The short version. By Nov. 2, 2026, the state had disbursed about $2.08 billion of the $4.11 billion it has agreed to lend through nine Texas Energy Fund loans for new natural gas power plants on the ERCOT grid, according to the fund's awards ledger, which the Public Utility Commission of Texas (PUCT) publishes as the program's administrator (In-ERCOT table last updated Nov. 2, 2026). Two of the nine plants are in commercial operation, according to the companies, and are listed as operating by the U.S. Energy Information Administration (EIA). None of the other seven had passed an announced in-service target as of Nov. 10, 2026; those targets run from 2027 to 2029. EIA lists 821.4 megawatts (MW) of operating capacity at those two plants, against 5,446 MW announced for all nine. The fund's two grant programs work differently. Completion bonus grants are paid yearly only after a plant completes a performance period; the ledger showed $0 paid on five agreements worth up to $172.56 million as of its June 26, 2026 update. Under $658.0 million in signed Outside ERCOT grant agreements, $197,250 had been paid by Nov. 2.

Three programs, three kinds of money
The Texas Energy Fund runs three programs. Their dollar amounts measure different things and should not be added together.
- In-ERCOT Generation Loans. These are repayable loans for new gas-fired plants on the ERCOT grid. The nine executed loans total $4,109,114,828.82 in awards, which is the most each borrower can draw. Where terms are public, the loans carry a 3% fixed rate over 20 years. The ledger shows $2,077,942,275.67 disbursed, or 50.6% of the total awarded.
- Completion Bonus Grants. These grants go to new dispatchable plants that connect to the ERCOT grid by set dates. They are paid in yearly installments over 10 years, and only if the plant meets performance tests. NRG says Wharton's first test period runs from June 1, 2026 through May 31, 2027, after which it becomes eligible for a first payment. The state has signed five agreements worth up to $172.56 million in total. The ledger, last updated June 26, 2026, shows $0 paid. Two of the five grants are for the same plants as the operating loans, NRG's T.H. Wharton expansion and Calpine's Pin Oak Creek.
- Outside ERCOT Grants. These grants pay for transmission and distribution upgrades in parts of Texas outside the ERCOT grid, and they do not add generating capacity. In four orders in 2025, the PUCT selected 29 project lines totaling $964,481,390. By Nov. 2, 2026, 18 lines had signed agreements worth $658.0 million, and $197,250.24 had been paid. East Texas Electric Cooperative withdrew its joint applications, covering three selected lines worth $94.7 million, on Aug. 27, 2026. It said its member cooperatives would refile separately. Eight selected lines, worth $162.1 million, had no agreement on the ledger.

Where the loan money went
| Project (county) | Sponsor | Loan awarded | Disbursed by Nov. 2, 2026 | Announced MW | EIA status, Sept. 2026 |
|---|---|---|---|---|---|
| CPV Basin Ranch (Ward) | Competitive Power Ventures (OPC Energy) and GE Vernova, per the state ledger | $1,124.8M | $430.8M | 1,350 | Under construction, 50% or less complete |
| Permian Power / Vast Sands (Ward) | Vistra | $583.3M | $234.9M | 860 | Under construction, 50% or less complete |
| Cedar Bayou 5 (Chambers) | NRG Energy | $561.9M | $385.5M | 721 | Under construction, 50% or less complete |
| Pecos Power Plant / Tolivar (Reeves) | Affiliates of Mercuria and Continental Resources (jointly owned) | $459.2M | $245.0M | 452 | No planned-generator record |
| Rayburn Energy Station II (Grayson) | Rayburn Country Electric Cooperative | $411.0M | $44.6M | 570 | No planned-generator record |
| Greens Bayou 6 (Harris) | NRG Energy | $370.0M | $213.5M | 455 | Under construction, 50% or less complete |
| Pin Oak Creek (Freestone) | Calpine (Constellation Energy) | $278.3M | $273.9M | 460 | Operating since April 2026 |
| T.H. Wharton GT (Harris) | NRG Energy | $215.6M | $210.9M | 456 | Operating since May 2026 |
| Rock Island (Colorado) | Kerrville Public Utility Board | $105.0M | $38.8M | 122 | Regulatory approvals pending, not under construction |
| Total | $4,109.1M | $2,077.9M | 5,446 |
Sources: Texas Energy Fund awards ledger (amounts); Office of the Texas Governor releases and awards ledger (announced MW); EIA Form EIA-860M, September 2026 (status).
NRG's three loans total $1.15 billion, or 27.9% of loan dollars. CPV's Basin Ranch loan is $1.12 billion (27.4%), and Vistra's is $583 million (14.2%). Together, NRG and CPV hold 55.3% of the loan total, and the three largest sponsors hold 69.5%. On average, the loans equal about $754,500 per announced megawatt. That is a measure of loan size, not of what the plants cost to build.

Companies' own filings report draw or balance amounts close to the ledger's, on different dates and bases. NRG's quarterly report says the Wharton loan "has been fully disbursed as of September 30, 2026"; the state ledger, updated Nov. 2, shows $210.9 million disbursed against the $215.6 million award, and the public records do not explain the difference. NRG also reports that $386 million (Cedar Bayou 5) and $214 million (Greens Bayou 6) had been disbursed by Oct. 31. Vistra reported $236 million outstanding on Sept. 30, and Constellation reported $277 million outstanding on the Pin Oak loan.
What is in commercial operation
- T.H. Wharton GT, Houston (NRG). NRG reports commercial operation began May 26, 2026. EIA lists two new combustion turbines totaling 377.4 MW of nameplate capacity (408 MW net summer capacity). NRG describes the plant as 415 MW, and the state's loan announcement used 456 MW.
- Pin Oak Creek, Freestone County (Calpine, now part of Constellation). EIA lists two turbines totaling 444 MW of nameplate capacity (424 MW net summer), operating since April 2026. The Governor's office held an opening event on May 5, 2026, and the state uses 460 MW for the plant.
EIA's monthly generation data show these two plants produced 464,898 megawatt-hours (MWh) from January through August 2026: 88,036 MWh at Wharton's new turbine plant and 376,862 MWh at Pin Oak. Each plant has its own EIA plant ID, and EIA's inventory lists only the new turbines under those IDs. EIA's figures for recent months are preliminary.
EIA's 821.4 MW is 15.1% of the 5,446 MW announced for all nine projects. Using the state's announced figures instead (456 MW and 460 MW), the two operating plants account for 916 MW, or 16.8%. Nameplate capacity is a different measure from the MW figures in state announcements, so both are shown here.

What is still being built
Seven of the nine loan projects were not operating in EIA's September 2026 inventory. Four are under construction and 50% or less complete: Cedar Bayou 5, Greens Bayou 6, CPV Basin Ranch and Vistra's Vast Sands units. Rock Island is listed with regulatory approvals pending and is not under construction. Rayburn Energy Station II and the Pecos plant have no EIA planned-generator record yet. Both are in ERCOT's October 2026 interconnection report, which lists developer-projected commercial operation dates in 2027 (Pecos) and 2028 (Rayburn).

None of the seven had an announced in-service target that had passed as of Nov. 10, 2026. The targets announced by the state and the companies run from June 2027 (Rock Island) to 2029 (Basin Ranch); they are expectations, not commitments in the public record. Dates from different sources do not always agree. For Rock Island, the state release and ERCOT list June 1, 2027, while EIA lists September 2027. For Vistra's units, the state release and ERCOT list 2028, while EIA lists May 2027. For Basin Ranch, ERCOT lists Dec. 1, 2028, while EIA and the state release list 2029. The public record does not include the completion deadlines written into each loan agreement, so the data cannot show whether any project is on schedule under its contract.
Three of the nine borrowers, Rayburn, Vistra (Permian Power I) and the Pecos project, requested and received extensions of the Dec. 31, 2025 statutory deadline for a first loan disbursement. The PUCT approved them in December 2025 under a state law that allows extensions for market factors outside an applicant's control; it approved similar requests from other applicants. All three signed loan agreements before their extended deadlines (June 30, 2026 for Rayburn and Vistra; Dec. 31, 2026 for Pecos). The extensions applied to the first-disbursement deadline, not to plant completion dates; Rayburn and the Pecos project told the PUCT their planned commercial operation dates would not change. NRG requested an extension for Greens Bayou 6 in October 2025 and withdrew the request the next month.
What the records do not show
- Cause and effect. The records do not show whether the loans or grants caused any plant to be built, or how much any plant has changed reliability on the ERCOT grid.
- Contract terms. The executed loan and grant agreements, including their milestones and collateral, are not public in full. Terms for the Pecos loan were not located.
- Real-time payment data. The awards ledger is the state's own summary. Its loan and Outside ERCOT tables were last updated Nov. 2, 2026, and the completion bonus grant table on June 26, 2026. EIA's generator inventory is preliminary.
- Capacity on one basis. State announcements, ERCOT, EIA and companies report different MW figures for several plants. Cedar Bayou 5, for example, is 721 MW in the state ledger and EIA, 697 MW in ERCOT's report and 689 MW in NRG's filing.
How we did this
We started from a research package prepared for Power Hopper and checked each figure against primary records. We used the Texas Energy Fund awards ledger, PUCT dockets 56896, 57937 and 58492, EIA's September 2026 generator inventory and August 2026 generation data, ERCOT's October 2026 interconnection report, state announcements, and company SEC filings. That check corrected several figures in the package: loan disbursements, two loan amounts, three application numbers, the applicant or application number on three Outside ERCOT grant lines, and the priority order of two others. It also added the August 2026 withdrawal of three Outside ERCOT grant lines. The full dataset, with each record's sources, is on our data page.
Sources.
- Texas Energy Fund (PUCT), Texas Energy Fund Awards (In-ERCOT and Outside ERCOT tables last updated Nov. 2, 2026; completion bonus grant table June 26, 2026).
- PUCT, Project No. 56896, Texas Energy Fund In-ERCOT Loan Program (market-factor extension memo and order, items 98 and 99; Greens Bayou 6 extension request and withdrawal, items 84 and 97; Vistra consolidation, items 100 and 102).
- PUCT, Project No. 57937, Completion Bonus Grant Program (items 3-11).
- PUCT, Project No. 58492, Outside ERCOT Grant Program (staff memos and orders, items 3-10; withdrawal statement, item 11).
- U.S. EIA, Preliminary Monthly Electric Generator Inventory (Form EIA-860M), September 2026.
- U.S. EIA, Form EIA-923 monthly generation data, through August 2026.
- ERCOT, Generator Interconnection Status report, October 2026.
- Office of the Texas Governor, Texas Energy Fund loan announcements (Rock Island, T.H. Wharton, Pin Oak, Basin Ranch, Rayburn, Vistra, Pecos) and Pin Oak opening (May 5, 2026).
- NRG Energy, Form 10-Q for the quarter ended Sept. 30, 2026; Vistra, Form 10-Q; Constellation Energy, Form 10-Q.
Customers of most city-owned utilities and electric cooperatives in Texas cannot choose a different electricity provider. If you live where retail choice is available, you can compare plans with Power Hopper. Power Hopper is a PUCT-registered broker, BR260201; electricity providers may pay us a commission if you sign up through us. BJW Ventures LLC is paid by the retail electric provider, or by an enrollment platform that is paid by that provider, if you enroll through a path that pays us a commission; you are not charged a broker fee by us.
Power Hopper is not affiliated with or endorsed by the PUCT, the Texas Energy Fund, the Office of the Texas Governor, ERCOT, the U.S. Energy Information Administration, NRG Energy, Competitive Power Ventures, OPC Energy, GE Vernova, Vistra, Pecos Power Plant LLC, Mercuria, Continental Resources, Rayburn Electric Cooperative, Calpine, Constellation Energy, the Kerrville Public Utility Board, East Texas Electric Cooperative, or any other company, cooperative, utility, project or plant named in this article.
Power Hopper (BJW Ventures LLC d/b/a Power Hopper) is a PUCT-registered electricity broker, BR260201; registration is not a PUCT endorsement. Electricity providers may pay us a commission if you sign up through us. Power Hopper is not a retail electric provider, utility or transmission and distribution utility, and is not affiliated with or endorsed by the PUCT, ERCOT or any utility, supplier or data provider named above. This brief was prepared with AI assistance.