Oct. 23, 2026). Announced MW and EIA nameplate MW are different measures; EIA nameplate at Wharton (377.4 MW) and Pin Oak (444 MW) is lower than the 456 MW and 460 MW announced. Zero means no EIA operating record, not a cancellation.
Cite this chart
Power Hopper Team. "Texas Energy Fund loan projects: announced capacity and capacity EIA lists as operating." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loan-projects-announced-vs-operating-mw-2026. Accessed [date accessed].
Data table
| Project | Announced MW | EIA operating nameplate MW (Sept. 2026) |
|---|---|---|
| CPV Basin Ranch (Ward Co.) | 1,350 MW | 0 MW |
| Vistra Permian Power / Vast Sands (Ward Co.) | 860 MW | 0 MW |
| NRG Cedar Bayou 5 (Chambers Co.) | 721 MW | 0 MW |
| Rayburn Energy Station II (Grayson Co.) | 570 MW | 0 MW |
| Calpine Pin Oak Creek (Freestone Co.) | 460 MW | 444 MW |
| NRG T.H. Wharton GT (Harris Co.) | 456 MW | 377.4 MW |
| NRG Greens Bayou 6 (Harris Co.) | 455 MW | 0 MW |
| Pecos Power Plant / Tolivar (Reeves Co.) | 452 MW | 0 MW |
| Kerrville PUB Rock Island (Colorado Co.) | 122 MW | 0 MW |
Power Plant Financing · As of Nov 2, 2026
Three sponsors hold 69.5% of Texas Energy Fund loan dollars
Total loan awards by project sponsor, nine executed loans totaling $4.11 billion. NRG's three projects: 27.9%; NRG plus CPV: 55.3%. Millions of dollars.
Millions of dollars

Chart image 2,400 × 1,696 px, with headline, source and credit
Download PNG of Texas Energy Fund In-ERCOT loan awards by sponsor WebP of Texas Energy Fund In-ERCOT loan awards by sponsor SVG of Texas Energy Fund In-ERCOT loan awards by sponsor
Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026). Sponsor grouping by Power Hopper from state releases and SEC filings. Calpine is now part of Constellation Energy. Loan concentration describes who borrowed; it does not imply anything about the merits of any award.
Cite this chart
Power Hopper Team. "Texas Energy Fund In-ERCOT loan awards by sponsor." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loan-awards-by-sponsor-2026. Accessed [date accessed].
Data table
| Sponsor | Loan awards |
|---|---|
| NRG Energy | $1,147M |
| CPV (OPC Energy) / GE Vernova | $1,125M |
| Vistra | $583M |
| Pecos (Mercuria / Continental affiliates) | $459M |
| Rayburn Country Electric Cooperative | $411M |
| Calpine (Constellation) | $278M |
| Kerrville Public Utility Board | $105M |
Power Plant Financing · EIA-860M, September 2026
Seven of nine Texas Energy Fund loan projects were not yet operating in EIA's September 2026 inventory
Count of projects by EIA-860M status. No announced target date had passed without operation as of Nov. 10, 2026.
- 2OperatingNRG T.H. Wharton GT (EIA: May 2026) and Calpine Pin Oak Creek (EIA: April 2026). 821.4 MW nameplate.
- 4Under construction, 50% or less completeCedar Bayou 5, Greens Bayou 6, CPV Basin Ranch, Vast Sands (Vistra). Planned dates May 2027 to Feb. 2029.
- 1Approvals pending, not under constructionRock Island (Kerrville PUB). EIA planned Sept. 2027; state release and ERCOT June 1, 2027.
- 2No EIA planned-generator recordRayburn Energy Station II and Pecos/Tolivar. Both are in ERCOT's interconnection report with 2027-2028 dates.

Chart image 2,400 × 1,414 px, with headline, source and credit
Download PNG of Status of the nine Texas Energy Fund loan projects in EIA's September 2026 inventory WebP of Status of the nine Texas Energy Fund loan projects in EIA's September 2026 inventory SVG of Status of the nine Texas Energy Fund loan projects in EIA's September 2026 inventory
Sources: U.S. EIA Form EIA-860M, September 2026; ERCOT Generator Interconnection Status report, October 2026; Office of the Texas Governor releases. EIA, ERCOT and company target dates differ for several projects. The public record does not include each loan's contractual completion deadlines.
Cite this chart
Power Hopper Team. "Status of the nine Texas Energy Fund loan projects in EIA's September 2026 inventory." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-loan-projects-status-eia-2026. Accessed [date accessed].
Data table
| Step | Count | Note |
|---|---|---|
| Operating | 2 | NRG T.H. Wharton GT (EIA: May 2026) and Calpine Pin Oak Creek (EIA: April 2026). 821.4 MW nameplate. |
| Under construction, 50% or less complete | 4 | Cedar Bayou 5, Greens Bayou 6, CPV Basin Ranch, Vast Sands (Vistra). Planned dates May 2027 to Feb. 2029. |
| Approvals pending, not under construction | 1 | Rock Island (Kerrville PUB). EIA planned Sept. 2027; state release and ERCOT June 1, 2027. |
| No EIA planned-generator record | 2 | Rayburn Energy Station II and Pecos/Tolivar. Both are in ERCOT's interconnection report with 2027-2028 dates. |
Power Plant Financing · As of Nov 10, 2026
Of 29 Outside ERCOT grant lines the PUCT selected in 2025, 18 had signed agreements by Nov. 2, 2026
PUCT selected 29 lines totaling $964.5 million in four 2025 orders. Status on the state awards ledger and PUCT docket as of Nov. 10, 2026.
- 18Executed grant agreements$658.0 million in awards; $197,250.24 paid. Some awards are below the selected amount.
- 8Selected, no agreement on the ledger$162.1 million selected: El Paso Electric (4), Golden Spread (3), Rita Blanca (1).
- 3Selected, then withdrawn$94.7 million: East Texas Electric Cooperative withdrew its joint applications on Aug. 27, 2026 to refile by member.

Chart image 2,400 × 1,250 px, with headline, source and credit
Download PNG of Outside ERCOT Grant Program: 29 selected project lines by agreement status WebP of Outside ERCOT Grant Program: 29 selected project lines by agreement status SVG of Outside ERCOT Grant Program: 29 selected project lines by agreement status
Sources: PUCT Project No. 58492, staff memos and orders (items 3-10) and ETEC withdrawal statement (item 11); Texas Energy Fund awards ledger, Outside ERCOT table last updated Nov. 2, 2026. Outside ERCOT grants fund transmission and distribution upgrades outside the ERCOT grid; they do not add generating capacity.
Cite this chart
Power Hopper Team. "Outside ERCOT Grant Program: 29 selected project lines by agreement status." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/charts#chart-texas-energy-fund-outside-ercot-grants-status-2026. Accessed [date accessed].
Data table
| Step | Count | Note |
|---|---|---|
| Executed grant agreements | 18 | $658.0 million in awards; $197,250.24 paid. Some awards are below the selected amount. |
| Selected, no agreement on the ledger | 8 | $162.1 million selected: El Paso Electric (4), Golden Spread (3), Rita Blanca (1). |
| Selected, then withdrawn | 3 | $94.7 million: East Texas Electric Cooperative withdrew its joint applications on Aug. 27, 2026 to refile by member. |
More charts and share cards
Power Plant Financing · Additional charts
Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98%

Download PNG of Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98% WebP of Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98% SVG of Share of each Texas Energy Fund loan disbursed as of Nov. 2, 2026 ranges from 11% to 98%
Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).
Cite this chart
Power Plant Financing · Additional charts
About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026

Download PNG of About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026 WebP of About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026 SVG of About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026
Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).
Cite this chart
Power Hopper Team. "About $2.03 billion of Texas Energy Fund loan awards had not yet been disbursed on Nov. 2, 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loans-disbursed-and-not-yet-disbursed-by-project-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026

Download PNG of Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026 WebP of Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026 SVG of Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026
Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).
Cite this chart
Power Hopper Team. "Texas Energy Fund loan agreements reached $4.11 billion with the ninth loan in October 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-cumulative-loan-awards-by-agreement-date-2025-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026

Download PNG of Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026 WebP of Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026 SVG of Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026
Source: Texas Energy Fund (PUCT) awards ledger, completion bonus grant table last updated June 26, 2026 (read Nov. 10, 2026).
Cite this chart
Power Hopper Team. "Five completion bonus grants total up to $172.56 million; none had been paid as of June 26, 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-completion-bonus-grants-by-plant-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced

Download PNG of All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced WebP of All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced SVG of All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced
Sources: Texas Energy Fund awards ledger and Office of the Texas Governor releases (announced MW); U.S. EIA Form EIA-860M, September 2026.
Cite this chart
Power Hopper Team. "All five completion bonus grant plants appear as operating in EIA records; four at lower nameplate MW than announced." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-completion-bonus-grant-plants-announced-vs-eia-mw-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements

Download PNG of Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements WebP of Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements SVG of Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements
Source: Texas Energy Fund (PUCT) awards ledger, Outside ERCOT table last updated Nov. 2, 2026; PUCT Project No. 58492 (items 3-11).
Cite this chart
Power Hopper Team. "Outside ERCOT grants: three utilities hold $513 million of $658 million under signed agreements." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-outside-ercot-grant-awards-by-utility-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn

Download PNG of Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn WebP of Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn SVG of Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn
Source: Texas Energy Fund (PUCT) awards ledger, Outside ERCOT table last updated Nov. 2, 2026; PUCT Project No. 58492 (items 3-11).
Cite this chart
Power Hopper Team. "Outside ERCOT grants: $658 million under signed agreements, $162 million selected without one, $95 million withdrawn." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-outside-ercot-grant-dollars-by-status-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026

Download PNG of The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026 WebP of The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026 SVG of The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026
Source: U.S. EIA Form EIA-923, 2026 data through August (preliminary).
Cite this chart
Power Hopper Team. "The two Texas Energy Fund loan plants in commercial operation generated 464,898 MWh from January to August 2026." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-plants-net-generation-jan-aug-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans

Download PNG of Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans WebP of Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans SVG of Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans
Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).
Cite this chart
Power Hopper Team. "Ward County's two plants account for $1,708 million of the $4.11 billion in Texas Energy Fund loans." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-awards-by-county-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion

Download PNG of All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion WebP of All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion SVG of All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion
Source: Texas Energy Fund (PUCT) awards ledger, txenergyfund.texas.gov/texas-energy-fund-awards, In-ERCOT table last updated Nov. 2, 2026 (read Nov. 10, 2026).
Cite this chart
Power Hopper Team. "All nine Texas Energy Fund loans finance natural gas plants; combustion turbine projects hold $1.86 billion." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-awards-by-plant-technology-2026. Accessed [date accessed].
Power Plant Financing · Additional charts
Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans

Download PNG of Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans WebP of Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans SVG of Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans
Sources: Texas Energy Fund awards ledger (In-ERCOT table, Nov. 2, 2026); NRG, Vistra and Constellation Forms 10-Q for Q3 2026.
Cite this chart
Power Hopper Team. "Company filings and the state ledger agree within $4 million on four Texas Energy Fund loans." Chart. Texas Energy Fund loans and grants: awards, disbursements and plant status, 2025-2026 dataset. Power Hopper Media Data Room, published November 10, 2026. https://powerhopper.energy/media/data/texas-energy-fund-loans-grants#cv2-texas-energy-fund-loan-draws-state-ledger-vs-company-filings-2026. Accessed [date accessed].
Share cards
Methodology
- Awards and payments. Copied from the Texas Energy Fund awards page. That page loads its tables with JavaScript, so we saved a rendered copy on Nov. 10, 2026. The In-ERCOT loan and Outside ERCOT tables were last updated Nov. 2, 2026; the completion bonus grant table was last updated June 26, 2026.
- Selections and eligibility. Taken from PUCT staff memos and orders in Project Nos. 57937 (completion bonus grants) and 58492 (Outside ERCOT). Withdrawals and extensions come from Project Nos. 56896 and 58492.
- Plant status. Each loan project was matched by plant and generator to EIA's Preliminary Monthly Electric Generator Inventory (September 2026) and ERCOT's Generator Interconnection Status report (October 2026). Generation comes from EIA-923 2026 monthly data through August. The most recent months are preliminary.
- Company filings. Draws and balances reported in Q3 2026 SEC filings are shown alongside the ledger. They are not used for totals.
- Totals. Each program is summed on its own basis. Shares use loan principal only. The disbursed total is the ledger's stated total ($2,077,942,275.67); the row sum is $0.01 higher because of rounding.
Limitations
- Loan principal is repayable at 3% where terms are public. It is a loan, not a grant. Completion grants are paid only after completion and over time. Outside ERCOT grants fund wires work, not generation.
- Outside ERCOT lines withdrawn by East Texas Electric Cooperative on Aug. 27, 2026 are shown with status "Withdrawn" and are excluded from executed and pending totals; ETEC said its members would resubmit standalone applications.
- Contractual completion deadlines and loan amendments are not public. The records do not show whether any project is on or off schedule against its loan terms.
- The completion bonus grant table had not been updated since June 26, 2026.
- Announced, EIA nameplate, EIA net summer and ERCOT MW differ by source and are labeled.
- The data do not measure effects on reliability, prices or bills.
Data dictionary
| Field | Description |
|---|---|
record_id | Power Hopper record ID (program prefix + application ID, plus line suffix for Outside ERCOT lines) |
program | In-ERCOT Generation Loan / Completion Bonus Grant / Outside ERCOT Grant |
record_type | Executed loan or grant agreement, selected with no agreement on the ledger, or selected then withdrawn |
application_id | Texas Energy Fund application number |
recipient | Loan or grant recipient as named on the awards ledger |
sponsor_or_parent | Sponsor or parent company (Power Hopper grouping from state releases and SEC filings) |
project | Project name |
county | County (loan and completion grant projects) |
technology | Generating technology |
amount_usd | Amount, USD; basis in amount_basis (loan: maximum principal; CBG: maximum grant over the agreement term; OEGP: executed agreement amount, blank if no agreement) |
amount_basis | What amount_usd measures |
amount_source | Where amount_usd was read, with table and last-updated date |
puct_eligibility_or_selection_usd | PUCT eligibility notice (CBG) or selection order amount (OEGP), USD |
award_or_selection_date | Award, agreement or selection date |
state_ledger_expended_usd | The Texas Energy Fund ledger's "amount expended", USD |
state_ledger_as_of | Last-updated date of the ledger table read |
sec_filing_draw_or_balance_usd | Company-reported draw or balance, USD (attributed; dates differ; not used for totals) |
sec_filing_basis | Filing, date and basis of the company-reported figure |
interest_rate_pct | Loan interest rate, % (where terms are public) |
loan_term_years | Loan term, years (where terms are public) |
announced_mw | Announced capacity, MW (state or sponsor) |
unique_mw_in_analysis | MW counted once in Power Hopper totals |
eia_plant_id | EIA plant ID |
eia_generator_ids | EIA generator IDs matched |
eia_status_sep2026 | EIA-860M status, September 2026 |
eia_operating_nameplate_mw | EIA operating nameplate capacity, MW |
eia_operating_net_summer_mw | EIA operating net summer capacity, MW |
eia_operating_month | EIA operating month |
eia_planned_nameplate_mw | EIA planned nameplate capacity, MW |
eia_planned_operation | EIA planned operation month |
eia923_net_generation_jan_aug_2026_mwh | EIA-923 net generation, January-August 2026, MWh (recent months preliminary) |
ercot_inr | ERCOT interconnection request number |
ercot_mw | Capacity in ERCOT's Generator Interconnection Status report (October 2026), MW |
ercot_projected_cod | Developer-projected commercial operation date in ERCOT's report |
public_target | Announced in-service target (state or company) |
objective | Outside ERCOT grant objective |
agreement_status | Agreement status on the ledger or PUCT docket |
notes | Notes |
sources | Source codes for the record (semicolon-separated) |
Power Hopper is not affiliated with or endorsed by the PUCT, the Texas Energy Fund, the Office of the Texas Governor, ERCOT, the U.S. Energy Information Administration, any loan or grant recipient or sponsor listed in this dataset (including NRG Energy, Competitive Power Ventures, OPC Energy, GE Vernova, Vistra, Pecos Power Plant LLC, Mercuria, Continental Resources, Rayburn Electric Cooperative, Calpine, Constellation Energy, the Kerrville Public Utility Board, LCRA, Tejas Power Generation and Shell Energy North America, and every utility and electric cooperative named in the Outside ERCOT records), or any other company, project or plant named on this page.
Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility, and is not affiliated with or endorsed by the PUCT, ERCOT or any utility, supplier or data provider named above. This brief was prepared with AI assistance.